P & C Construction Co. v. American Diversified/Wells Park II

789 P.2d 688, 101 Or. App. 51, 1990 Ore. App. LEXIS 297
CourtCourt of Appeals of Oregon
DecidedMarch 28, 1990
DocketA8708-04908; CA A51058
StatusPublished
Cited by4 cases

This text of 789 P.2d 688 (P & C Construction Co. v. American Diversified/Wells Park II) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P & C Construction Co. v. American Diversified/Wells Park II, 789 P.2d 688, 101 Or. App. 51, 1990 Ore. App. LEXIS 297 (Or. Ct. App. 1990).

Opinion

*53 JOSEPH, C. J.

This is an action for breach of contract and to foreclose a construction lien for labor performed and material supplied by plaintiff in the renovation of the Wells Building in Portland. Defendants American Diversified Capital Corporation, American Diversified/Wells Park II and ADC Financial Corporation (defendants) 1 appeal the lien foreclosure judgment, raising two claims: (1) The judgment should be reduced by $130,087 because of a lien release signed by plaintiff; and (2) they should not be bound to pay pre- and post-judgment interest at the rate of 12 percent stated in the construction contract, because they were not parties to that contract. We review de novo. ORS 19.125(3); McClory v. Gay, 45 Or App 561, 563, 608 P2d 1213 (1980).

In July, 1985, Princeton Portland Investors, Ltd., 2 contracted with plaintiff to act as general contractor for the renovation of the Wells Building. Princeton was the owner of the building when the contract was executed. The building was later sold to defendant American Diversified/Wells Park II. Defendants then collectively became the owner and the financing institution for the project under an agreement with Princeton.

Plaintiffs contract with Princeton provided for a guaranteed maximum cost for the project and a 7 percent contractor’s fee. It was also to receive 25 percent of any cost savings as additional compensation. Plaintiff was to submit applications for payment 3 at the beginning of every month for the costs incurred during the previous month. If approved by the architect, a draw request was to be paid within ten days after the delivery of the request. The contract also provided that unpaid amounts would bear interest at the annual rate of 12 percent. The contract did not specify a particular method or order for applying payments. Although not required by the *54 contract, plaintiff also had to sign lien releases as a condition of being paid.

Construction began on the project sometime after April, 1985. Initially, defendants made payments on draw requests to Princeton, which, in turn, would pay plaintiff. In April, 1986, defendants began making payments directly to plaintiff. However, plaintiff continued to treat Princeton as responsible for payment, and it continued to work with Princeton on the development and construction of the building, as well as with defendants. Defendants ordered changes in the work, met frequently with Princeton and plaintiff and, eventually, became active in the day-to-day activities of the project.

In July, 1986, plaintiff submitted Draw Request No. 14 for work completed through June 30, 1986. The amount of the request was $308,429. On August 22,1986, defendants paid $178,342, which left $130,087 as the unpaid balance on that request. On October 10,1986, plaintiff executed a lien release 4 that said that it had been paid in full for all labor performed and for all materials furnished on the project as of June 30, 1986. Between July 1,1986, when the June draw request was submitted, and October 10,1986, when the release was signed, other draw requests had been submitted and additional payments had been made. Consequently, when the lien release was signed, plaintiff had received, in total, more money than it had billed and was unpaid as of June 30,1986.

After completion of the project in 1987, plaintiff believed that it was owed $592,786 under the contract, plus the cost saving allowance. It sued Princeton for breach of contract for the outstanding balance and sought to foreclose its lien, seeking a judgment in the same amount, plus various costs and *55 attorney fees, with pre- and post-judgment interest at 12 percent per annum. Judgment was entered against Princeton on the breach of contract claim in the amount of $570,367, 5 with 12 percent pre- and post-judgment interest, and against defendants on the lien foreclosure claim in the same amount, plus attorney fees and costs, with 12 percent interest. 6

Defendants’ first assignment of error is that the lien foreclosure judgment improperly included $130,087 for work covered by the October lien release. Defendants argue that, because the release is unambiguous, 7 we must hold that it encompassed lien rights arising from all work performed through June 30, and billed before October 10, whether a particular draw request had been fully paid or not. Defendants contend that, because payments were applied to the request most recently received and approved and because, when plaintiff signed the release, there was an outstanding balance owing on Draw Request No. 14, plaintiff released its lien rights as to that outstanding amount by signing the release. Defendants further argue that, because the language of the release is clear, no evidence should have been admitted to explain plaintiffs intent.

Plaintiff claims that the language of the release is ambiguous, because it does not state how “paid in full” was to be calculated. It says that payments were applied on a cumulative basis, not just to the last request received, so that money paid was applied first to any outstanding balances on earlier requests. It also argues that, because a waiver must be a voluntary and intentional relinquishment of a known right, evidence of what it intended to release was relevant and admissible. See Daly v. Fitch, 70 Or App 18, 687 P2d 1124 (1984); Harris v. Dyer, 50 Or App 223, 623 P2d 662, mod on other basis 292 Or 233, 637 P2d 918 (1981).

A contract provision is unambiguous if the language *56 is “so clear as to preclude doubt by a reasonable person,” but it is ambiguous if the language is “capable of more than one sensible and reasonable interpretation.” Deerfield Commodities v. Nerco, Inc., supra n 7, 72 Or App at 317. Moreover, a lien waiver must be “reasonably clear” about what rights the supplier of materials or labor intended to waive. Nelson v. Cohen, 160 Or 336, 338, 84 P2d 658 (1938). To determine whether a contract is ambiguous, evidence about the surrounding circumstances is admissible to put the judge in the position of the parties to the contract. Deerfield Commodities v. Nerco, Inc., supra.

The construction contract required that plaintiff submit monthly draw requests. The contract also established a guaranteed maximum cost, necessitating that each request be viewed in relation to the anticipated maximum project cost. As the financer, defendants’ focus would tend to be on each request. Each request showed how much had been billed to date and what was being billed that month, while payment checks contained a reference to a particular draw request, whether or not the payment equalled the amount billed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morse Bros. v. Kemp Construction, Inc.
935 P.2d 464 (Court of Appeals of Oregon, 1997)
D & D CO. v. Kaufman
912 P.2d 411 (Court of Appeals of Oregon, 1996)
Trevitts v. Hoffman-Marmolejo
909 P.2d 187 (Court of Appeals of Oregon, 1996)
Biomass One, L.P. v. S-P Construction
852 P.2d 847 (Court of Appeals of Oregon, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
789 P.2d 688, 101 Or. App. 51, 1990 Ore. App. LEXIS 297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-c-construction-co-v-american-diversifiedwells-park-ii-orctapp-1990.