This text of Oregon § 701.420 (Partial payment; retainage; effect; interest; notice of completion; payment by contractor and owner) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 701.420 (2026).

Text

(1)Partial payment is allowed and may be made on contracts for construction and home improvement. An owner, contractor or subcontractor may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed. Partial payment allowed under this subsection is not acceptance or approval of some of the work or a waiver of defects in the work.
(2)The owner, contractor or subcontractor shall pay interest at the rate of one percent per month on the final payment due the contractor or subcontractor. The interest shall commence 30 days after the contractor or subcontractor has completed and the owner has accepted the work under the contract for construction for which the final payment is due. The interest shall run until the date when final payment is t

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P & C Construction Co. v. American Diversified/Wells Park II
789 P.2d 688 (Court of Appeals of Oregon, 1990)
4 case citations

Legislative History

1975 c.772 §2; 2010 c.77 §8; 2013 c.410 §2; 2019 c.486 §2; 2024 c.2 §3