Morse Bros. v. Kemp Construction, Inc.

935 P.2d 464, 147 Or. App. 217, 1997 Ore. App. LEXIS 425
CourtCourt of Appeals of Oregon
DecidedMarch 19, 1997
DocketC950646CV; CA A92399
StatusPublished
Cited by2 cases

This text of 935 P.2d 464 (Morse Bros. v. Kemp Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morse Bros. v. Kemp Construction, Inc., 935 P.2d 464, 147 Or. App. 217, 1997 Ore. App. LEXIS 425 (Or. Ct. App. 1997).

Opinion

HASELTON, J.

Defendants Louis Fasano and Arthur & Associates Real Estate, Inc.1 appeal from the trial court’s denial of their motion for summary judgment and from the court’s allowance of plaintiffs summary judgment motion. The court determined that plaintiff had a valid lien on defendants’ property in the amount of $55,947, together with pre- and post-judgment interest at 18 percent per annum, and ordered the foreclosure of that lien. Defendants also assign error to the award of attorney fees to plaintiff, pursuant to ORS 87.060.2 We affirm.

Defendants were the principals of a real estate development business, L.A. Development Co., that contracted with Kemp Construction, Inc. to build a subdivision in Sherwood. Kemp Construction, in turn, entered into a subcontract with plaintiff, by which plaintiff was to provide sand, gravel, and rock products for the subdivision. Plaintiff provided materials with a reasonable value of $70,208.35 but received payment of only $17,395.07. Thereafter, plaintiff filed this action, seeking, inter alia, to foreclose a lien on certain escrowed funds in lieu of a lien on defendants’ property. Plaintiffs complaint alleged, in material part:

“The contract price and agreed and reasonable value of the materials furnished by Plaintiff to [Kemp Construction] and used and incorporated in the construction * * * is the sum of [$70,208.35], together with eighteen percent (18%) interest per annum from January 5, 1995, until paid. No part of said sum has been paid except the sum of [$17,395.87] and there is now due and owing to plaintiff the [220]*220sum of [$55,947.07], together with service charges thereon at the rate of eighteen percent (18%) per annum from March 6,1995, until paid.”

Plaintiff prayed for a decree declaring its lien to be “a first, valid, and subsisting lien against the escrowed funds,” and ordering the foreclosure of the lien

“for the amount of [$55,947.07], together with interest thereon at eighteen percent (18%) per annum from March 6,1995, until paid, [$10.00] as the recording fee, its reasonable attorney fees, and for its costs and disbursements incurred herein, against the funds held in escrow [.]”

Defendants answered with the affirmative defense that the lien was invalid because “plaintiff failed to deliver to L.A. Development a Notice of Right to Lien, as is required by ORS 87.018, 87.021 and 87.023.”

Defendants moved for summary judgment on their affirmative defense, asserting that the trial court should dismiss the complaint because plaintiff had not given them proper notice of its right to lien. Plaintiff opposed defendants’ motion and submitted affidavits and argument as to the sufficiency of the delivery of the notice of right to lien. In addition, plaintiff filed a cross-motion for summary judgment “for the reason that there is no genuine issue as to any material fact and Plaintiff is entitled to Judgment as a matter of law.” In support of its cross-motion, plaintiff submitted an affidavit from its accountant, Miner, establishing the facts alleged in its complaint, including the entitlement to the 18 percent finance charge.

Defendants did not dispute the sufficiency of plaintiffs prima facie showing, e.g., the Miner affidavit, in support of its cross-motion for summary judgment. Rather, the only contested issue was the sufficiency of plaintiffs notice of its right to lien. That issue was one of law; that is, all parties agreed that there were no material disputes of fact and that the issue of notice was purely legal. The trial court concluded that plaintiff had effected delivery of the notice of right to lien, as specified in ORS 87.018, denied defendants’ motion for summary judgment, and granted plaintiffs motion.

[221]*221Thereafter, plaintiff submitted a form of judgment that awarded plaintiff the relief sought in its prayer, including pre- and post-judgment interest, based on the finance charge of 18 percent, and attorney fees. Defendants objected to the form of judgment, arguing that plaintiff was not entitled to all of the attorney fees claimed and that plaintiff was not entitled to 18 percent interest, as alleged in the complaint. The trial court considered and rejected those objections and entered judgment awarding 18 percent pre- and post-judgment interest and attorney fees.

On appeal, defendants make three assignments of error. In their first assignment, defendants argue that the trial court erred in concluding that plaintiff had given valid notice of its right to lien. ORS 87.021 provides, in part:

“(1) Except when material, equipment, services or labor * * * is furnished at the request of the owner, a person furnishing any materials, equipment, services or labor * * * for which a lien may be perfected * * * shall give a notice of right to a lien to the owner of the site.”

ORS 87.018 provides:

“All notices required under ORS 87.001 to 87.060 * * * shall be in writing and delivered in person or delivered by registered or certified mail[.]”

The uncontroverted facts, as presented in the summary judgment submissions, are that plaintiff sent notice of its right to lien on September 23, 1994, via certified mail, to L.A. Development’s former address at 8875 SW Beaverton-Hillsdale Highway. L.A. Development’s correct address was 8925 SW Beaverton-Hillsdale Highway. The postal carrier nevertheless delivered the notice on September 26 to the correct address, which L.A. Development shared with another business, Carefree Property Management. In an affidavit, which is part of the summary judgment record, Carefree’s receptionist, Marillyn Bennett, explained:

“Anyone desiring to gain access to the offices of L.A. Development Co. had to go up a set of outside stairs and then walk through the offices of Carefree Property Management and past my desk as receptionist for Carefree before coming to the office of L.A. Development. When the postman had certified or registered mail for L.A. Development Co., he [222]*222would first stop at my receptionist desk and inquire if there was anyone present in the offices of L.A. Development. The majority of the time, there was no one present in the offices of L.A. Development and I would sign for any registered or certified mail addressed to L.A. Development. If Mr. Lutz [one of L.A. Development’s principals] was going to be on vacation or gone for an extended period of time, he would advise me of that fact and request that I leave any mail for L.A. Development on his desk in his office. The practice of my signing for certified or registered mail for L.A. Development continued over a period of several years. At no time did Mr. Lutz or Mr. Fasano [the other principal of L.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sugiyama v. Arnold
431 P.3d 466 (Court of Appeals of Oregon, 2018)
Taylor v. Ramsay-Gerding Construction Co.
172 P.3d 251 (Court of Appeals of Oregon, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
935 P.2d 464, 147 Or. App. 217, 1997 Ore. App. LEXIS 425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morse-bros-v-kemp-construction-inc-orctapp-1997.