Taylor v. Ramsay-Gerding Construction Co.

172 P.3d 251, 215 Or. App. 670, 2007 Ore. App. LEXIS 1535
CourtCourt of Appeals of Oregon
DecidedOctober 31, 2007
Docket015188; A127434
StatusPublished
Cited by3 cases

This text of 172 P.3d 251 (Taylor v. Ramsay-Gerding Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor v. Ramsay-Gerding Construction Co., 172 P.3d 251, 215 Or. App. 670, 2007 Ore. App. LEXIS 1535 (Or. Ct. App. 2007).

Opinion

*673 ORTEGA, J.

Plaintiffs H. H. and C. A. Taylor own a hotel in Lincoln City. Plaintiff Taylor & Taylor Development Company operates the hotel. 1 Plaintiffs sued ChemRex, Inc., 2 for breach of warranty based on the alleged failure of an exterior stucco system that was manufactured by ChemRex and installed during construction of the hotel under the supervision of the general contractor on the hotel construction project. 3 The Taylors sought as damages the costs of repairing the building. The development company sought consequential damages resulting from closure of the hotel during repairs. The jury determined that the development company failed to file its breach of warranty claim within the applicable statutory limitations period. As pertinent to this appeal, the jury also determined that ChemRex breached one or more express warranties to the Taylors, that the Taylors incurred damages of $775,000 as a result of the breach, that the Taylors were negligent in one or more of the ways alleged in ChemRex’s answer, that their negligence was a cause of their damages, and that ChemRex was 51 percent at fault and the Taylors were 49 percent at fault. The trial court entered a limited judgment awarding the Taylors $395,250 and dismissing the development company’s claim.

*674 On appeal, plaintiffs assign error to the trial court’s submission to the jury of ChemRex’s comparative fault defense and its failure to dismiss ChemRex’s statute of limitations defense against the development company’s claim. ChemRex cross-assigns error to the trial court’s denial of its motion for a directed verdict in its favor on the development company’s claim. ChemRex also cross-appeals, assigning error to the trial court’s denial of its motion for a directed verdict in its favor on the Taylors’ claim; to the trial court’s denial of its motion for judgment on the pleadings in its favor based on its statute of limitations defense against the Taylors’ claim; to its entry of a judgment that did not conform to the jury’s verdict; and to its order of bifurcation. We affirm on the appeal and reverse on the cross-appeal.

I. BACKGROUND

The relevant historical and procedural facts are undisputed. The Taylors own the O’Dysius Hotel in Lincoln City. They are the only shareholders of the development company, which operates the hotel. Ramsay-Gerding Construction Company was general contractor for construction of the hotel.

Ramsay-Gerding hired TFC Enterprises, Inc. (TFC), to install the hotel’s plaster stucco exterior siding and accompanying metal accessories. TFC submitted to RamsayGerding a request to install a “SonoWall” exterior stucco finish system that was manufactured by ChemRex. The request was approved, and stucco application commenced at the end of August 1998.

About two weeks later, Todd Taylor called Thomas Gerding of Ramsay-Gerding to inform him of a concern that the galvanized metal accessories included in the ChemRex stucco system would rust under coastal conditions. Taylor also followed up with a letter. Gerding stopped work on the installation.

In September 1998, a meeting was held at the construction site. Todd Taylor continued to assert that galvanized metal would rust in Lincoln City’s climate. A ChemRex sales representative, McDonald, asserted that the SonoWall system was bullet-proof against rust, noted that the system *675 came with a five-year warranty, and added that an extra-cost rust inhibitor coating would provide further protection against rust. Taylor and McDonald agreed to proceed with the installation, with the addition of the rust inhibitor coating.

Ten months later, in July 1999, McDonald sent a letter to TFC, stating that ChemRex would “warrantee the SonoWall stucco system for five years * * * starting in [M]arch of 1999.” McDonald intended the warranty to extend to the Taylors.

There was evidence that an employee of the development company discovered that the galvanized metal on the roof was rusting in the late summer or early fall of 1999 and, in March or April of the following year, evidence of rust appeared on the exterior, on corners, and on some expansion joints. On July 20, 2000, Todd Taylor wrote to Gerding about the problem, invoking the five-year ChemRex warranty. On August 2, 2000, Gerding informed Taylor that representatives from ChemRex and TFC would be at the hotel on August 4. On August 24, Taylor informed Gerding by letter that the meeting had occurred but that he had not heard from ChemRex since that time. As of 2004, the problem had not been fixed.

II. THE TRIAL

In October 2001, the Taylors initiated an action against Ramsay-Gerding for breach of the construction contract, seeking damages for repair of the building and for lost profits due to its “unattractive” condition and the necessity of making repairs. Ramsay-Gerding answered and, as an affirmative defense, asserted in part that the Taylors were negligent in selecting the stucco system.

In April 2002, Ramsay-Gerding initiated its third-party complaint against ChemRex, among other entities involved in the construction of the hotel. Ramsay-Gerding alleged that ChemRex had been negligent in designing the system and in other particulars and that it had breached its warranty pertaining to the system. It also sought indemnity and contribution from ChemRex for any damages awarded to the Taylors against Ramsay-Gerding. ChemRex answered, *676 asserting as an affirmative defense that the Taylors’ damages were caused by their own fault or negligence or that of others involved in the construction.

In August 2003, the Taylors and Ramsay-Gerding stipulated to the Taylors’ filing of an amended complaint. The complaint, which was filed on August 8, asserted claims against Ramsay-Gerding for breach of contract and negligence and asserted a claim against ChemRex for breach of express warranty. As to the latter, the Taylors alleged that ChemRex had warranted the stucco system and related materials for five years beginning in March 1999 and that, within two years of completion of construction, the system began to rust and stain the building. The Taylors sought economic damages in an amount pertaining to the repair of the building and consequential damages for lost profits. ChemRex moved to strike the amended complaint on the ground that the Taylors had not obtained leave of the court or ChemRex’s consent to file it, but the trial court denied that motion.

In April 2004, plaintiffs filed a second amended complaint, adding the development company as a plaintiff. Plaintiffs again asserted breach of contract and negligence claims against Ramsay-Gerding and a breach of express warranty claim against ChemRex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Ramsay-Gerding Construction Co.
226 P.3d 45 (Court of Appeals of Oregon, 2010)
Taylor v. Ramsay-Gerding Construction Co.
196 P.3d 532 (Oregon Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
172 P.3d 251, 215 Or. App. 670, 2007 Ore. App. LEXIS 1535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-v-ramsay-gerding-construction-co-orctapp-2007.