Biomass One, L.P. v. S-P Construction

852 P.2d 847, 120 Or. App. 194, 1993 Ore. App. LEXIS 720
Court of Appeals of Oregon·Decided May 12, 1993·No. 87-1724-J-2, 87-1766-J-2, 86-1146-J-2, 86-1567-J-2, 86-2621-J-2, & 87-1986-J-2 (Consolidated) CA A68622·Published·Cited by 10 cases

Opinion

*198 LANDAU, J.

Third-party plaintiffs Underwriters of Interest (Underwriters) appeal from a summary judgment in favor of third-party defendant Detroit Stoker. We reverse and remand.

S-P Construction (S-P) contracted to design and construct for Biomass One, L.P. (Biomass), a completed cogeneration power plant. S-P subcontracted with Detroit Stoker to provide “stokers,” which are pieces of equipment in which wood waste fuel is burned to heat the boilers that produce electricity-generating steam.

Following completion of the plant, Biomass experienced difficulties with its operation. Among other things, Biomass had problems with the plant’s combustion system, including the stokers. Biomass sued S-P for alleged defects in the design, engineering and construction of the plant. S-P, in turn, filed third-party complaints against various subcontractors, including Detroit Stoker. S-P’s insurers settled the claims brought by Biomass. A group of those insurers, known collectively as Underwriters, elected to pursue the third-party claims against the subcontractors, and Underwriters were substituted for S-P as third-party plaintiffs.

The crux of the third-party complaint against Detroit Stoker is that it delivered equipment that failed to perform in accordance with its agreement with S-P. That agreement contained the following specifications:

“Guarantees
“The Company [Detroit Stoker] guarantees that the stokers covered in this proposal, when operated under the conditions herein provided, will produce the following results, it being understood and agreed that the Purchaser [S-P Construction] will provide the conditions hereinafter specified.
“Fuel •
“The fuel to be burned shall be as described on page 13.
“Capacity
“The Company guarantees that the stoker will be capable of burning sufficient fuel as described on page 13 to operate *199 the boiler at [175,000] lbs.[ 1 ] of steam per hour for a period of twenty-four hours.”

Page 13 of the agreement describes the “fuel” as “Wood & Sander Dust (30%)” with a moisture content of 40 percent and “BTUs per lb. as fired” of 5,300. Underwriters alleged that the stokers did not have the capacity to generate 175,000 pounds of steam in a 24-hour period. Detroit Stoker answered that its guarantee was expressly conditioned on the use of fuel meeting the specifications of the agreement, and that any failure of the equipment to operate in accordance with the guarantee was a result of the use of fuel that did not comply with those specifications.

The trial court bifurcated the case, electing to proceed first with issues related to the guarantee. It limited the proceedings in the first phase to three issues:

“1. What were the specifications (physical and chemical) of the wood fuel supplied at the plant?
“2. What were the specifications of the wood fuel to be used for equipment design, as required by the contracts between the parties?
“ 3. If the wood fuel specified was not supplied, which (if any) breach of contract claims are barred as a matter of law?”

A dispute followed over which party bore the burden of proof on each of the three issues. Detroit Stoker argued that the use of the specified fuel was a condition precedent to enforcement of its guarantee and that, accordingly, Underwriters should bear the burden of proving its compliance with that condition. Underwriters argued that the parties did not intend the fuel specification to operate as a condition precedent, and they asked the court for an evidentiary hearing to prove the point.

The trial court denied Underwriters’ request on the ground that the guarantee provision unambiguously required proof of use of wood fuel with a moisture content of 40 percent as a condition of its enforcement, and that Underwriters bore the burden of proving the use of fuel meeting those specifications. Underwriters then stipulated that it could not establish the characteristics of the fuel actually *200 burned at the cogeneration plant. Based on that stipulation, Detroit Stoker moved for summary judgment, which the court granted.

We review a summary judgment to determine whether there are any genuine issues of material fact and whether the prevailing party is entitled to judgment as a matter of law. Seeborg v. General Motors Corporation, 284 Or 695, 699, 588 P2d 1100 (1978). Underwriters argue that the trial court erred in granting summary judgment, because its decision was based on the erroneous ruling that the guarantee provision of the contract is unambiguous.

Whether language in a contract is ambiguous is a question of law. If the language is ambiguous, then what the parties intended by that language presents a question of fact. OSEA v. Rainier School Dist. No. 13, 311 Or 188, 194, 808 P2d 83 (1991); CH2M Hill Northwest, Inc. v. Parktel I, Inc., 107 Or App 461, 465, 812 P2d 840 (1991). Generally, a dispute concerning that factual question may not be resolved by summary judgment. Pierce v. Mt. Hood Meadows Oregon, Ltd., 118 Or App 450, 454, 847 P2d 909 (1993); Ziegler v. Bostwick, 106 Or App 666, 668, 809 P2d 131, rev den 311 Or 644 (1991). Therefore, if the trial court was incorrect that the guarantee provision of the Detroit Stoker Agreement is unambiguous, its entry of summary judgment was error.

A contract is ambiguous

“if it has no definite significance or if it is capable of more than one sensible and reasonable interpretation; it is unambiguous if its meaning is so clear as to preclude doubt by a reasonable person.” Deerfield Commodities v. Nerco, Inc., 72 Or App 305, 317, 696 P2d 1096, rev den 299 Or 314 (1985).

A contract is not ambiguous merely because the parties disagree about its interpretation. Biomass One, L.P. v. S-P Construction (A61560), 103 Or App 521, 525, 799 P2d 152 (1990). There must be competing interpretations, each of which is reasonable. P & C Construction Co. v. American Diversified, 101 Or App 51, 56, 789 P2d 688 (1990).

Detroit Stoker contends that the guarantee provision of the contract operates only if the stokers were fired with fuel conforming to the contractual specifications. The contract states that “[t]he fuel to be burned shall be” wood and sander *201 dust with a moisture content of 40 percent. Thus, Detroit Stoker argues, a breach of the guarantee can be established only by proof that the specified fuel was used and that the stoker nevertheless did not produce 175,000 pounds of steam in a 24-hour period.

Free access — add to your briefcase to read the full text and ask questions with AI

Biomass One, L.P. v. S-P Construction, 852 P.2d 847, 120 Or. App. 194, 1993 Ore. App. LEXIS 720 (Or. Ct. App. 1993).

852 P.2d 847 (Biomass One, L.P. v. S-P Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Koch v. Spann
92 P.3d 146 (Court of Appeals of Oregon, 2004)
Western Surety Co. v. FDS Diving Construction & Salvage Co.
88 P.3d 293 (Court of Appeals of Oregon, 2004)
Brown v. American Property Management Corp.
1 P.3d 1051 (Court of Appeals of Oregon, 2000)
Mobley v. MANHEIN SERVICES CORP.
889 P.2d 1342 (Court of Appeals of Oregon, 1995)
Towery v. Lucas
876 P.2d 814 (Court of Appeals of Oregon, 1994)
Swanson v. Warner
865 P.2d 493 (Court of Appeals of Oregon, 1993)
Biomass One, L.P. v. S-P Construction
852 P.2d 844 (Court of Appeals of Oregon, 1993)