Harris v. Dyer

623 P.2d 662, 50 Or. App. 223
CourtCourt of Appeals of Oregon
DecidedApril 7, 1981
Docket78-1378-E-3, CA 17650
StatusPublished
Cited by7 cases

This text of 623 P.2d 662 (Harris v. Dyer) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris v. Dyer, 623 P.2d 662, 50 Or. App. 223 (Or. Ct. App. 1981).

Opinion

*225 BUTTLER, J.

The sole issue in this action to foreclose a construction lien is whether either party is entitled to costs and statutorily authorized attorney fees. ORS 87.060(4). 1 The question arises because after the foreclosure proceeding was commenced, it was abated on defendant’s motion pending arbitration of the dispute pursuant to ORS 33.240 2 and the contract between the parties, and after the arbitration award was filed with the circuit court (ORS 33.310), 3 the action was dismissed on defendant’s motion after the amount of the award was tendered to plaintiff.

From the judgment dismissing the action, plaintiff appeals, contending that he is entitled to a judgment for the amount of the award, plus costs and attorney fees. Defendant, having filed a cost bill, which included attorney fees, cross-appeals from that portion of the judgment denying those costs, contending he is the prevailing party. We reverse the judgment of dismissal, affirm the trial court’s *226 denial of defendant’s cost bill, and remand the case for further proceedings.

On September 15, 1977, plaintiff, as contractor, and defendant, as owner, executed a construction contract in a standard form prepared by the American Institute of Architects, under which plaintiff agreed to construct a racquetball facility for defendant in Medford, and defendant agreed to pay plaintiff the contract price of $207,000. After construction commenced, additional work was authorized, increasing the contract price. Subsequently, a dispute arose and, on April 27, 1978, defendant terminated the contract. Plaintiff, contending that the termination was unlawful, made a demand for the amount he claimed was owing from defendant and, when defendant refused to pay, plaintiff filed a claim of lien, notified defendant of that filing and of his intention to commence suit to foreclose the lien. On May 9, 1978, this action was commenced to foreclose the construction lien and, in a second cause of action, to recover damages for breach of contract.

The construction contract, a copy of which was attached to the complaint, contained a provision requiring that all claims and disputes between the contractor and owner arising out of the contract, or its breach, be decided by arbitration. 4 Relying on that provision and on ORS 33.240, defendant moved to abate the action on June 8, 1978; on November 7, 1978, the trial court entered an order abating the proceeding pending arbitration.

The dispute was then submitted to arbitration. On November 13, 1979, the arbitrators issued their award in favor of plaintiff in the amount of $64,089.71, plus interest from May 4, 1978, and provided that the expenses of the *227 arbitration were to be borne equally by the parties. Thereafter, the arbitration award was entered of record in this proceeding. See Jackson v. Penny Duquette Knits, 276 Or 465, 555 P2d 201 (1976). After the time for filing exceptions to the award had expired (ORS 33.310, 33.320), plaintiff moved for a decree foreclosing his lien in the amount of the award, plus interest, lien preparation and recording fees, reasonable attorney fees and court costs. Defendant tendered the amount of the arbitration award to plaintiff, but the tender was rejected because it did not include any amount other than the precise amount of the award, with interest. Plaintiff’s motion for a decree was denied. Thereafter, defendant’s motion to dismiss was granted and defendant submitted the cost bill described above, contending that he was entitled to costs as the "prevailing party.”

The underlying question presented by this appeal is whether the plaintiff, having expressly agreed in his contract with defendant to submit all disputes to arbitration, has waived his right to file a statutory construction lien for amounts unpaid under the contract. Defendant contends that plaintiff seeks "redundant remedies” and that the compulsory arbitration provision is tantamount to a waiver by the contractor of his right to assert such a lien. However, those contentions overlook the significant differences between the right to secure payment of amounts claimed and the obligation to resolve any dispute as to the amounts claimed in a particular manner. This distinction is analogous to that recognized in Jackson v. Penny Duquette Knits, supra, where the court held that an agreement to arbitrate did not deprive the parties of the benefit of prejudgment attachment.

Although it is true that disputes as to amounts owing may be litigated in a suit to foreclose the lien, all lien foreclosures do not involve disputes of that kind. Where there is no dispute, the sole purpose of the lien foreclosure suit is to affect collection by selling the property against which the lien is filed. Where, as here, the parties have agreed to arbitrate their disputes, there appears to be no reason why, once the dispute has been resolved by arbitration, the amount awarded the contractor should not be collectible through a lien foreclosure, assuming that the *228 items included within the award are lienable and other statutory prerequisites are met.

We conclude, therefore, that in the absence of an express waiver by the contractor of his right to file a construction lien, an agreement to arbitrate disputes does not deprive him of the right to file a lien. Having the right to file a claim of lien for amounts claimed to be due would be a hollow gesture unless the contractor also has the right to pursue that claim to fruition. If he is not entitled to file a suit to foreclose the lien, the lien would expire within six months after the filing of the lien claim, ORS 87.055, 5 and would be for naught. If, however, the contractor files a suit to foreclose the lien within the statutory period, the lien continues and, if it ripens into a decree foreclosing it, the lien has priority as of the date it was filed. ORS 87.025. The priority of the contractor’s claim over other liens against the property might well, in many cases, be the difference between the contractor’s being paid, or not being paid, the full amount of his claim.

It is not contended that the lien foreclosure suit was improperly abated to abide the outcome of the arbitration proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
P & C Construction Co. v. American Diversified/Wells Park II
789 P.2d 688 (Court of Appeals of Oregon, 1990)
Buckminster v. Acadia Village Resort, Inc.
565 A.2d 313 (Supreme Judicial Court of Maine, 1989)
Harris v. Dyer
637 P.2d 918 (Oregon Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
623 P.2d 662, 50 Or. App. 223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-v-dyer-orctapp-1981.