Steel Products Co. of Oregon, Inc. v. Portland General Electric Co.

615 P.2d 344, 47 Or. App. 597, 1980 Ore. App. LEXIS 3201
CourtCourt of Appeals of Oregon
DecidedAugust 4, 1980
DocketE6045, CA 14861
StatusPublished
Cited by3 cases

This text of 615 P.2d 344 (Steel Products Co. of Oregon, Inc. v. Portland General Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steel Products Co. of Oregon, Inc. v. Portland General Electric Co., 615 P.2d 344, 47 Or. App. 597, 1980 Ore. App. LEXIS 3201 (Or. Ct. App. 1980).

Opinion

*599 BUTTLER, J.

Plaintiff appeals from judgments entered in favor of three of the defendants after the trial court sustained demurrers to plaintiff’s complaint and denied leave to amend. We reverse and remand.

Plaintiff seeks by this proceeding to foreclose a construction lien for materials furnished for use in the construction of defendant Portland General Electric’s (PGE) Boardman Plant # 1 in Morrow Comity. Defendants demurred to the complaint for failure to state facts sufficient to constitute a cause of suit, in support of which it was argued that (1) notice of delivery was defective and (2) insufficient facts were alleged to show that the materials supplied by plaintiff were supplied at the instance of the owner or its construction agent. The trial court agreed with both contentions.

NOTICE

The requirements for a notice of delivery are specified in ORS 87.021(2). 1 Defendants note two defects in the notice of delivery from plaintiff to PGE. First, plaintiff’s notice claims only for those materials delivered within the previous seven days and not the previous ten days allowed by statute.

*600 All of the materials supplied by plaintiff were delivered within the seven days preceding the notice of delivery. The fact that plaintiff advised PGE that a claim might be made for materials delivered within a shorter time period than that allowed by statute does not invalidate the notice, although it might well limit plaintiff to materials supplied after a date which is seven days before the notice was given rather than the statutory 10 days.

The second defect noted in the notice of delivery is the failure to inform PGE that "[n]o further notice to the owner of this or any subsequent delivery is necessary.” ORS 87.021(2)(e). Like the public works bond statute in question in School Dist. No. 1 v. Rushlight & Co., 232 Or 341, 375 P2d 411 (1962), ORS 87.021 requires only that the notice given be "in substance” as set out in the statute.

"* * * Whether or not the appellant has substantially complied with the statute should be determined largely by deciding whether or not the notice given performed the function intended.” School District No. 1 v. Rushlight & Co., 232 Or 341, 347, 375 P2d 411 (1962).

It is apparent here that PGE was given sufficient information to be made aware of the fact that a lien might be claimed for the materials delivered. The notice gave PGE sufficient information to allow it to monitor plaintiff’s deliveries and to protect itself in dealing with its original contractor. See Fowler Co. v. Medical Research, 238 Or 316, 393 P2d 657 (1964). Plaintiff’s claim of lien will not be rendered void by the failure of the notice of delivery to inform PGE that no further notice was necessary unless PGE establishes that it was prejudiced by that failure. We will not presume prejudice; it is a matter of pleading and proof by PGE, and therefore may not be determined on demurrer.

SUFFICIENCY OF ALLEGATIONS

Whether the complaint contains sufficient allegations to withstand a demurrer on the ground that *601 it does not allege a lienable claim presents a more difficult question. Plaintiff alleged the contractual relationships between PGE and Westmont Industries, Inc. (Westmont), the original contractor; between Westmont and Calfred Industries, Inc., dba Rodgers Structural Steel (Rodgers), who contracted with Westmont to fabricate certain steel structures to be used in building the plant; and between Rodgers and plaintiff, who provided the steel to be used by Rodgers. The precise terms of those contracts, however, are not alleged. The complaint incorporates by reference the claim of lien filed after plaintiff completed delivery of materials, a copy of which claim is attached to the complaint as an exhibit. That claim of lien includes a statement that Rodgers was a "subcontractor” "having charge of the construction” of the Boardman plant. 2 Having been incorporated into the complaint, the lien claim is considered part thereof and may be considered in determining the sufficiency of the complaint. See Andersen v. Turpin, 172 Or 420, 142 P2d 999 (1943).

ORS 87.010(1) provides:

"Any person * * * furnishing any material to be used in * * * the construction of any improvement shall have a lien upon the improvement for the * * * material furnished * * * at the instance of the owner of the improvement or his construction agent.”

*602 In order to have been supplied "at the instance of” the owner or his construction agent as the statute requires, the materials for which plaintiff claims a lien must have been contracted for, either directly by the owner, or indirectly for the owner through the construction agent. See Lemire v. McCollum, 246 Or 418, 425 P2d 755 (1967); Gabriel Pow. & Sup. Co. v. Thompson, 163 Or 623, 97 P2d 182 (1940).

Construction agent, according to the definition provided by statute "includes a contractor, architect, builder or other person having charge of construction or preparation.” ORS 87.005(3). The allegation contained in the claim of lien is sufficient to put defendant on notice that plaintiff is claiming to have provided materials at the instance of PGE’s construction agent. This might end the inquiry but for defendants’ argument that Rodgers could not have been a construction agent as a matter of law because it is not alleged that Rodgers provided on-site labor.

It is true that plaintiff did not allege that Rodgers provided labor at the site of the improvement, and from the briefs it seems to be agreed that it did not. The question then presented is whether a party who contracts with the original contractor 3 to fabricate structures to be used in an improvement without providing on-site labor can be a construction agent within the meaning of the statute.

Rodgers is not alleged to be an architect or builder. It is not a contractor under the statutory definition because:

" 'Contractor’ means * * * a person who contracts on predetermined terms to be responsible for the performance of all or part of a job of preparation or construction in accordance with established specifications or plans, retaining in himself control of means, method and manner of accomplishing the desired result, and who provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P & C Construction Co. v. American Diversified/Wells Park II
789 P.2d 688 (Court of Appeals of Oregon, 1990)
Nucor Corp. v. Mohr Construction Co.
763 P.2d 754 (Court of Appeals of Oregon, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
615 P.2d 344, 47 Or. App. 597, 1980 Ore. App. LEXIS 3201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steel-products-co-of-oregon-inc-v-portland-general-electric-co-orctapp-1980.