Andersen v. Turpin

142 P.2d 999, 172 Or. 420, 1943 Ore. LEXIS 103
CourtOregon Supreme Court
DecidedOctober 5, 1943
StatusPublished
Cited by18 cases

This text of 142 P.2d 999 (Andersen v. Turpin) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andersen v. Turpin, 142 P.2d 999, 172 Or. 420, 1943 Ore. LEXIS 103 (Or. 1943).

Opinion

HAY, J.

Plaintiff and respondent brought suit to foreclose a mechanic’s lien for labor performed on a residence building constructed for and owned by defendants and appellants.

The lien notice was filed for record December 1, 1941. The complaint was filed May 19, 1942. It alleged that the defendants contracted with and employed plaintiff to do the work for which he claimed a lien, and showed substantial compliance with the statutory requirements. Details which were attacked by defendants will be mentioned hereafter. Judgment was demanded against the defendants and each of them for $527.85, the sum alleged to be due, with legal interest, costs and attorney’s fees, and a decree foreclosing the lien was prayed for.

The defendant demurred to the complaint on the ground that it did not state facts sufficient to constitute a cause of suit, in that there was a material variance between the contract alleged therein and that stated in the notice of lien. This demurrer was sustained by the court, with leave to amend. On July 23, 1942, *424 plaintiff filed an amended complaint. The defendants moved to strike snch amended complaint upon the ground that it changed substantially the cause of suit set forth in the original complaint and was such an amendment as was beyond the jurisdiction of the court to allow. This motion was overruled, whereupon the defendants demurred on the ground that suit to foreclose plaintiff’s lien had not been commenced within the time limited by the Code, in that more than six months had elapsed between the filing of the notice of lien and the institution of suit to foreclose it. The demurrer was overruled, and defendants answered, making certain formal admissions and denials which, so far as material to the present discussion, will be considered in due course. Affirmatively, they pleaded that the plaintiff did not complete and finish his work, but, without just cause or excuse, abandoned it and left it in an uncompleted state. Further answering affirmatively, they alleged that they were obliged to expend the sum of $546.46 in completing the work left unfinished by plaintiff and in “doing over” a part thereof. The new matter was denied by the reply, but therein plaintiff impliedly admitted that he did not complete the work, stating as a reason therefor that the defendants had refused to permit him to do so.

After a hearing before the court, a decree was entered foreclosing plaintiff’s lien for the sum of $377.85, with legal interest, certain minor disbursements, and attorney’s fees. In arriving at this sum, the court allowed the sum of $150 as an offset against the amount prayed for, by reason of defects in plaintiff’s work. From this decree the defendants have appealed.

It is the contention of the defendants that the original complaint did not state a cause of suit, and *425 that, if the amended complaint did so, it was not filed until after the expiration of six months from the date of the filing of the notice of lien, as required by law. Section 67-107, O. C. L. A.; Shea v. Graves, 142 Or. 503, 509, 19 P. (2d) 406.

We have carefully considered the original complaint together with the notice of lien, a copy of which was attached thereto as an exhibit. It was incumbent upon the plaintiff, by his complaint, to show that he had complied substantially with the provisions of the statute entitling him to a lien. Pilz v. Killingsworth, 20 Or. 432, 435, 26 P. 305; Rankin v. Malarkey, 23 Or. 593, 597, 32 P. 620, 34 P. 816; Christman v. Salway, 103 Or. 666, 685, 205 P. 541; McCormack v. Bertschinger, 115 Or. 250, 253, 237 P. 363; Phillips v. Graves, 139 Or. 336, 347, 9 P. (2d) 490, 83 A. L. R. 1.

In support of their contention that the original complaint did not state a cause of suit, the defendants point out certain particulars wherein they allege that pleading to have been defective. They say that the complaint alleged that plaintiff’s work was performed under contract with the defendant-owners, whereas the notice of lien stated that it was performed at the instance and request of I. N. Eichardson, the original contractor.

The notice of lien was set out in haec verba in the exhibit and was incorporated in the complaint by reference. Moreover, the complaint contained a specific allegation that each and all of the statements contained in the lien notice were true. The exhibit was thus not only incorporated in the complaint, but the allegations thereof became allegations of the complaint, supported by the same verification. In determining the sufficiency of the pleading, therefore, the *426 allegations of the notice of lien must be held to prevail over any discrepancy between them and those of the complaint proper. Benedict v. Price, 38 F. (2d) 309, 312; Somers v. Hanson, 78 Or. 429, 432, 153 P. 43; Strong v. Moore, 118 Or. 649, 654, 245 P. 505; Birkemeier v. Knobel, 149 Or. 292, 311, 40 P. (2d) 694; Lorenz Co. v. Gray, 136 Or. 605, 612, 298 P. 222; O'Neil v. Twohy Bros. Co., 98 Or. 481, 487, 190 P. 306; Pritchard v. Myers, 174 Md. 66, 197 A. 620, 116 A. L. R. 775, 779.

The notice of lien states that the lien was claimed for labor performed on the building at the instance and request of I. N. Eichardson; that, at the time when plaintiff commenced to perform such labor, defendants were the owners or reputed owners of the building, and that they were such owners at the date when the notice of lien was executed; that the defendants had notice of the construction of the building, and caused the same to be done; that, in such construction, Eichardson was the contractor and agent of defendants; and that the reasonable price of the labor was the sum of $527.85. There follows a detailed statement of the labor of each person employed by plaintiff on the work, showing the number of hours worked by each, the rate of pay and the total earned. These allegations, in our opinion, are sufficient to show that the plaintiff claimed as a subcontractor under the original contractor, notwithstanding the allegation of the complaint that plaintiff contracted with defendants.

The defendants contend that necessary and material averments of a pleading cannot be supplied by an exhibit. Such has been the uniform holding of this court. Malheur County v. Carter, 52 Or. 616, 98 P. 489; Lorenz Co. v. Gray, supra; Wright v. White, 166 Or. 136, 153, 110 P. (2d) 948, 135 A. L. R. 1. We are not *427 dealing, however, with the effect of a mere exhibit, but with the effect of the allegations of an exhibit, when such allegations have been incorporated into the pleading by reference accompanied by an affirmation of their truth. In Wright v. White, supra, it was held that the plaintiff, by attaching as an exhibit to his complaint a certain charge sheet, could not be held to have alleged that the charges contained therein were true, but merely the fact that such charges had been preferred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Twin Island Development Corp. v. Winchester
512 A.2d 319 (Supreme Judicial Court of Maine, 1986)
Steel Products Co. of Oregon, Inc. v. Portland General Electric Co.
615 P.2d 344 (Court of Appeals of Oregon, 1980)
Oak Grove Parr, Inc. v. McCutcheon Construction Co.
550 P.2d 1382 (Oregon Supreme Court, 1976)
Elvalsons v. Industrial Covers, Inc.
525 P.2d 105 (Oregon Supreme Court, 1974)
Marsh v. Davidson
510 P.2d 558 (Oregon Supreme Court, 1973)
Lemire v. McCollum
425 P.2d 755 (Oregon Supreme Court, 1967)
Dent v. Pollard
362 P.2d 324 (Oregon Supreme Court, 1961)
Burgess v. Downing
354 P.2d 293 (Oregon Supreme Court, 1960)
Kohler v. GILBERT ET UX
339 P.2d 1102 (Oregon Supreme Court, 1959)
In re the Estate of Clark
323 P.2d 334 (Oregon Supreme Court, 1958)
Drake Lumber Co. v. Paget Mortgage Co.
274 P.2d 804 (Oregon Supreme Court, 1954)
Bidlingmeyer v. City of Deer Lodge
274 P.2d 821 (Montana Supreme Court, 1954)
Zumstein v. STOCKTON ET UX.
264 P.2d 455 (Oregon Supreme Court, 1953)
Anderson v. Chambliss Et Ux.
262 P.2d 298 (Oregon Supreme Court, 1953)
Smith v. Gunniss
144 P.2d 186 (Montana Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
142 P.2d 999, 172 Or. 420, 1943 Ore. LEXIS 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andersen-v-turpin-or-1943.