Smith v. Wilcox

71 P. 708, 44 Or. 323, 1903 Ore. LEXIS 22
CourtOregon Supreme Court
DecidedDecember 28, 1903
StatusPublished
Cited by10 cases

This text of 71 P. 708 (Smith v. Wilcox) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Wilcox, 71 P. 708, 44 Or. 323, 1903 Ore. LEXIS 22 (Or. 1903).

Opinions

Mr. Justice AVolverton,

after stating the facts in the foregoing terms, delivered the opinion of the court.

[325]*3251. Appellants’ counsel first insist that a subcontractor is not within the. purview of the mechanic’s lien statute, and hence he cannot claim its benefits. The question is wholly one of construction. “Every mechanic, artisan, machinist, builder, contractor, lumber merchant, laborer, teamster, drayman, and other person performing labor upon or furnishing material, or transporting or hauling any material of any kind, to be used in the construction, alteration, or repair, either in whole or in part, of any building, wharf, * * or any structure or superstructure, shall have a lien upon the same for the work or labor done or transportation or material furnished at the instance of the owner of the building or other improvement or his agent; and every contractor, subcontractor, architect, builder, or other person having charge of the construction, alteration, or repair, in whole or in any part, of any building or other improvement as aforesaid, shall be held to be the agent of the-owner for the purposes of this act”: B. & C. Comp. § 5640. “A subcontractor is one who has entered into a contract, express or implied, for the performance of an act with the person who has already contracted for its performance”: Phillips, Mech. Liens, (3 ed.) § 44. A subcontract is defined to be “a contract by one who has contracted for the performance of labor or service with a third party for the whole or part performance of that labor or service”: Bouvier, Law. Diet. The term “subcontractor” therefore is not inappropriate to designate one who has contracted with the principal contractor to perform the whole as well as a part of the service which the latter has undertaken to perform. The statute was certainly intended to be, and is by its tefms, very comprehensive in its scope and bearing, as it concerns persons performing labor and furnishing materials, one or both, in the construction or repair of the structures or superstructures designated. A subcontractor is not [326]*326specially designated by name, as are others in the statute, as entitled to its benefits; but, if the term “ contractor ” is to be treated as used in its generic sense, he certainly falls within the category. He is assuredly a person who performs labor or furnishes materials, one or both, as the case may be ; and in the case at bar he has not only done both, hut he has erected and completed the entire structure. And would it not seem strange that a contractor, who did the same work, and workmen and materialmen who are employed and furnish materials at his instance and request, should have the benefit of the statute, and yet that the subcontractor should be eliminated ? True, there is no contractual privity between him and the owner. Neither is there between the laborer or the materialman and the owner, where employed by the contractor, but he stands in identically the same relation to the owner as the latter.

2. To facilitate the acquirement of the lien, however, the statute has made the original contractor an agent of the owner while in charge of the construction. Necessarily, he is given the primary control thereof. He may authorize some other person to superintend or take the management of the work, or the parties may agree that an architect or a special builder shall be in charge, but unless there is some such provision to shift the supervision he is necessarily intrusted with it. Being in entire charge, therefore, of the construction, he may subject the building to a lien by the employment of any person to perform labor or furnish materials therefor. A subcontractor, as we have seen, is within the range of such employment, so that he is manifestly within both the letter and spirit of the statute. The principle upon which mechanic’s liens are upheld, where they are given to persons other than those contracting directly with the owner, is that the contractor becomes, for the purpose of the statute, an agent of the owner, and thus do all such persons indirectly con[327]*327tract with the owner: Osborn v. Logus, 28 Or. 302 (37 Pac. 456, 38 Pac. 190, 42 Pac. 997). Some authorities base the right to a lien exclusively upon the circumstance that the labor and materials have been employed and used in the structure and have thereby inured to the benefit of the owner. In all cases supporting the doctrine, however, it is to be observed that there existed either an express or implied contract between the owner and the principal contractor for the construction of the improvement, which is not inconsistent with the view that the reason that such subcontractors and materialmen are entitled to impose a-burden on the parties, depriving the owner of his property, is that the latter has impliedly, through the agency of the principal contractor, contracted for such material and labor: 20 Am. & Eng. Enc. Law, (2 ed.) 350, 351, and note to latter page.

3. The next question is one arising under the evidence, and is whether the plaintiff entered into one or two contracts with Dammeier Company for the construction of the Wilcox and Turple dwellings. The plaintiff testifies that Dammeier told him that he had some buildings he wanted him to figure on, and gave him the plans and specifications for the two; that witness looked them over, but did not want to carry the whole business, and took the specifications for one of them (the Wilcox dwelling) home with him, made the estimate, and told Dammeier that it figured up to $1,335, but that, if the water was in front of the house, he would do the work for $1,325 ; that on investigation it was found that the water was not in front of the house, and it was finally agreed that Dammeier Company would allow $40 for bringing it in, one pipe being all that was needed for both houses, and that witness then agreed to build the house for $1,345; that Dammeier thought there was a little difference in the other plans, and wanted witness to figure on them also, in [328]*328order to see if lie could not do the work for less; that witness then looked them over again, and said that he would not spend any further time in figuring upon them, but that, if Dammeier wanted to let him have both houses at the same figure, namely, $1,345, he would take them, and that Dammeier agreed to it. George H. Dammeier testifies that he let plaintiff have the contract to build the two houses for Wilcox and Turple, and was to give him $1,345 for building each house, that amount being specified and agreed upon; that the contract for the two houses was made at the same time, at the same interview, but was not reduced to writing; that the witness had a contract with Wilcox to build him a house on his premises, also one with Turple to build a house on his premises, and that his contract with plaintiff was for building the two houses for $2,690; that they made up the price for the two houses by doubling his estimate for the one. It is a little difficult to determine from this testimony, which is, in substance, all that was offered upon the subject, whether the parties entered into separate contracts for the construction of each house, or a single one for the construction of both. The work of construction was carried forward upon both dwellings concurrently, the plaintiff letting subcontracts for doing portions of the work on both jointly, and it might be said that he treated them, so far as the employment of his workmen was concerned, as one undertaking.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andersen v. Turpin
142 P.2d 999 (Oregon Supreme Court, 1943)
Arcweld Manufacturing Co. v. Burney
121 P.2d 350 (Washington Supreme Court, 1942)
Riggen v. Perkins
246 P. 962 (Idaho Supreme Court, 1926)
Republic Supply Co. v. Allen
262 S.W. 113 (Court of Appeals of Texas, 1924)
Christman v. Salway
205 P. 541 (Oregon Supreme Court, 1922)
Paulson v. Hurlburt
183 P. 937 (Oregon Supreme Court, 1919)
Stuart v. Camp Carson Mining Co.
165 P. 359 (Oregon Supreme Court, 1917)
Zanello & Son v. Portland Central Heating Co.
139 P. 572 (Oregon Supreme Court, 1914)
Equitable Savings & Loan Ass'n v. Hewitt
106 P. 447 (Oregon Supreme Court, 1910)
Litherland v. Cohn Real Estate Co.
100 P. 1 (Oregon Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
71 P. 708, 44 Or. 323, 1903 Ore. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-wilcox-or-1903.