Riggen v. Perkins

246 P. 962, 42 Idaho 391, 1926 Ida. LEXIS 103
CourtIdaho Supreme Court
DecidedApril 5, 1926
StatusPublished
Cited by3 cases

This text of 246 P. 962 (Riggen v. Perkins) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riggen v. Perkins, 246 P. 962, 42 Idaho 391, 1926 Ida. LEXIS 103 (Idaho 1926).

Opinions

TAYLOR, J.

This action was originally brought by Frank Riggen to foreclose eight labor liens for work done by himself and his seven assignors in the erection of a house for the respondent Proctor K. Perkins. The other parties, *395 Brownell Brothers Company, Gem State Lumber Company, Wood Biver Power Company and the Coast Lumber Company, were made parties on their claims of liens upon the same property. A judgment of nonsuit was entered against the plaintiff Biggen and the Coast Lumber Company, and in favor of the other lien claimants. Biggen and the Coast Lumber Company appealed from that judgment, and Brownell Brothers Company from the portion of the judgment declaring a priority between the successful lien claimants.

The defendant Perkins entered into a written contract with the Arco Mill & Building Company by which the latter agreed “to provide all the materials and to perform all the work” in erecting the dwelling-house in controversy, according to plans and specifications. This company partially completed the building and abandoned its work. All the lien claimants are shown to have dealt directly with the contractor Arco Mill & Building Company, and were to have been paid by it. They had no contracts of employment or purchase or sale with, or promise of pay from, the owner.

The labor lien claims did not contain “the name of the person by whom he was employed,” as required by C. S., see. 7346. The labor liens filed were all similar in form to that of plaintiff Biggen. They contained no recital, in the title or elsewhere, of the name of the contractor, or that there was such a contract or contractor. Bach recited that the claimant “as laborer” performed labor in and upon that certain building, describing it. The only recital of the name of the owner or person by whom the claimant was employed, was: “That the said Proctor K. Perkins is the owner or reputed owner of said described premises, and caused said labor by the said Frank Biggen.”

Counsel for plaintiff Biggen attempts to support the claims for labor liens by the contention that the contractor Arco Mill & Building Company was the statutory agent of defendant Perkins, and that thus he should be permitted to establish, under an allegation such as recited, that the defendant employed the labor claimants. The Arco Mill & *396 Building Company was the statutory agent of defendant for the purpose of giving a lien upon the premises by one who performed labor for it, but not for the purpose of making a laborer employed by it the direct contract employee of the owner, or thus by law to supply a relation which would support an allegation of the lien or complaint that the laborer was “employed” by the owner, or that, under the facts, the owner was the “person by whom he was employed.” The failure to set forth in the claims of liens, under these circumstances, any statement of the person by whom the laborers were employed, was fatal to the liens. (Robertson v. Moore, 10 Ida. 115, 77 Pac. 218; Steel v. Argentine Mining Co., 4 Ida. 505, 95 Am. St. 144, 42 Pac. 585; Hogan v. Bigler, 8 Cal. App. 71, 96 Pac. 97 ; Dillon v. Hart, 25 Or. 49, 34 Pac. 817.)

The court entered a nonsuit against the Coast Lumber Company on its claim of lien for materials, upon the insufficiency of its lien claim and cross-complaint. The company has filed no brief and made no appearance on the hearing. "We have, however, examined the record, and find the judgment of nonsuit warranted.

The lien claim and cross-complaint of Brownell Brothers Company, a corporation, allege that it furnished “labor and materials,” in a total amount named, to Arco Mill & Building Company as contractor and as the statutory agent of defendant Perkins, which were for use and actually used in the construction of the building. The court found that appellant Brownell Brothers Company did furnish materials, to be used and actually used, in the amount of $410, and did, under a contract with Arco Mill & Building Company so to do, furnish and install, as a subcontractor, the heating plant and plumbing fixtures. The court found in favor of the appellant, giving it a lien which was not contested, except as to its classification; but gave it a lien as a material-man for such items only as paints, hardware, and the like, in the sum of $410, and a lien priority as a subcontractor only for the amounts of its contracts for the installation of the heating plant and plumbing fixtures, which placed this *397 appellant’s lien in that amount inferior to those of the Wood Biver Power Company and the Gem State Lumber Company, who were classified as materialmen and given a priority as such.

The appeal is “from that part of the judgment . . . . wherein it was decreed that the balance of the amount owing Brownell Bros. Company, Ltd., .... is .... a lien of a subcontractor and is inferior and subject to the liens of Gem State Lumber Company, a corporation, and Wood Biver Power Company, a corporation.....”

There was evidence that appellant submitted competitive bids for this work, and entered into written contracts with the Arco Mill & Building Company, under the terms of which it might well be found to be a subcontractor. Witnesses for appellant testified that these contracts were abrogated by it for some failure of the Arco Mill & Building-Company to live up to their terms. It is not greatly material whether the written contracts introduced were actually carried out, or whether, as contended by appellant, it furnished the materials and performed the work under oral contracts with the Arco Mill & Building Company, for the evidence supports the holding in either event, that it was a subcontractor as to the heating plant and plumbing.

Appellant seeks to support its claim that it was, as to the heating and plumbing, a “materialman,” on the theory that the installation of these materials, and the labor necessary to install them, were a part of the contract price of delivery of the materials. The evidence does not support this contention. Appellant did enter into contracts which its officers say were abrogated, but even the lien claim and cross-complaint allege the furnishing of labor and materials to be used, and actually used, in the erection and construction of the building. This corporation could not claim for itself a labor lien; and until the theory sought to be unfolded at the trial and on appeal, the evidence shows that at no time was the labor included in the contract prices of the delivered articles, except in the only logical view of the evidence, that the appellant was a subcontractor. It is *398 shown that the appellant made charges for extras in labor and material and allowances itemized, such as, “Credit nse of galv. iron instead of tin, 15.00,” and “Allowance same from dining room, 5.40.” No reasonable explanation of this evidence can be given, unless appellant was charging for extras above, and making allowances in reduction of, a contract price for the job, not the materials.

Brownell Brothers Company is a corporation. No reasonable theory can be advanced supporting a lien for the items of labor shown, except that of a subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pierson v. Sewell
539 P.2d 590 (Idaho Supreme Court, 1975)
White v. Constitution Mining & Milling Co.
55 P.2d 152 (Idaho Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
246 P. 962, 42 Idaho 391, 1926 Ida. LEXIS 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riggen-v-perkins-idaho-1926.