Dolese Bros. Co. v. Andrecopulas

1925 OK 171, 237 P. 844, 113 Okla. 18, 1925 Okla. LEXIS 860
CourtSupreme Court of Oklahoma
DecidedMarch 3, 1925
Docket14961
StatusPublished
Cited by21 cases

This text of 1925 OK 171 (Dolese Bros. Co. v. Andrecopulas) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dolese Bros. Co. v. Andrecopulas, 1925 OK 171, 237 P. 844, 113 Okla. 18, 1925 Okla. LEXIS 860 (Okla. 1925).

Opinion

RILEY, J.

This action was begun in the district court of Oklahoma county by Gus Andreeopulas, one of -the defendants in error, against Dolese Brothers Company, a corporation, II. L. Salley, W. L. Dickson and Rank Brothers, a copartnership, defendants in error, seeking the cancellation of a mechanics’ lien against, and removing a cloud from the title of certain real estate owned by said Andreeopulas, and for damages.

Andreeopulas, as owner of certain real estate in said county, made a contract with defendant Salley, by the terms of which the latter was to furnish materials and labor-an <1 to construct a building on said real estate. Defendant Salley subcontracted to W. L. Dickson, and Dickson resubcontracted a part of the work thereon to Rank Brothers. Rank Brothers contracted and purchased from defendant Dolese Brothers Company building materials to the value cff $225.80.

There is some contention on the part of Andreeopulas that Dolese Brothers Company had furnished to Rank Brothers a receipt and acknowledgment of payment in full on the account of building materials so furnished ; that Rank Brothers had produced this receipt to the satisfaction of Dickson and that Dickson had presented it to Salley. However, the trial court found, and his findings are supported by the evidence, that the alleged receipt was only a statement, and that -the same was not signed nor authorized by Doiese Brothers Company. Dolese Brothers Company filed a verified answer and cross-petition to the petition of plaintiff, amongst other things, praying for a foreclosure of the lien in controversy; to which plaintiff answered. Likewise, sep arate answers were filed by Salley and Dickson, to which Dolese Brothers Company made reply in Ube nature of a general denial.

It will be observed that all the defendants except Rank Brothers had answered before trial.

The summons as to Neal and M. E. Rank, copartners composing the firm of Rank; Brothers, had been returned with a return-of service “not found.” No objection was. made, on the part of any party to the action, to proceeding in the case on account; *19 of the absence of Rank Brothers, and the court continued the cause as to Rank Brothers until service upon them could be had. Upon the issues thus joined the cause was tried to the court without the intervention of a jury!. Judgment was rendered for plaintiff, Andrecopulas, for cost, and defendant Dolese Brothers Company's lien was ordered canceled. The court later modified said judgment by rendering judgment in favor of cross-petitioner Dolese Brothers Company, foreclosing its lien upon the property of plaintiff for the sum of $59.00, interest and cost, based upon the value of materials, furnished by cross-petitioner, which entered into the construction of a sidewalk adjacent to and abutting the property in question, for the construction of which sidewalk the defendant Salley had contracted directly with Rank Brothers, subcontractors, who purchased the materials from cross-petitioner.

The contention of Dolese Brothers Company is that the trial court erred in its holding upon the following matter:

“Does a materialman or a subcontractor, who may stand in the third degree under the Oklahoma Mechanic's Lien Law as it now stands, have a lien for the cost of its material which enters into the construction of an owner’s property?”

Let us set out more clearly the position occupied by the parties to this suit: Owner of property — Gus Andrecopulas; contractor —H. L. Salley; first subcontractor — W. L. Dickson; second subcontractor — Rank Brothers; materialmen under second subcontractor — Dolese) Brothers Company.

The question raised makes it necessary that this court place its construction on section 7463, Comp. Staf. 1921, which is as follows :

“Any person who shall furnish any such material or perform such labor as a subcontractor, or as an artisan or day laborer in the employ of the contractor, may obtain a lien upon, such land, or improvements, or both, from the same time, in the same manner, and to “the same extent as the original contractor, for the amount due him for such material and labor; and any artisan or day laborer in the employ of, and any person furnishing material to such subcontractor, may obtain a lien upon suclh, land, or improvements, or both, for the same time, in the same manner, and to the same extent as the subcontractor, for the amount due him for such material and labor. * * *’

The question here presented is whether or not a materialman or subcontractor, standing in the third degree removed from the contractor and the fourth degree removed from the property owner, comes within the limit of the statute above quoted so as to entitle him to a lien upon the property owner’s real estate, upon which the improvements were made and ior which the materials were furnished, when there is no actual contractual relation existing between such a materialman and the owner or his contractor.

Defendant in error contends that the statutes of Oklahoma and Kansas regarding liens are the same in effect., and cites the case of Vandenberg v. Walton Lumber Co., 19 Okla. 169, 92 Pac. 149. This court, in deciding the Arandenberg Case, had before it for construction the mechanics’ lien law as it then existed. Tlhe Oklahoma statute at that time was indentical with the Kansas statute, and this court then followed the Kansas rule in holding that the materialman or subcontractor to a subcontractor had no lien. The Kansas statute, and the Oklahoma statute at the time of the Vandenberg decision, was as follows:

“Any person who shall furnish any such material or perform such labor under a subcontractor with the contractor * * * may obtain a lien.* * *”

In 1905 the Oklahoma statute on such liens was amended so as to give right of lien to a materialman furnishing materials to a subcontractor, and this court, in t!he Hoggson Bros. v. Dickason-Goodman Lumber Company Case, 81 Okla. 31, 196 Pac. 686, held that the Walton Lumber Company rule was no longer applicable.

It will be observed that the Kansas statute limits the materialman’s lien to a subcontractor of the contractor, while the Oklahoma statute says any person furnishing such materials, as a subcontractor, is entitled to a lien.

The codifiers of Harris-Day Code, in bringing the statute, supra, forward, amended the phrase “under a subcontractor with the contractor” so as to make it read “as a subcontractor.”

We can further clarify the meaning of the Oklahoma statute byi eliminating the phrase “or as an artisan or day laborer in the employ of tlhe contractor,'” inasmuch as the same deals with a separate and distinct contract foreign to the relation of a subcontractor. Thus the statute reads: ‘‘Any person who shall furnish any such material or perform such labor as a subcontractor, * * * may obtain a lien.”. There is no provision, then, that the subcontractor must *20 have his contract with the original contractor, and all subcontractors must come within this class irrespective of the degree they are removed from the original contract. Mobley v. Leeper Bros. Lbr. Co., 89 Okla. 97, 214 Pac. 174, is in accord with this rule:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Welling v. American Roofing & Sheet Metal Co.
1980 OK 131 (Supreme Court of Oklahoma, 1980)
McGlumphy v. Jetero Const. Co., Inc.
1978 OK 154 (Supreme Court of Oklahoma, 1978)
Manhattan Construction Co. v. District Court of Oklahoma County
1973 OK 156 (Supreme Court of Oklahoma, 1973)
O'Neal Steel Company v. Leon C. Miles, Inc.
187 So. 2d 19 (Mississippi Supreme Court, 1966)
M & M ENTERPRISES v. Kaul
1963 OK 139 (Supreme Court of Oklahoma, 1963)
Shugart v. LF Platt Lumber Company
1963 OK 45 (Supreme Court of Oklahoma, 1963)
Schuman v. Teague
1945 OK 25 (Supreme Court of Oklahoma, 1945)
Wooten v. Warmack
1941 OK 92 (Supreme Court of Oklahoma, 1941)
Hardware Mut. Casualty Co. v. Hilderbrandt
119 F.2d 291 (Tenth Circuit, 1941)
Consolidated Cut Stone Co. v. Seidenbach
1937 OK 701 (Supreme Court of Oklahoma, 1937)
Rogers v. Crane Co.
1937 OK 340 (Supreme Court of Oklahoma, 1937)
Cameron v. Speer
1937 OK 303 (Supreme Court of Oklahoma, 1937)
Standard Accident Insurance v. Deep Rock Oil Corp.
1937 OK 150 (Supreme Court of Oklahoma, 1937)
J. Watts Kearny & Sons v. Perry
141 So. 13 (Supreme Court of Louisiana, 1932)
F. J. Lewis Mfg. Co v. Snyder
37 F.2d 299 (Sixth Circuit, 1930)
Sutherland Lumber Co. v. Gale
1929 OK 192 (Supreme Court of Oklahoma, 1929)
Harris v. Spurrier Lbr. Co.
1928 OK 192 (Supreme Court of Oklahoma, 1928)
Eagle Oil Co. v. Altman
1928 OK 66 (Supreme Court of Oklahoma, 1928)
Fox v. Dunning
1927 OK 79 (Supreme Court of Oklahoma, 1927)
Riggen v. Perkins
246 P. 962 (Idaho Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
1925 OK 171, 237 P. 844, 113 Okla. 18, 1925 Okla. LEXIS 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dolese-bros-co-v-andrecopulas-okla-1925.