Consolidated Cut Stone Co. v. Seidenbach

1937 OK 701, 75 P.2d 442, 181 Okla. 578, 1937 Okla. LEXIS 223
CourtSupreme Court of Oklahoma
DecidedDecember 7, 1937
DocketNo. 21661.
StatusPublished
Cited by44 cases

This text of 1937 OK 701 (Consolidated Cut Stone Co. v. Seidenbach) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Cut Stone Co. v. Seidenbach, 1937 OK 701, 75 P.2d 442, 181 Okla. 578, 1937 Okla. LEXIS 223 (Okla. 1937).

Opinions

*580 MeRXLL, Speci'al Justice.

This action arose out of the construction of a building in the city of Tulsa upon real estate belonging to J. L. Seidenbach, one of the defendants in error, and was instituted in the district court of Tulsa county, April 22, 1927, by Ed M. Lightfoot to foreclose a mechanic’s lien he asserted against s'aid property. Various lien claimants were parties to the suit, as was the general contractor, J. W. Wilson, and the lien claimants filed pleading's asserting- their respective liens.

The eontr!aet between Seidenbach and Wilson for- the construction of the bpilding was made August 26, 1926, and it was specified therein that the owner would pay the contractor “in current funds for the performance of the contract, one hundred twenty-eight thousand, one hundred forty-six ($128,-146) dollars subject to additions and deductions as provided in the general provisions of the contract.” It was also specified in the contract that the building should be completed on or before the 15th day of January, 1927, and that, in the event it was not completed upon that date, the owner should be entitled to damages against the contractor in the sum of $125 per d'ay for each day thereafter until the completion of the building. The time for completion was later extended until the 14th day of February, 1927. The contractor did not complete the building within the time contemplated, and on the 2nd day of April, 1927, the owner took over the contract for the purpose of completing the building, and thereafter continued with construction work until the 15th day of September, 1927, when the building was completed.

All the lien claims involved in this action accrued during the time the general contractor was in charge of the work.

The -owner, J. L. Seidenbach, in his answer and cross-petition, claimed offsets against the various liens for delay in completion of the building, for costs of completing the same, for additional managerial and supervisory help, for defective work, and for attorney’s fees. He further claimed that any liability that may have existed to lien claimants had been discharged by payments to the general contractor, which payments had been in turn paid to the lien claimants, and that with such payments and the deductions claimed there was no balance available for the payment of lien claims.

The cause was referred to Robert D. Hudson, as referee, for trial. Thereafter the referee made his report to the trial court. Exceptions filed by the various lien claimants were overruled, the referee’s report was adopted, and judgment was rendered in accordance therewith. From this judgment, the lien claimants who appear here as plaintiffs in error appealed.

Twenty-four claims, totaling in amount $5'8,261.25, were filed. Five of these, amounting to $10,971.04, were denied in full, while seven others were reduced in amount from $24,956.10 to $19,357.34. The principal amount of unpaid claims, as determined and allowed 'by the referee, was $41,085.85. Interest was allowed in the sum of $6,798.50, and attorneys’ fees in the sum of $7,000, m'aking a grand total of $54,884.41.

In determining the owner’s liability for the payment of claims allowed, deductions from the contract price were made as follows : Damages for del'ay in the completion of the building, from February 14, 1927, to September 15', 1927, at the rate of $125 per day, $26,625; for cost of completing the building, $55,239.69. It was further found by the referee that out of the sum of $37,-660 paid by the owner to the contractor, $19,-445.57 has been applied in payment of preferred labor claims 'and should be deducted from the contract price. Labor claims amounting to $978.52, including interest, and paid by the owner, were also found to be deductible, as were the costs of the suit, amounting to $13,194.15. The sum of all these deductions being $115,502.93, the trial court held that the amount available for the payment of lien claims was $13,-143.07.

The court added to the sum of $54,884.41, which was the total amount of claims allowed, with interest 'and attorneys’ fees, the sum of $12,616.69, which the court found had been paid by the contractor to lien claimants of equal rank with the claimants in this suit out of the sum of $37,660 paid by the owner to the contractor for payment of lienable claims, thus making a total of $67,501.10 to be prorated and paid out of said sum of $13,143.07. The percentage of proration was therefore found to be .19471 plus. The owner was given the benefit of said payment of $12,616.69 only to the extent that the sum was properly 'apportioned among lien claimants, and on that basis of calculation his liability to lien claimants holding unpaid claims was reduced by the judgment of the trial court to $9,061.01. Judgment was rendered against J. W. Wilson, the contractor, in favor of the lien claimants, in the principal sum of $49,-954.22, with interest in the sum of $S,241.32 *581 and attorneys’ fees in the sum of $7,275, making a total judgment of $65,470.54.

Before the case was tried, the owner, for the purpose of discharging the several liens against his property, made separate deposits ■of cash in the amount of each lien as filed, hnd posted separate bonds, all as provided by section 10980, O. S. 1931.

This appeal is prosecuted by Consolidated Cut Stone Company, a corporation, Patterson Steel Company, a corporation, J. B. Klein Iron & Foundry Company, a corporation, Builders’ Supply Company, a Corporation, Pickering Lumber Company, a corporation, Campbell Metal Window Company, a corporation, Mary A. Walker, United Brick & Tile Company, Standard Hoofing & Material Company, and the Monohan Plastering Company, on a joint petition in error. Consolidated Cut Stone Company and Patterson Steel Company h'ave filed supplemental individual petitions in error.

Some time after the appeal was lodged in this court, plaintiffs in error presented an application for the appointment of a special referee to take evidence and determine whether certain portions of a sum amounting to $46,250 recovered by the owner, after this case was tried, in settlement of a suit instituted by the owner against the surety on the contractor’s bond, the Hartford Accident & Indemnity Company, covered items which the owner was permitted by the trial court to claim as offsets against lien claimants. It appears that during the proceedings in the trial court, the surety company was made a party to the litigation and the owner attempted to maintain a cross-petition upon said bond in connection with this litigation. The trial court sustained a motion of the surety company to dismiss as against it, and no appeal was taken from such order of dismissal.

The owner contends th'at very little of the amount recovered by him was in any way connected with the items allowed as offsets. This court, upon consideration of the application, decided that its jurisdiction in this case is appellate only, and that we cannot properly assume original jurisdiction to try and determine questions of fact and law which are not involved in the appeal. The rule that an appellate tribunal can in proper cases take cognizance of facts occurring during the pen-dency of the appeal, where the facts bear directly upon the questions presented by the appeal, is not applicable here for the reason that new and different questions of law not involved in this case when it was presented on appeal would he injected into the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H2K TECHNOLOGIES v. WSP USA
2021 OK 59 (Supreme Court of Oklahoma, 2021)
Cities Service Co. v. Gulf Oil Corp.
1999 OK 14 (Supreme Court of Oklahoma, 1999)
Panganiban v. Panganiban, No. 538834 (Jan. 20, 1998)
1998 Conn. Super. Ct. 111 (Connecticut Superior Court, 1998)
Sabine Corp. v. ONG Western, Inc.
725 F. Supp. 1157 (W.D. Oklahoma, 1989)
Dixon v. Kelley (In Re Producers Energy Corp.)
11 B.R. 669 (W.D. Oklahoma, 1981)
Hidalgo Properties, Inc. v. Wachovia Mortgage Co.
617 F.2d 196 (Tenth Circuit, 1980)
B & B Lines, Inc. v. Ryan Freight Lines, Inc.
601 P.2d 1207 (Court of Civil Appeals of Oklahoma, 1979)
Masten Lumber & Supply Co. v. Brown
405 A.2d 101 (Supreme Court of Delaware, 1979)
MASTEN LUMBAR AND SUPPLY CO., INC. v. Brown
405 A.2d 101 (Supreme Court of Delaware, 1979)
Quapaw Co. v. Varnell
566 P.2d 164 (Court of Civil Appeals of Oklahoma, 1977)
Larrance Tank Corporation v. Burrough
1970 OK 205 (Supreme Court of Oklahoma, 1970)
Knapp v. Arko Interstate Electric Co.
1968 OK 183 (Supreme Court of Oklahoma, 1968)
D. H. Overmyer Warehouse Co. v. W. C. Caye & Co.
157 S.E.2d 68 (Court of Appeals of Georgia, 1967)
Metropolitan Water Company v. Hild
1966 OK 96 (Supreme Court of Oklahoma, 1966)
Richardson v. H. E. Leonhardt Lumber Co.
1964 OK 15 (Supreme Court of Oklahoma, 1964)
Lembke Construction Co. v. JD Coggins Company
382 P.2d 983 (New Mexico Supreme Court, 1963)
Cushing Country Club v. Boardman Company
1963 OK 83 (Supreme Court of Oklahoma, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
1937 OK 701, 75 P.2d 442, 181 Okla. 578, 1937 Okla. LEXIS 223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-cut-stone-co-v-seidenbach-okla-1937.