H2K TECHNOLOGIES v. WSP USA

2021 OK 59, 503 P.3d 1177
CourtSupreme Court of Oklahoma
DecidedNovember 16, 2021
StatusPublished
Cited by2 cases

This text of 2021 OK 59 (H2K TECHNOLOGIES v. WSP USA) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H2K TECHNOLOGIES v. WSP USA, 2021 OK 59, 503 P.3d 1177 (Okla. 2021).

Opinion

OSCN Found Document:H2K TECHNOLOGIES v. WSP USA

H2K TECHNOLOGIES v. WSP USA
2021 OK 59
Case Number: 119422
Decided: 11/16/2021
THE SUPREME COURT OF THE STATE OF OKLAHOMA


Cite as: 2021 OK 59, __ P.3d __

NOTICE: THIS OPINION HAS NOT BEEN RELEASED FOR PUBLICATION. UNTIL RELEASED, IT IS SUBJECT TO REVISION OR WITHDRAWAL.

 


H2K TECHNOLOGIES, INC., Plaintiff/Appellant,
v.
WSP USA, INC. and FIDELITY AND DEPOSIT COMPANY OF MARYLAND, Defendants/Appellees.

APPEAL FROM THE DISTRICT COURT OF GARVIN COUNTY
HONORABLE LEAH EDWARDS, TRIAL JUDGE

¶0 This is an action by a materialman to foreclose a materialmen's lien. The lien was discharged and the original contractor and its surety were substituted as defendants. The trial court granted summary judgment in favor of the defendants holding that because the subcontractor had waived its right to file a lien the materialman had no right to file a lien. We reverse and remand for further proceedings.

APPEAL PREVIOUSLY RETAINED;
TRIAL COURT REVERSED AND REMANDED FOR FURTHER
PROCEEDINGS

Brett Agee, Garvin Agee Carlton, P.C., Pauls Valley OK, for plaintiff/appellant

John T. Richer, D. Kenyon Williams, and Christopher J. Gnaedig, Hall, Estill, Hardwick, Gable, Golden & Nelson, P.C., Tulsa, OK, for defendants/appellees

COMBS, J.:

¶1 This cause concerns an action to foreclose a materialman's lien filed on property located in Garvin County, Oklahoma. Wynnewood Refining Co., LLC (Wynnewood or owner) is the owner of an oil refinery located in Garvin County, Oklahoma (Property). On or about March 2, 2004, the owner, what is now Wynnewood, entered into an Environmental Services Agreement with the original contractor, what is now WSP USA, Inc. (WSP or original contractor), to provide labor and materials to improve the Property.1 Thereafter, on or about August 28, 2018, WSP entered into a subcontract with Techsas, Inc., (Techsas or subcontractor) to provide labor and materials to improve the property (Techsas Contract). The Techsas Contract contained a waiver clause whereby Techsas waived all liens and claims, statutory or otherwise, resulting from the labor done and materials furnished on the project. The waiver clause also required Techsas to insert a similar waiver clause into any subcontracts it engages in. The parties agree that sometime in 2019, Techsas entered into a subcontract (H2K Contract) with the plaintiff/appellant, H2K Technologies, Inc., (H2K or materialman) to provide materials and labor to improve the property.

¶2 WSP received a total of three invoices from Techsas for the work it performed on the project and claims to have paid the first and second invoices on January 7, 2019 and February 11, 2019, respectively. Techsas filed for bankruptcy protection on February 13, 2019, two days after the second invoice was paid. Thereafter, H2K sent an invoice to Techsas dated February 14, 2019, in the amount of $116,280.00. In addition, H2K sent an invoice to WSP Environment & Energy (WSP E&E) on March 5, 2019, in the amount of $4,500.00.2 Each invoice contained a provision for charging a monthly interest rate of 1.5% on past due invoices. When Techsas failed to pay H2K, the materialman served a preliminary lien notice on Wynnewood, Techsas and WSP which indicated the estimated price of the provided labor, services, equipment or materials was $120,780.00. On May 6, 2019, H2K filed a lien statement in the office of the Garvin County Clerk. The statement claims a lien in the amount of $120,780.00 plus interest after March 6, 2019, at a monthly rate of 1.5%, plus attorney fees and filing costs. On September 20, 2019, H2K filed its petition to foreclose the lien.

¶3 On January 3, 2020, the defendants, WSP, as principal, and Fidelity and Deposit Company of Maryland, as surety, submitted a bond in the amount of $150,975.00 to discharge the lien pursuant to 42 O.S. Supp. 2019, § 147.1. WSP and Fidelity were substituted as defendants and H2K dismissed Wynnewood as a defendant in this action which resulted in an in rem action against the bond. After H2K objected to the bond amount, an additional $14,535.00 was placed into a trust account.

¶4 Both plaintiff and defendants filed competing motions for summary judgment. On February 26, 2021, the trial court ruled in favor of the defendants' motion and denied the plaintiff's motion. First, it ruled that although the Techsas Contract was governed by New York law, which prohibits waiver clauses, contract provisions that subject a construction contract to the laws of another state are against public policy in Oklahoma pursuant to 15 O.S. 2011, § 821(B)(1). Next, the trial court ruled H2K is charged with constructive notice of the subcontract between Techsas and WSP and because Techsas had waived its rights to all liens and claims, H2K could not "obtain any greater rights" than the subcontractor Techsas. It held, H2K did not have a legal right to impress a lien on the Property and H2K's May 6, 2019 lien statement did not constitute a valid or proper lien. The trial court exonerated and discharged the bond and directed the surety to return all sums to WSP. The court also released the amounts held in the trust account to WSP. Enforcement of the order was stayed by the court for ten days.

¶5 H2K filed its petition in error on March 19, 2021. It asserted it had a valid lien for labor and materials and Techsas could not waive H2K's statutory right to a lien without H2K's knowledge and consent. H2K further asserted 15 O.S. 2011, § 821(B)(1) provides it is against public policy of this state for a construction contract to have "[a] provision, covenant, clause or understanding in, collateral to or affecting a construction contract that disallows or alters the rights of any contractor or subcontractor to receive and enforce any and all rights under this act."3 On March 22, 2021, this Court retained the matter on its own motion.

STANDARD OF REVIEW

¶6 Although a trial court in making a decision on whether summary judgment is appropriate considers factual matters, the ultimate decision turns on purely legal determinations, i.e., whether one party is entitled to judgment as a matter of law because there are no material disputed factual questions. Carmichael v. Beller, 1996 OK 48, ¶2, 914 P.2d 1051, 1053. Therefore, as the decision involves purely legal determinations, the appellate standard of review of a trial court's grant of summary judgment is de novo. Id.

ANALYSIS

¶7 The trial court held, as a matter of law, H2K had no right to file a lien. Therefore, the court determined the many objections to the alleged uncontroverted facts in the parties' motions for summary judgment were not material to the resolution of the issues presented.4 H2K does not assert on appeal that the trial court erred in granting summary judgment because there were disputed genuine issues of material fact. However, because today we reverse the order granting summary judgment, we remand the matter to the trial court wherein the parties will have an opportunity to conduct discovery and pursue a trial if necessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BAUGHMAN v. WORLD ACCEPTANCE CORPORATION
2025 OK 57 (Supreme Court of Oklahoma, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2021 OK 59, 503 P.3d 1177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h2k-technologies-v-wsp-usa-okla-2021.