Maddux v. Buchanan

92 S.E. 830, 121 Va. 102, 1917 Va. LEXIS 14
CourtCourt of Appeals of Virginia
DecidedJune 14, 1917
StatusPublished
Cited by11 cases

This text of 92 S.E. 830 (Maddux v. Buchanan) is published on Counsel Stack Legal Research, covering Court of Appeals of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maddux v. Buchanan, 92 S.E. 830, 121 Va. 102, 1917 Va. LEXIS 14 (Va. Ct. App. 1917).

Opinion

Kelly, J.,

delivered the opinion of the court.

James A. Buchanan entered into a written agreement with John H. Nolan, a building contractor, whereby the latter agreed to furnish for the former all the material and labor necessary for the erection of a costly residence. After the work was less than half done, and after less than half of the total contract price had been paid, Nolan failed financially and surrendered the contract and the work done and to be done thereunder to Buchanan, who proceeded to carry the same to completion under the following provision of the contract:

“Art. V. Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after three days’ written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools and appliances thereon, and to employ any other person or persons 'to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor he shall not be entitled to any further payment under this contract until the said work shall be wholly finished, at which [106]*106time if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the .owner in finishing the work, such excess shall be paid by the owner to the contractor; but if such expense shall exceed such unpaid balance the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided either for furnishing materials or for finishing the work, and any balance incurred through such default, shall be audited and certified by the architect, whose certificate thereof shall be conclusive upon the parties.”

There is some controversy as to whether this clause in the contract was strictly complied with, but it is entirely clear from the evidence that there was such compliance, and the certificate of the architect, made after the building was completed, showed that Nolan was indebted to Buchanan in the sum of $4,756.49.

The appellants, Maddux and others, were sub-contractors who had furnished labor and material to Nolan, and to whom he was indebted at the time of his failure and surrender of the contract. Having filed their claim of liens in conformity with section 2477 of the Code of Virginia, and given notice thereof to Buchanan, they proceeded to institute their separate suits in equity to enforce the same. These suits were brought before the building was completed, and Buchanan filed, first, an original answer in each case, exhibiting his contract, denying any indebtedness whatever to the general contractor, and averring that it would cost more than the balance of the contract price to finish the work, and, later, a supplemental answer exhibiting the certificate of the architect and showing a balance due from the contractor of $4,756.49.

The several causes, which were heard together, were referred to a commissioner for a report upon a number of questions, but the gist of the inquiry, so far as it affects this appeal, was whether Buchanan owed Nolan anything at the time the contract was surrendered, or would owe him any[107]*107thing when the work was completed. The commissioner, upon evidence which was extensive and thorough, made a report fully sustaining the position assumed by Buchanan in his answer. Complainants excepted to this report and the circuit court, after mature consideration, overruled the exceptions, confirmed the report, and dismissed the bills at the cost of complainants.

The decree was right in all respects. It, of course, comes to us with the strong presumption in its favor attaching to a decree by which the trial court has confirmed the report of a commissioner upon a question of fact (Hall v. Hall, 104 Va. 773, 776, 52 S. E. 557, and cases cited) ; but, independently of that presumption, the evidence satisfies us that there was no time after notice- to General Buchanan of the claim of the appellants when he was indebted in any amount to the general contractor; and this is necessarily the end of the case. Laborers and material men are favored by the statute, but not to the extent of requiring the owner of property to pay the same bills twice, once to the builder with whom he has contracted, and again to parties with whom he has no contractual relations. Our present mechanic’s lien laws deal fairly with both the owner and the sub-contractor, requiring the owner, after notice, to withhold from the general contractor enough to pay the sub-contractor, provided however, “the same does not exceed the sum in which the owner is indebted to the general contractor at the time the notice is given, or may thereafter become indebted by virtue of his contract with said general contractor.” (Code, sections 2477, 2479). The sub-contractor will generally be as well situated as the owner to determine whether the general contractor is solvent. To do more than our statute has done in relieving the sub-contractor of risk in this respect would be to make the owner of a building the guarantor of all the bills incurred thereon by the general contractor. This would unjustly, if not unconstitutionally, abridge the right of contract. The statute [108]*108was designed to protect sub-contractors, and creates a liability which would not otherwise exist, but the terms must be met before its benefits can be enjoyed. In other words, as this court has said in former decisions, “the owner is under no obligation to protect the interest of the subcontractor, except where the latter has complied with the law and thus placed himself in a position to demand protection from the owner.” (Schrieber V. Bank, 99 Va. 257, 262, 38 S. E. 134, 135; University of Va. v. Snyder, 100 Va. 567, 581, 42 S. E. 337; Steigleder v. Allen, 113 Va. 686, 691, 75 S. E. 191.)

The authority of the case of S. V. R. R. Co. v. Miller, 80 Va. 821, relied upon by counsel for appellants, in so far as it is at variance with the view here expressed, has been entirely destroyed by the subsequent change in the statute, which now very justly limits the liability of the owner to his indebtedness to the general contractor at or after the time he received notice of the sub-contractor’s claim.

In Burks’ Pleading and Practice, page 821, section 421, the author, after stating, as pointed out by counsel for appellants, that the sub-contractor is given by the statute three different methods by which he may secure the payment of the amount due him, namely, (1) by filing an independent lien, (2) by taking steps to hold the owner personally liable, and (3) by invoking the benefit of the general contractor’s lien, makes it perfectly clear that each of these three methods is dependent upon and limited by the indebtedness of the owner to the general contractor.

.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H2K TECHNOLOGIES v. WSP USA
2021 OK 59 (Supreme Court of Oklahoma, 2021)
Butler v. Creative Design Builders, Inc.
24 Va. Cir. 362 (Louisa County Circuit Court, 1991)
Alessandrini v. Mullins
16 S.E.2d 323 (Supreme Court of Virginia, 1941)
Coleman v. Pearman
165 S.E. 371 (Supreme Court of Virginia, 1932)
Boulia-Gorrell Lumber Co. v. East Coast Realty Co.
148 A. 28 (Supreme Court of New Hampshire, 1929)
National Supply Co. v. Weaver
248 P. 353 (Wyoming Supreme Court, 1926)
Electric Transmission Co. v. Pennington Gap Bank, Inc.
119 S.E. 99 (Supreme Court of Virginia, 1923)
Richmond College v. Scott-Nuckols Co.
98 S.E. 1 (Supreme Court of Virginia, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
92 S.E. 830, 121 Va. 102, 1917 Va. LEXIS 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maddux-v-buchanan-vactapp-1917.