Electric Transmission Co. v. Pennington Gap Bank, Inc.

119 S.E. 99, 137 Va. 94, 1923 Va. LEXIS 140
CourtSupreme Court of Virginia
DecidedSeptember 20, 1923
StatusPublished
Cited by7 cases

This text of 119 S.E. 99 (Electric Transmission Co. v. Pennington Gap Bank, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electric Transmission Co. v. Pennington Gap Bank, Inc., 119 S.E. 99, 137 Va. 94, 1923 Va. LEXIS 140 (Va. 1923).

Opinion

Prentis, J.,

delivered the opinipn of the court.

[97]*97The Electric Transmission Company of Virginia, hereafter called the owner, entered into a contract with Jewell & Son Company (a corporation), hereafter called the contractor, for the construction of an addition to the owner’s power plant at “The Pocket,” in Lee county, Virginia, for the sum of $54,800.00. The contractor was required to give bond for the faithful performance of its contract. It gave such bond in the penalty of $55,000.00, with the Aetna Accident and Liability Company, of Hartford, Conn., hereafter called the surety, as its surety, conditioned to indemnify the owner “against any loss directly arising by reason of the failure of the principal (contractor) to faithfully perform said contract.” The bond further provides, “that in the event of any default, the surety shall have the right at its option to proceed, or procure others to proceed, with the performance of such contract; that if the surety does proceed or procure others to proceed with the performance of such contract any and all monies or property that may at the time of such default be due, or that thereafter may become due to the principal (contractor) under said contract shall become payable to the surety and shall be paid to it; and the surety shall be subrogated to all of the rights of the principal (contractor). The contractor, after having partly performed its contract, abandoned it. At the time of such abandonment $38,824.61 had been paid on account of the gross contract price of $54,800.00. The owner had the right to retain a certain proportion of the amounts falling due from time to time to the contractor under the contract until it had been fully performed, and had retained the sum of $4,127.88 of these partial payments. The surety, when notified of the contractor’s default, exercised its option to proceed itself with the completion of the contract, and thus entitled itself to collect the resi[98]*98due of the contract price which otherwise would have been due by the owner to the contractor. The surety procured the completion of the building at a cost greatly exceeding the balance due by the owner on the original contract price. At or after the time when the contractor defaulted, a number of mechanics liens were filed by the subcontractors who had furnished labor and material for the structure. Before the contractor abandoned the work, he borrowed $1,500.00 from the Pennington Gap Bank, and secured it by deed of trust on certain machinery, appliances and material which were then in use or about to be used by the contractor, and were at that time on the premises. This deed was recorded on the 12th day of February, 1917, and before the surety exercised its option to take possession of such property and complete the contract.

The Norton Hardware Company levied an attachment on February 7, 1917, on certain machinery and material of the contractor on the premises of the owner. At or about this time a receiver for the contractor was appointed in the Superior Court of Cincinnati, Hamilton county, Ohio, and by order of that court of the 13th day of February, 1917, the receiver was directed to transfer, assign and set over to the surety “all of the right, title and interest of the said The John A. Jewell & Son Company in and to its said contract with the said The Electric Transmission Company of Virginia, and that said The Aetna Accident and Liability Company, of Hartford, Connecticut, be empowered to exercise all rights that they may have under said application, contract and bond, and that said surety company be subrogated to all of the rights of the said The John A. Jewell & Son Company under said contracts.”

There are other incidental facts, but we believe that these are all that the record presents which are signifi[99]*99cant. The controversy is not with the owner, but arises between the creditors of the contractor and the surety. These creditors assert liens either upon the property of their debtor, the contractor, or upon the fund due by the owner upon the completion of the work. On the other hand the surety denies the validity of all such claims, and asserts its right to all the machinery, appliances and materials of the contractor which were found on the premises, which it used in completing the contract, as well as to the entire balance of the contract price due by the owner on the completion of the contract.

The issues thus raised were referred to a commissioner, who reported that the claimants of such liens were entitled to be paid out of the balance due by the owner for the completion of the contract. As these claims aggregated $4,607.03, the balance, $15,975.39, due by the owner, is ample for their satisfaction.

There were exceptions to the report. The court disagreed with the commissioner and held that the mechanics’ liens were liens on the sum of $4,127.88 retained by the owner, that being the amount of the percentage which had been retained by the owner at or about the time of the default and when the mechanics’ liens were filed and perfected. It also adjudged that the debt of the Pennington Gap Bank, Incorporated, by virtue of its deed of trust, and the debt of the Norton Hardware Company, by virtue of its attachment, were valid liens against the sum just stated as due by the owner, as well as upon material and equipment found by the surety on the premises and used, which belonged to the contractor, which property was found to be worth at least the sum of $3,391.72. The report of the commissioner, except as modified by the decree, was confirmed, and judgments were entered [100]*100against the owner in favor of the several claimants for amounts aggregating $4,127.88, so found to be due, as above stated, and for the balance then remaining due to the Pennington Gap Bank, which such fund was insufficient to satisfy, as well as for the costs, also gave judgment against the surety.

It is this decree which is here under review.

The assignments of error are nineteen in number, but they all depend upon the claim that the surety stands in the place of the owner, and is subrogated to .all of its legal rights as against these claimants. That inasmuch as it took a very much larger amount of its money than the balance which was due by the owner to the contractor on the original contract, to complete the building, therefore none of these claims can be paid out of the fund due by the owner, and that there is no fund out of which they can be paid. For this view, the case of Maddux v. Buchanan, 121 Va. 102, 92 S. E. 830, is cited. The rule there established is perfectly sound, and cannot now be fairly questioned. Indeed, it has since been made statutory by Code 1919, section 6432, which expressly provides that if the owner is compelled to complete his building in consequence of the failure or refusal of the general contractor to do so, the amount expended by the owner for such completion shall have priority over all mechanics’ liens which have been or may be placed on such building, either by the general contractor or any subcontractor. If, therefore, this surety of the contractor can be held entitled to all of the rights of the owner when it exercised its right to complete the contract, its contention is sound.

While this question appears never to have been raised in Virginia, there are precedents in other jurisdictions which clearly show that the contention is unsound.

[101]*101The germ of the true rule here applicable is found in Heckmann v. Pinckney, 81 N. Y.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Fidelity Insurance v. Ashland Lumber Co.
463 S.E.2d 664 (Supreme Court of Virginia, 1995)
Esposito v. Chandler
24 Va. Cir. 143 (Loudoun County Circuit Court, 1991)
Graves Construction Co. v. Rockingham National Bank
263 S.E.2d 408 (Supreme Court of Virginia, 1980)
Hudson v. Hudson
5 S.E.2d 912 (Supreme Court of Georgia, 1939)
MacDonald, Etc. v. Calumet Supply Co.
19 N.E.2d 567 (Indiana Supreme Court, 1939)
David Lupton's Sons Const. Co. v. Hugger Bros. Const.
148 So. 610 (Supreme Court of Alabama, 1933)
DeWitt v. Coffey
143 S.E. 710 (Supreme Court of Virginia, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
119 S.E. 99, 137 Va. 94, 1923 Va. LEXIS 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electric-transmission-co-v-pennington-gap-bank-inc-va-1923.