Maneely v. City of New York

119 A.D. 376, 105 N.Y.S. 976, 1907 N.Y. App. Div. LEXIS 3947
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 17, 1907
StatusPublished
Cited by23 cases

This text of 119 A.D. 376 (Maneely v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maneely v. City of New York, 119 A.D. 376, 105 N.Y.S. 976, 1907 N.Y. App. Div. LEXIS 3947 (N.Y. Ct. App. 1907).

Opinion

Laughlin, J.

This is an action to foreclose a mechanic’s .lien, filed against moneys due or to' grow due the defendants, the surety companies, which, for brevity, will be designated the fidelity and bonding companies respectively, on a contract between the Armstrong & > Bolton Company and the city of New York,, bearing date, .the 20th. day of April, 1899, for the construction of the high and low-pressure steam plant, dynamo and electric lighting plant and. .'kitchen in the new city prison at Centre, Franklin and Leonard streets, for tile gross sum of $93,325. The Armstrong &.Bolton Company abandoned the work and the fidelity and bonding companies performed it as sureties. " ,

The Armstrong & Bolton Company, the original contractors, abandoned the contract in March, 1900. The fidelity and bonding companies were duly notified of the default of their principal and called upon to perform. They thereupon took charge of the work, and through the defendant Wood, who was their duly authorized. agent, and, in his name, made a sub-contract.with the Barron & Cooke Heating and Power Company, which will be referred to [379]*379as the Barron & Cooke Company, on the 24th day of April, 1901, for completing the stéamfitting for the high and low pressure steam plant, according to the plans and specifications, for $8,548, and the defendant Kieley became surety for the contractor to the extent of $5,000. The Parrón & Cooke Company commenced the work, and after receiving $4,093 thereon, which equaled or exceeded the amount .then due and payable according to the terms of the contract, defaulted. Wood thereupon gave notice to the Parrón & Cooke Company, pursuant to the contract, that unless it prosecuted the work diligently and tb his satisfaction within eight days, he would annul the contract; and he also gave Kieley as surety notice and called upon him to perform. After the expiration of eight days Wood, assuming to act under -the terms of the contract, annulled it. Kieley then had an interview with Wood and it was agreed that he should complete the contract and should receive therefor the sum of $4,454,40, being the balance of the contract price unpaid to his principal, the same as the principal would have received if it had performed. He performed the work, hut filed no lien; and he has recovered against the fidelity and bonding companies the sum of $5,554.28, being the balance unpaid on the contract, and interest thereon from the date of completion, March 31, 1903, together with costs and an extra allowance of $222. The trial court found that Kieley, the surety for the Parrón & Cooke Company, completed under a new and independent contract and on that is the theory on which the entire balance of the fund was awarded to him. Plaintiff’s intestate and defendant Daniels furnished materia] and performed labor for the Parrón & Cooke Com-. pany, for which they filed liens, and their appeal presents their contention that it should have been held that Kieley completed as assignee of or as surety for his principal and under its contract; and that their liens attached to the moneys thus earned in preference to any claim on his part. The fidelity and bonding companies also appeal from the judgment in favor of Kieley and claim that his recovery against them was unauthorized in this aetion, bec&us& he filed ho lien and they also claim that his answer is insufficient; but they do not admit that they are. liable for the claims embraced in the liens of the plaintiff and Daniels.

Wbod, representing the fidelity and bonding companies, also con[380]*380tracted. with the Eddy Electric Manufacturing Company, which we will designate as the Eddy ■ Company, for the electric work, including the furnishing of electrical appliances, embraced in the original contract, and agreed to pay therefor the' sum of $10,000. The Frank M. Pierce Engineering Company, hereinafter designated the Pierce Company, performed part of the work and furnished some of the material for the Eddy Company for which, it was not paid, and it filed a lien therefor. This action was not commenced. nntil the 4th day of April, 1903. On the 18th day of November, 1902, more than four months prior to the commencement of the action, that lien was discharged by an order of. the court made on the application of the fidelity and bonding companies, on their own undertaking with the City Trust, Safe Deposit and. Surety Company of Philadelphia as surety. The undertaking was in the form- required by the statute

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vogel Bros Contracting Corp. v. Town of Oyster Bay
50 Misc. 2d 401 (New York Supreme Court, 1966)
Lehmann v. Kingston Plaza, Inc.
44 Misc. 2d 63 (New York Supreme Court, 1964)
R. E. Crist, Inc. v. Lasker-Goldman Corp.
27 Misc. 2d 552 (New York Supreme Court, 1960)
Nassau Suffolk Lumber & Supply Corp. v. Bruce
177 Misc. 825 (New York County Courts, 1941)
MacDonald, Etc. v. Calumet Supply Co.
19 N.E.2d 567 (Indiana Supreme Court, 1939)
Wilson v. Moon
240 A.D. 440 (Appellate Division of the Supreme Court of New York, 1934)
David Lupton's Sons Const. Co. v. Hugger Bros. Const.
148 So. 610 (Supreme Court of Alabama, 1933)
Smith v. Vara
136 Misc. 500 (New York County Courts, 1930)
Parisi v. Hubbard
226 A.D. 280 (Appellate Division of the Supreme Court of New York, 1929)
National Surety Co. v. Wallace
221 A.D. 506 (Appellate Division of the Supreme Court of New York, 1927)
John Comolli & Co. v. Margolies
130 Misc. 894 (New York Supreme Court, 1927)
Anderson v. Hayes
215 A.D. 109 (Appellate Division of the Supreme Court of New York, 1926)
Atlantic Terra Cotta Co. v. Rubenfield Construction Corp.
126 Misc. 279 (New York Supreme Court, 1926)
Lasky v. State
126 Misc. 360 (New York Supreme Court, 1925)
Electric Transmission Co. v. Pennington Gap Bank, Inc.
119 S.E. 99 (Supreme Court of Virginia, 1923)
Piper v. New York State Railways
185 A.D. 184 (Appellate Division of the Supreme Court of New York, 1918)
Conway v. Bluff Point Stone Co.
180 A.D. 835 (Appellate Division of the Supreme Court of New York, 1917)
Harley v. Plant
149 A.D. 719 (Appellate Division of the Supreme Court of New York, 1912)
Wood Manufacturing & Realty Co. v. Johnstone
148 A.D. 747 (Appellate Division of the Supreme Court of New York, 1912)
Palmer Lumber Co. v. Stern
140 A.D. 680 (Appellate Division of the Supreme Court of New York, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
119 A.D. 376, 105 N.Y.S. 976, 1907 N.Y. App. Div. LEXIS 3947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maneely-v-city-of-new-york-nyappdiv-1907.