This text of 221 A.D. 506 (National Surety Co. v. Wallace) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Wallace, 221 A.D. 506, 224 N.Y.S. 684, 1927 N.Y. App. Div. LEXIS 6483 (N.Y. Ct. App. 1927).

Opinion

Taylor, J.

In June, 1923, James J. Doyle made a contract with the county of Herkimer for improving a county and town road. The respondent, National Surety Company, went upon the contractor’s bond (in the usual form) as surety for his faithful performance of the contract: The work was to be completed before November 1, 1924. May 12, 1926, the county superintendent of highways served a notice on the contractor that he had failed so to proceed as to insure completion on time, and that he had forfeited his right to complete. Twelve days later the superintendent served a notice on the contractor and the surety company, referring to the former notice, to the effect that the contractor had forfeited all his rights to complete under the contract and that it had been canceled. The surety company was also notified that it must complete the contract and that it would be held responsible for its completion and for damages on account of the default of Doyle.

The estimated cost of the work was $130,544. On May 24, 1926, Doyle had been paid on account $86,719.44. There was still due him $6,070.78, and $10,294.52 had been retained by the county as a percentage. By September 24, 1926, liens in the amount of over $42,000 had been filed on claims for materials and labor furnished to Doyle.

On June 30, 1926, the surety company made a contract with one Hopkins for the immediate commencement and completion of the improvements. In this contract matters which had been involved in the Doyle-County of Herkimer contract were mentioned in the Whereas ” clauses, and the following provisions were incorporated:

“ The aforesaid contract between the said James J. Doyle and the County of Herkimer, New York, together with the plans and specifications and alterations thereof as provided therein and herein, and the bond aforesaid of the National Surety Company are hereby referred to and made a part of this contract with the same force and effect as though fully set forth herein. * * *
The party of the second part hereby agrees to complete, and [508]*508at the item prices hereinafter set forth, the improvement of said road in a good and workmanlike manner in accordance with the said [Doyle-Herkimer County] contract, plans and specifications therefor * * *.
It is understood and agreed that second party shall have the free use of all tools, machinery, equipment, appliances and materials of the former contractor now on the said road. * * *
Upon the execution and delivery of this contract, party of second part agrees to take immediate possession of the above mentioned equipment in the name of the party of the first part.” On August 24, 1926, the surety company consented to substantial amendments of the original plans and specifications and entered into a contract with the county of Herkimer. In this contract occur the following provisions:
Whereas, on May 24th, 1926, the County Superintendent of Highways of Herkimer County declared said [original] contract forfeited by the said Doyle and that the same was and had been cancelled, and served notice of such forfeiture and cancellation on National Surety Company, as surety, and demanding that it proceed with the completion of said contract; and
“ Whereas, The National Surety Company, as surety, and in accordance with said demand, has started work for the completion of said contract, * * *
“ Party of the first part, National Surety Company, hereby consents to the amendment to plans and specifications, in accordance with and as particularly shown on schedule hereto attached and made a part hereof, with the same force and effect as if the original plans and specifications had been so written, and agrees to furnish all labor and material provided for in said schedules hereto attached and forming part of this agreement, and at the prices therein set out in accordance with the terms of the said contract between said Doyle and Herkimer County. * * *
“ The County of Herkimer agrees to pay to said National Surety Company, party of the first part, the prices mentioned in this agreement and plans and schedules hereto attached for the quantities of labor and material actually used and performed estimated to amount to a total of $151,856.30, less the amount heretofore paid said Doyle, namely, in the same manner as is provided in the said contract between Doyle and the County of Herkimer, hereinbefore referred to.
“ 3. Except as herein otherwise specifically provided, the said contract between the County of Herkimer, New York, and J. J. Doyle shall remain in full force and effect, except as affected by the notices of cancellation heretofore served as hereinabove referred to.”

[509]*509On August thirty-first a new and supplemental contract was made between the surety company and Hopkins, making the amended plans and specifications a part of their old contract.

The county later recognized an obligation to the surety company under its estimate No. 19 for $22,059.87. But on November 15, 1926, under estimate No. 20, for $17,118.54, payment was refused by the county, although there were sufficient funds in the superintendent’s hands to make payment.

On February 7, 1927, a peremptory mandamus order was made ordering the county of Herkimer to pay the said amount of $17,118.54, upon presentation of the estimate. The original contract between Doyle and the county provided: “ The owner may retain out of the moneys due or to grow due the Contractoi, sufficient moneys to pay all persons who shall do work or furnish materials for the party of the first part and shall have filed a statement or claim therefor with the County Superintendent of Highways, which moneys may be retained by the party of the second part until such claims or any liens that may be filed in pursuance to law shall have been fully paid.”

It appears that prior to January 29, 1927, the date of the application for the mandamus order, actions had been commenced and were pending in the Supreme Court of the State of New York for the foreclosure of all the liens which had been filed, except two — and that three months had not elapsed since those two were filed.

It also appears that the contractor is insolvent, and has not sufficient means or property to pay the said claims of the lienors, if .the same should be established, and that the amount to which either the petitioner or the lienors are entitled has not been established.

Defendant, appellant, makes the claim that the surety proceeded to complete the contract in the place of its principal and that the county had the right to retain the money in the county treasurer’s hands which the petitioner sought to obtain until all claims and liens had been established or dismissed or discharged.

The appellant states that he does not expect to obtain a decision establishing the relative rights of the lienors, the assignees, the surety, the contractor and the county, but only that the mandamus order should be reversed and vacated and the county treasurer advised to hold all money due, earned and unpaid until the relative rights of the parties claiming to be legally interested have been adjusted by a proper court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Village of North Hills v. Johnson
37 Misc. 2d 168 (New York Supreme Court, 1962)
Cedar Lane Heights Corp. v. Marotta
17 A.D.2d 651 (Appellate Division of the Supreme Court of New York, 1962)
Ellsworth, Barrows & Co. v. Ward
255 A.D. 91 (Appellate Division of the Supreme Court of New York, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
221 A.D. 506, 224 N.Y.S. 684, 1927 N.Y. App. Div. LEXIS 6483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-co-v-wallace-nyappdiv-1927.