Van Clief v. . Van Vechten

29 N.E. 1017, 130 N.Y. 571, 42 N.Y. St. Rep. 736, 85 Sickels 571, 1892 N.Y. LEXIS 961
CourtNew York Court of Appeals
DecidedFebruary 9, 1892
StatusPublished
Cited by123 cases

This text of 29 N.E. 1017 (Van Clief v. . Van Vechten) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Clief v. . Van Vechten, 29 N.E. 1017, 130 N.Y. 571, 42 N.Y. St. Rep. 736, 85 Sickels 571, 1892 N.Y. LEXIS 961 (N.Y. 1892).

Opinions

*577 Yann, J.

The statute applicable to the subject of this action is chapter 342 of the Laws of 1885, as it stood before it was amended by chapter 316 of the Laws of 1888. As we construe that statute and read the decisions made thereunder, as well as those made under similar statutes, we think that the following rules determine the extent to which a mechanics’ lien, filed by a sub-contractor or a material-man, attaches to the locus in qyüo:

1. If anything is due to the contractor, pursuant to the terms of the contract, when the lien is filed, it attaches to that extent.

2. If nothing is due to the contractor according to the contract, when the lien is filed, but a certain amount subsequently becomes due thereunder, the lien attaches to the extent of that sum.

3. If nothing is due to the contractor pursuant to the contract, when the lien is filed and he abandons the undertaking without just cause, but the owner completes the building according to the contract and under a provision thereof permitting it, the lien attaches to the extent of the difference between the cost of completion and the amount unpaid when the lien was filed. (Larkin v. McMullin, 120 N. Y. 206; Powers v. City of Yonkers, 114 id. 145; Mayor, etc., v. Crawford, 111 id. 638; Graf v. Cunningham, 109 id. 369; Taylor v. Mayor etc., 83 id. 625; Heckmann v. Pinkney, 81 id. 211; Gibson v. Lenane, 94 id. 183; Rodbourn v. Seneca Lake Grape & Wine Co., 67 id. 215; Lombard v. Syracuse, B. & N. Y. R. R. Co., 55 id. 491; 15 Am. & Eng. Encyc. 78, 84.)

The first question presented for decision is whether there was anything due from the owner to the contractor, according to the terms of the contract, when the lien was filed. This depends on whether there is any evidence to support the finding of the referee that the plastering had been substantially finished at the time of the filing of the lien, for according to the contract, the third payment of $800 was to become due when the work had progressed to that extent. Evidence was given in behalf of the owner tending to show that it was worth *578 $200 to complete the plastering, and that the mason who did it was paid that amount. The witnesses for the plaintiffs, however, testified that it was worth much less. As the conflict in the evidence raised a question of fact, the version most favorable to the plaintiffs and most strongly tending to sustain the finding of the referee must be accepted as that upon which he acted.

The only witnesses for the plaintiffs as to the quantity or Value of the unfinished plastering were the defendants Newman, who as sub-contractors with Smalle, were engaged in doing the mason work when the lien was filed, and they stopped work on that account. One of these gentlemen testified in substance that the cornice had not been run nor the last coat put on the main hall; that the stairs were not up, so it was not plastered under the stairs; ” that he could not say that the plastering was all done in the second-story hall; that “ it was not finished, that is, it had not the last coat; ” and that it would cost from $20 to $25 to complete the plastering in the hall. The other sub-contractor testified that the last coat on the side walls of the parlor and the last coat in the entrance hall was not on and about forty feet of cornice work had not been run; that the stairs were not wholly up and not plastered; that the plastering was not done in the second-story hall, and of course, the plastering was not on all the stairs; ” “I have said four times there was no plastering done under the stair-cases and in the hall; ” that it was worth about $30 to finish the plastering.

All of the witnesses for the defendant testified that there was more plastering to be done, and that it would cost more than the sub-contractors stated in their testimony.

Although the referee found that the sum of $200 was paid for completing the plastering, he refused to find that it was fairly and reasonably worth that amount. The learned General Term apparently held that the plastering was not finished, because they say in their opinion that “ as between contractor and owner, nothing was due under the contract.” The third payment of $800 was not simply for the plastering, but for the plastering and all other work that necessarily preceded it, *579 after the completion of the exterior, which made the second payment due. The cost of completing the stairs must be added to the cost of completing the plastering, for the latter could not be done until the former had been done. The question of substantial performance depends somewhat on the good faith of the contractor. If he has intended and tried to comply with the contract and has succeeded, except as to some slight things omitted by inadvertence, he will be allowed to recover the contract price, less the amount necessary to fully compensate the owner for the damages sustained by the omission. (Woodward v. Fuller, 80 N. Y. 312; Nolan v. Whitney, 81 id. 648; Phillip v. Gallant, 62 id. 256, 264; Glacius v. Black, 50 id. 145; S. C., 67 id. 563, 566; Johnson v. DePeyster, 50 id. 666; Sinclair v. Tallmadge, 35 Barb. 602.)

But when, as in this case, there is a willful refusal by the contractor to perform his contract and he wholly abandons it, and after due notice refuses to have anything more to do with it, his right to recover depends upon performance of his contract, without any omission so substantial in its character as to call for an allowance of damages if he had acted in good faith. While slight and insignificant imperfections or deviations may be overlooked on the principle of de minimis non mrat lex, the contract in other respects must be performed according to its terms. When the refusal to proceed is willful the difference between substantial and literal performance is bounded by the line of de minimis. (Smith v. Brady, 17 N. Y. 173; Cunningham v. Jones, 20 id. 486; Bonesteel v. Mayor, etc., 22 id. 162; Walker v. Millard, 29 id. 375; Glacius v. Black, 50 id. 145; Catlin v. Tobies, 26 id. 217; Husted v. Craig, 36 id. 221; Flaherty v. Miner, 123 id. 382; Hare on Contracts, 569; Leake on Contracts, 821.)

In this sense the plastering was not substantially finished and there is no evidence to support the finding of the referee in that regard, for when three coats are required two will not suffice.' That is not substantially finished which requires a substantial sum to finish it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dworman v. New York State Division of Housing & Community Renewal
725 N.E.2d 613 (New York Court of Appeals, 1999)
Rure Associates, Inc. v. DiNardi Construction Corp.
917 F.2d 1332 (Second Circuit, 1990)
Carpenter v. Massachusetts Bonding & Insurance Co.
206 A.2d 225 (Supreme Judicial Court of Maine, 1965)
First National Bank v. Stoyanoff
390 P.2d 448 (Montana Supreme Court, 1964)
Louis Greenberg, Inc. v. Pioneer Syndicate, Inc.
284 A.D. 294 (Appellate Division of the Supreme Court of New York, 1954)
Cassino v. Yacevich
261 A.D. 685 (Appellate Division of the Supreme Court of New York, 1941)
Farm Supplies Corp. v. Goldstein
240 A.D. 330 (Appellate Division of the Supreme Court of New York, 1934)
Kohlmetz v. Amdoursky
227 A.D. 758 (Appellate Division of the Supreme Court of New York, 1929)
Gigliotti v. Jacksina
206 A.D. 368 (Appellate Division of the Supreme Court of New York, 1923)
Dinnie v. Lakota Hotel Co.
186 N.W. 248 (North Dakota Supreme Court, 1921)
Jacob & Youngs, Inc. v. Kent
129 N.E. 889 (New York Court of Appeals, 1921)
Lynch v. Culhane
129 N.E. 717 (Massachusetts Supreme Judicial Court, 1921)
Bullinger v. Interboro Brewing Co.
194 A.D. 205 (Appellate Division of the Supreme Court of New York, 1920)
Dempsey v. Mount Sinai Hospital
186 A.D. 334 (Appellate Division of the Supreme Court of New York, 1919)
Mansson v. Nostrand
183 A.D. 371 (Appellate Division of the Supreme Court of New York, 1918)
American Radiator Co. v. . City of New York
119 N.E. 391 (New York Court of Appeals, 1918)
McNulty Bros. v. . Offerman
116 N.E. 775 (New York Court of Appeals, 1917)
Chautauqua Institution v. Zimmerman
233 F. 371 (Sixth Circuit, 1916)
Borden Brick & Tile Co. v. Pulley
84 S.E. 513 (Supreme Court of North Carolina, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
29 N.E. 1017, 130 N.Y. 571, 42 N.Y. St. Rep. 736, 85 Sickels 571, 1892 N.Y. LEXIS 961, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-clief-v-van-vechten-ny-1892.