William F. Klingensmith, Inc. v. David H. Snell Landscape Contractor, Inc.

291 A.2d 56, 265 Md. 654, 1972 Md. LEXIS 988
CourtCourt of Appeals of Maryland
DecidedMay 19, 1972
Docket[No. 355, September Term, 1971.]
StatusPublished
Cited by15 cases

This text of 291 A.2d 56 (William F. Klingensmith, Inc. v. David H. Snell Landscape Contractor, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William F. Klingensmith, Inc. v. David H. Snell Landscape Contractor, Inc., 291 A.2d 56, 265 Md. 654, 1972 Md. LEXIS 988 (Md. 1972).

Opinion

Smith, J.,

delivered the opinion of the Court.

This is a dispute between a general contractor, appellant William F. Klingensmith, Inc. (Klingensmith), and its subcontractor, appellee David H. Snell Landscape Contractor, Inc. (Snell), on a job involving the construction of a playground at South Capitol and I Streets, S.W., in the District of Columbia.

When Klingensmith paid Snell only $11,125.04 of a $16,500.00 contract price for landscaping, Snell sued for the balance of $5,374.96. Klingensmith brought a counterclaim contending that it had incurred liability to the government by virtue of non-performance by Snell of its contract with Klingensmith. The trial judge (Shearin, J.) entered judgment in favor of Snell for the full amount it claimed. We shall remand the case without affirmance or reversal under Maryland Rule 871 for further proceedings on the issue of damages.

*656 The contract between the parties was in the nature of a letter to Snell on Klingensmith’s printed form advising that it accepted Snell’s “estimate * * * to Furnish material and labor to complete all Plant Material and Planting Work on the Construction of Playground at Randall Recreation Center * * * in accordance with the plans and specifications therefor prepared by National Park Service, Dept, of the Interior Architect, which [Snell had] examined, namely Specs for Landscaping and Construction of Playgrounds at Randall Recreation Center dated 26 May 1967; Drawings NCR 69.484-61 sheets 1 thru 10; Addendums 1 thru 3.” Snell signed acknowledging receipt of that acceptance.

On the subject of payment, the contract said:

“Payments of the above contract price are to be made as follows: 90% of work satisfactorily completed on or before the 20th of the following month. Remaining 10% upon acceptance of government completion.”

The contract had in it the comment that the “estimate [was] accepted with the express understanding that [Snell would] strictly comply with the terms and conditions [t] hereinafter set forth.”

In its declaration Snell said the contract was not fully performed on its part, stating that one large red oak tree was not installed and that items which did not meet contract specifications were yet another large red oak tree, five dogwood trees and two hawthorn trees. It claimed those items were “the difference between full and substantial performance by Plaintiff” of the contract. It is conceded that the contract of Klingensmith with the National Park Service was terminated. Snell claimed this termination made impossible further performance by it.

Klingensmith filed a counterclaim based upon the failure of Snell to plant 29 red oaks and its “not performing in accordance with plans and specifications prepared by the National Park Service, Department of the Interior,” *657 as a result of which Klingensmith said it “was charged $9680.00 for the replacement and planting of dead trees, bushes and plants.” The counterclaim was dismissed.

Klingensmith sees four areas in which the trial court erred, (1) “when it found that the contract between the parties consisted of three documents not including the specifications between [Klingensmith] and the U. S. Government,” (2) “as a matter of law when it found that the reference in the agreement between the parties to the specifications for landscaping and construction of the playground * * * included only the contents of [Snell’s] Exhibit No. 2,” (3) “in finding that [Snell] substantially performed the contract in that it was based on numerical quantities and not value,” and (4) “when it found that there was no time limit within which the contract was to be performed.” Somewhat obliquely it adds a fifth point when it concludes its brief with a request “that the case be remanded in order that appellant may litigate its counterclaim based on all material and relevant evidence that was erroneously excluded.” We shall not consider such a fifth point, however, because nowhere in its brief does Klingensmith contend that the trial judge erred in dismissing the counterclaim at the end of the whole case and it did not print as a part of its record extract that portion of the proceedings.

I and II

Both of these points are concerned with the same subject, alleged error on the part of the trial judge in refusing to admit into evidence the contract between Klingensmith and the U. S. Government to which Snell was not a party. He found the contract between Klingensmith and Snell consisted of the letter we have mentioned and the items referred to in it which we also mentioned, all of which were in evidence.

In support of its position that the trial court erred in making its finding as to what constituted the contract, Klingensmith cites Stewart v. American Bridge Co., 108 Md. 200, 69 A. 708 (1908). We do not see much comfort *658 for Klingensmith there. That was a controversy between the owner of a building and the contractor. One point of argument to our predecessors was the refusal of the trial court to admit into evidence the “general conditions” sent by the architects to persons who were invited to bid for the construction of the entire building. These related to a variety of subjects. They set out with much particularity a great number of obligations to be assumed by the builder to the owner. The Court said:

“There is nothing to connect the plaintiff with these conditions. They were not discussed by the parties, and it would be most unreasonable to suppose that the plaintiff intended to assume obligations and to be bound by conditions which have not the remotest bearing upon the subject matter of its contract with the defendants. It had agreed to furnish and erect all the cast iron, steel and ornamental iron work described in the contract in strict accordance with the plans and specifications prepared by Wyatt & Nolting, the architects, and to subject it, under the circumstances, to obligations of the nature specified in these ‘general conditions’ would be an unwarrantable extension of its duty under the contract.
“* * * Our conclusion, that the ‘general conditions’ cannot be imported into the contract of June 23rd, 1904, is supported by the principle of the decision in the case of The Baltimore & Ohio Railroad Company v. Stewart, 79 Md. 487.” Id. at 214-15.

In Baltimore & O.R.R. v. Stewart, 79 Md. 487, 29 A. 964 (1894), cited in Stewart, Stewart had entered into a contract with a railroad company for building a bridge. The memorandum said, “Baltimore and Ohio specifications to govern.” In the railroad’s regular form of construction contract there was a provision that the company might “at any time, suspend the execution of, or *659 annul, the contract, upon giving_days’ notice, without being liable for any loss or damage to the contractors.” Stewart had signed such a contract with the railroad some five years before. The company contended that it was entitled to cancel Stewart’s contract. Chief Judge Robinson said for our predecessors:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barksdale v. Wilkowsky
20 A.3d 765 (Court of Appeals of Maryland, 2011)
Jackson v. State
959 A.2d 84 (Court of Special Appeals of Maryland, 2008)
Hollingsworth & Vose Co. v. Connor
764 A.2d 318 (Court of Special Appeals of Maryland, 2000)
Batson v. Shiflett
586 A.2d 792 (Court of Special Appeals of Maryland, 1991)
Exxon Corp. v. Yarema
516 A.2d 990 (Court of Special Appeals of Maryland, 1986)
Steel Suppliers, Inc. v. Ehret, Inc.
486 A.2d 32 (Superior Court of Delaware, 1984)
Hudson v. Wakefield
645 S.W.2d 427 (Texas Supreme Court, 1983)
Kennedy v. State
421 A.2d 1376 (Court of Appeals of Maryland, 1980)
Schackow v. Medical-Legal Consulting Service, Inc.
416 A.2d 1303 (Court of Special Appeals of Maryland, 1980)
Della Ratta, Inc. v. American Better Community Developers, Inc.
380 A.2d 627 (Court of Special Appeals of Maryland, 1977)
Beahm v. Shortall
368 A.2d 1005 (Court of Appeals of Maryland, 1977)
Kapiloff v. Locke
348 A.2d 697 (Court of Appeals of Maryland, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
291 A.2d 56, 265 Md. 654, 1972 Md. LEXIS 988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-f-klingensmith-inc-v-david-h-snell-landscape-contractor-inc-md-1972.