Gray Construction, Inc. v. Medline Industries, Inc.

CourtDistrict Court, D. Maryland
DecidedJanuary 6, 2023
Docket1:19-cv-03405
StatusUnknown

This text of Gray Construction, Inc. v. Medline Industries, Inc. (Gray Construction, Inc. v. Medline Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gray Construction, Inc. v. Medline Industries, Inc., (D. Md. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

* GRAY CONSTRUCTION, INC. * * Plaintiff * * v. * * MEDLINE INDUSTRIES, INC. * * Defendant * Civil Case No.: SAG-19-03405

MEDLINE INDUSTRIES, INC. * * Third-Party Plaintiff * * v. * * YORK BUILDING PRODUCTS CO., INC., * et al. * Third-Party Defendants * * * * * * * * * * * * MEMORANDUM OPINION

This case arises from a dispute between Medline Industries, Inc. (“Medline”), the entity who sold Medline a property, York Building Products Co, Inc. (“York”), and various contractors and subcontractors, seeking to apportion costs relating to a failed retaining wall. Gray Construction, Inc. (“Gray”), a contractor hired by Medline to construct a distribution facility, sued Medline for breach of contract to recover payment owed. ECF 1. Medline filed counterclaims against Gray, along with third-party claims against Gray’s subcontractors, Allan Myers, L.P. (“Allan Myers”) and DGS Construction, LLC T/A Schuster Concrete Construction (“Schuster”), York, and York’s subcontractors, Morris & Ritchie Associates, Inc. (“MRA”) and Geo-Technology Associates, Inc. (“GTA”). ECF 51. York also filed a third-party counterclaim against Medline. ECF 106. Now pending before this Court are three motions in limine filed by certain third-party defendants seeking to exclude the expert testimony of Medline’s expert witness, Justin M. Protasiewicz.1 See ECF 196 (York); ECF 198 (GTA and MRA); ECF 204 (Allan Myers).

Medline has responded to each motion. See ECF 254, 215, 231, respectively. Each moving third- party defendant has replied. See ECF 260, 258, 263, respectively. Medline has also moved for leave to file a surreply to Allan Myers’s reply, ECF 267, and Allan Myers has opposed, ECF 272. This Court has reviewed the filings and finds that no hearing is necessary. See Loc. R. 105.6 (D. Md. 2021). For the reasons explained below, the third-party defendants’ motions to exclude will be DENIED in part and GRANTED in part, and Medline’s motion for leave will be DENIED.

I. BACKGROUND Medline is a privately held manufacturer and distributor of medical supplies, operating more than forty distribution centers in North America. On September 1, 2017, Medline purchased from York a 128.5-acre property in Cecil County, Maryland for the purpose of constructing a medical distribution facility. ECF 196-3. The Purchase and Sale Agreement required York to complete certain on-site work. Id. at 11. As later amended, this work included the design and construction of a retaining wall, mass grading, and installation of erosion and sediment controls. ECF 196-4 at 9–11. Medline and York agreed that the retaining wall would be constructed in accordance with a geotechnical report drafted by GTA. Id. at 9; see also ECF 196-8. York brought in a subcontractor, MRA, to provide site civil engineering services, such as preparing and revising

1 Several motions for full or partial summary judgment are also pending, along with some related motions seeking to file surreplies. Those motions will be addressed separately. the Major Site Plan and the Erosion & Sediment Control/Stormwater Management Plans. ECF 216-3; ECF 216-4. On February 22, 2018, Medline entered into a separate agreement with Gray to design and construct the distribution facility. ECF 196-5. To assist with its work, Gray brought in a

subcontractor, Allan Myers, to, inter alia, provide and install the asphalt pavement and stormwater conveyance system. ECF 196-6 at 37–39. York completed construction of the retaining wall around October/November 2017. ECF 201-18 at 4. Approximately one month after the wall’s construction, GTA observed cracks in it. Id. at 3. GTA conducted an initial investigation of the wall’s cracking and issued a report of its findings on December 14, 2018. ECF 201-21. GTA determined that the retaining wall failed because of hydrostatic (i.e., water) pressure behind the wall. ECF 201-21 at 7 (“It is our opinion that the wall movement has occurred due to an increase in hydrostatic pressure behind the 50-foot- deep reinforced zone, an increase in mass of the retained soil and a reduction of the shear strength due to the presence of water.”).

Medline, through legal counsel, retained an independent engineering firm, SESI, to investigate the failure of the retaining wall and to make recommendations about remediation. ECF 232-5. SESI reviewed documents related to the construction project and performed site walk- throughs on January 9, 2019 and February 2, 2019. ECF 232-6 at 8, 13. SESI produced a preliminary report on March 13, 2019, documenting its observations and conclusions. ECF 232- 6 (“Preliminary Report”). In SESI’s opinion, the wall failed due to a combination of factors including the buildup of hydrostatic pressure behind the wall. ECF 232-6 at 3. SESI recommended removal and reconstruction of the wall. Id. at 34. Medline followed SESI’s recommendation and SESI performed a forensic deconstruction of the wall in the spring of 2019. ECF 201-22. During this deconstruction, SESI documented its observations and provided its findings and conclusions in various reports: a May 15, 2019 report regarding the stormwater conveyance piping and structure, ECF 202-5 (“Stormwater Report”); a

July 31, 2019 report summarizing its pavement evaluation, ECF 17-8 (“Pavement Report”); and an August 1, 2019 report of its global evaluations, ECF 201-23 (“Global Evaluation Report”). More than two years later, SESI issued a Supplemental Global Evaluation Report. ECF 202-1 (“Supplemental Global Evaluation Report”). Mr. Protasiewicz served as the principal engineer and lead author of each report. During the deconstruction of the retaining wall, SESI uncovered a stormwater conveyance pipe that served to transport water from behind the retaining wall to a drainage basin in the southwest corner of the property. ECF 201-23 at 48–52. Based on its observations of the pipe, SESI concluded that the “stormwater runoff . . . was infiltrating into the bedding stone under the stormwater pipes via leaks in the pipes and structures, and from lateral infiltration of water from

the bioretention basin.” Id. at 52. SESI also observed the permeable nature of the asphalt installed by Allan Myers and sent samples of the asphalt off for testing by a third-party laboratory. ECF 17-8 at 3. Based on these and other findings, in its Supplemental Global Evaluation Report, SESI enumerated numerous alleged failings of the third-party and counterclaim Defendants that were a “direct and substantial cause of the failure of the retaining wall.” ECF 202-1 at 71–77, 77. SESI further concluded that the work of MRA, Allan Myers, York, and GTA was defective and “not performed with a reasonable degree of care, skill and ability which is normally employed by contractors in their industry and location.” Id. at 70, 76, 77. MRA, Allan Myers, York, and GTA now challenge the reliability of these conclusions and seek to exclude them from consideration.

II. LEGAL STANDARDS Federal Rule of Evidence 702 governs the admissibility of expert witness testimony. A qualified expert may give testimony if: (a) the expert’s scientific, technical, or other specialized knowledge will help the trier of fact to understand the evidence or to determine a fact in issue; (b) the testimony is based on sufficient facts or data; (c) the testimony is the product of reliable principles and methods; and (d) the expert has reliably applied the principles and methods to the facts of the case. Fed. R. Evid. 702. In essence, the trial court must ensure the proposed expert testimony “both rests on a reliable foundation and is relevant to the task at hand.” Daubert v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
General Electric Co. v. Joiner
522 U.S. 136 (Supreme Court, 1997)
Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
George Martin v. Fleissner Gmbh
741 F.2d 61 (Fourth Circuit, 1984)
Pugh v. Louisville Ladder, Incorporated
361 F. App'x 448 (Fourth Circuit, 2010)
Adams v. NVR Homes, Inc.
141 F. Supp. 2d 554 (D. Maryland, 2001)
Khoury v. Meserve
268 F. Supp. 2d 600 (D. Maryland, 2003)
Milanowicz v. Raymond Corp.
148 F. Supp. 2d 525 (D. New Jersey, 2001)
Oglesby v. General Motors Corp.
190 F.3d 244 (Fourth Circuit, 1999)
Cooper v. Smith & Nephew, Inc.
259 F.3d 194 (Fourth Circuit, 2001)
Fleur Bresler v. Wilmington Trust Company
855 F.3d 178 (Fourth Circuit, 2017)
Westberry v. Gislaved Gummi AB
178 F.3d 257 (Fourth Circuit, 1999)
Casey v. Geek Squad® Subsidiary Best Buy Stores, L.P.
823 F. Supp. 2d 334 (D. Maryland, 2011)
Kopf v. Skyrm
993 F.2d 374 (Fourth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Gray Construction, Inc. v. Medline Industries, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gray-construction-inc-v-medline-industries-inc-mdd-2023.