Gray Construction, Inc. v. Medline Industries, Inc.

CourtDistrict Court, D. Maryland
DecidedSeptember 30, 2020
Docket1:19-cv-03405
StatusUnknown

This text of Gray Construction, Inc. v. Medline Industries, Inc. (Gray Construction, Inc. v. Medline Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gray Construction, Inc. v. Medline Industries, Inc., (D. Md. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

GRAY CONSTRUCTION, INC.,

Plaintiff / Counterclaim Defendant,

v. Civil Action No.: GLR-19-3405

MEDLINE INDUSTRIES, INC.,

Defendant / Counterclaim Plaintiff.

Counterclaim Plaintiff,

v.

YORK BUILDING PRODUCTS CO., INC., ET AL.,

Counterclaim Defendants.

MEMORANDUM OPINION THIS MATTER is before the Court on Defendant/Counterclaim Plaintiff Medline Industries, Inc.’s (“Medline”) Motion to Join Counterclaim Defendants York Building Products Co., Inc. (“York”), Geo-Technology Associates, Inc. (“GTA”), Morris & Ritchie Associates, Inc. (“MRA”), Allan Myers, L.P. (“Allan Myers”), and DGS Construction, LLC (“Schuster”) (ECF No. 53); Counterclaim Defendants GTA’s and MRA’s Omnibus Response to Medline’s February 26, 2020 Filings, and Motion to Dismiss Amended Pleading (ECF No. 69); Counterclaim Defendant Allan Myers’ Motion to Dismiss the Counterclaim and Opposition to Medline’s Motion For Joinder (ECF No. 72); Counterclaim Defendant Schuster’s Motion to Dismiss First Amended Counterclaims or, in the Alternative, Motion For Summary Judgment (ECF No. 73); and Counterclaim Defendant York’s Motion to Dismiss, or, in the Alternative, Sever, Medline’s Amended Counterclaims Against York (ECF No. 85).1 The Motions are ripe for disposition, and no

hearing is necessary. See Local Rule 105.6 (D.Md. 2018). For the reasons outlined below, the Court will grant in part and deny in part Medline’s Motion to Join Counterclaim Defendants York, GTA, MRA, Allan Myers, and Schuster; deny GTA’s and MRA’s Motion To Dismiss Amended Pleading; deny Allan Myers Motion to Dismiss the Counterclaim; and grant in part and deny in part York’s Motion To Dismiss.

1 Also pending before the Court are several motions responsive to Medline’s Verified Answer to Complaint and Petition to Establish and Enforce Mechanic’s Lien, Counterclaim Against Gray Construction, Inc., and Third Party Claims (ECF No. 17): GTA & MRA’s Motion Dismiss Third-Party Complaint (ECF No. 32); York’s Motion Dismiss and Strike Third-Party Complaint (ECF No. 44); and Schuster’s Motion Dismiss Third- Party Complaint or, in the Alternative, Motion for Summary Judgment (ECF No. 50). These Motions will be dismissed as moot in light of Medline’s Amended Counterclaims and Counterclaim Defendants’ Responses thereto. The Court will also deny Plaintiff/Counterclaim Defendant Gray Construction, Inc.’s (“Gray”) Consent or Unopposed Motion for Telephonic Scheduling Conference (ECF No. 82) ) because a scheduling conference will come in due course following the disposition of the instant motions. As such, the Court will also deny Gray’s prior Motion for Telephonic Scheduling Conference (ECF No. 15) as moot. The Court will also grant nunc pro tunc York’s Motion to Withdraw its Motion to Dismiss and Strike Third-Party Complaint (ECF No. 74); therefore, York’s Motion to Dismiss and Strike Third-Party Complaint (ECF No. 44) will be denied as moot. Finally, the Court will deny as moot Schuster’s Motion to Stay (ECF No. 93). I. BACKGROUND2

A. Factual Background

Medline is a privately held manufacturer and distributor of medical supplies that operates more than forty distribution centers in North America. (Medline’s Am. Answer and Countercls. Against Gray, York, GTA, MRA, Allan Myers, Schuster [“Am. Countercl.”] at 10, ECF No. 51). In November 2017, Medline entered into a contract with York (the “Purchase and Sale Agreement”) through which it purchased 128.5 acres of vacant land in Cecil County, Maryland (the “Property”). (Id. ¶ 12; see Ver. Answer Compl., Countercl. and Third Party Cls. [“Original Answer”] Ex. A [“P&S Agmt.”], ECF No 17- 3). The Purchase and Sale Agreement required York to complete certain work on the site in order to “deliver the Property in pad ready condition for [Medline’s] proposed development” (the “Pad Ready Work”). (Am. Countercl. ¶ 14; see P&S Agmt. at 11). The Pad Ready Work included “installing erosion and sediment controls, performing mass

grading and fill work in accordance with the draft site plan, and installing a modular retaining wall,” and required that York perform the work in accordance with a geotechnical report prepared by GTA (the “GTA Report”). (Am. Countercl. ¶ 15). Medline and York subsequently entered into an amended agreement (the “Amended Agreement”) in which Medline provided York additional time to complete the Pad Ready Work, which the

2 Unless otherwise noted, the Court takes the following facts from Medline’s Amended Answer and Counterclaims Against Gray and Additional Counterclaim Defendants York, GTA, MRA, Allan Myers, and Schuster, (ECF No. 51), and accepts them as true. See Erickson v. Pardus, 551 U.S. 89, 94 (2007) (citations omitted). amended agreement referred to as the “Post-Closing Work.” (Id. ¶¶ 16–17; see Original Answer Ex. B [“P&SA 1st Am.”], ECF No. 17-4).

In February 2018, Medline and Gray entered into a contract wherein Gray agreed to design and construct the distribution facility Medline sought to build on the Property (the “Medline/Gray Contract”).3 (Am. Countercl. ¶ 18). In April 2018, Gray assumed responsibility for completing the Post-Closing Work set forth in the Amended Agreement. (Id. ¶ 19). In March 2019, Medline and Gray executed a “Certificate of Substantial Completion,” which deemed the Project substantially complete and accepted by Medline

as of February 26, 2019. (Id.). The Certificate noted, however, that several items remained uncomplete. (Id.). Pursuant to the Purchase and Sale Agreement, York and Medline agreed that GTA would provide the “design, engineering, inspection and testing services necessary for the Pad Ready Work.” (Id. ¶ 15). Moreover, GTA would provide the design of the modular

retaining wall (the “Retaining Wall”), and was responsible for inspecting and approving York’s installation of fills behind the Retaining Wall. (Id.). The Retaining Wall was “located along an area of mapped wetlands, which necessitated the construction of the wall in order to raise Site grades to accommodate the Site layout and support a main access drive for the Site.” (Original Answer Ex. D [“SESI Report”] at 7, ECF No. 17-6). GTA

also “oversaw construction of the wall and provided construction inspection and testing

3 The work to be performed by York and the work to be performed by Gray and its subcontractors will hereinafter be collectively referred to as the “Project.” services initially to York and then to Gray for the remainder of the Project, including the construction of the distribution facility itself.” (Am. Countercl. ¶ 21).

The Retaining Wall “was constructed in the fall of 2017. Less than 12 months later, cracks in the wall itself and in the driveway areas behind the wall were observed.” (Id. ¶ 23). GTA conducted testing and determined that “the Retaining Wall was sliding away from the building and that the sliding caused dramatic settling and cracking of the paved driveway areas behind the wall.” (Id. ¶¶ 24–25). Medline avers that the Retaining Wall’s movement was “so dramatic” that it could result in “a collapse of the building itself.” (Id.

¶ 26). Following GTA’s investigation, Medline retained SESI Consulting Engineers (“SESI”) to investigate the failure of the Retaining Wall and recommend a path forward, resulting in a “Global Evaluation Report” created by SESI in August 2019. (Id. ¶¶ 28–29; see generally SESI Report). SESI discovered significant issues in the Retaining Wall,

concluding that it had “experienced a sliding failure” and that “complete deconstruction, redesign, and reconstruction of the wall system” was required. (Am. Countercl. ¶¶ 30–32; SESI Report at 58).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
United Mine Workers of America v. Gibbs
383 U.S. 715 (Supreme Court, 1966)
Scheuer v. Rhodes
416 U.S. 232 (Supreme Court, 1974)
Albright v. Oliver
510 U.S. 266 (Supreme Court, 1994)
Erickson v. Pardus
551 U.S. 89 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Bizzie Walters v. Todd McMahen
684 F.3d 435 (Fourth Circuit, 2012)
Pacific Indemnity Co. v. Whaley
560 F. Supp. 2d 425 (D. Maryland, 2008)
Gray & Son, Inc. v. Maryland Deposit Insurance Fund Corp.
575 A.2d 1272 (Court of Special Appeals of Maryland, 1990)
Sheeskin v. Giant Food, Inc.
318 A.2d 874 (Court of Special Appeals of Maryland, 1974)
Flaherty v. Weinberg
492 A.2d 618 (Court of Appeals of Maryland, 1985)
Cooper v. Berkshire Life Insurance
810 A.2d 1045 (Court of Special Appeals of Maryland, 2002)
White v. Peabody Construction Co., Inc.
434 N.E.2d 1015 (Massachusetts Supreme Judicial Court, 1982)
Giant Food, Inc. v. Washington Coca-Cola Bottling Co.
332 A.2d 1 (Court of Appeals of Maryland, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
Gray Construction, Inc. v. Medline Industries, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gray-construction-inc-v-medline-industries-inc-mdd-2020.