Stewart v. American Bridge Co.

69 A. 708, 108 Md. 200, 1908 Md. LEXIS 72
CourtCourt of Appeals of Maryland
DecidedMay 15, 1908
StatusPublished
Cited by6 cases

This text of 69 A. 708 (Stewart v. American Bridge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stewart v. American Bridge Co., 69 A. 708, 108 Md. 200, 1908 Md. LEXIS 72 (Md. 1908).

Opinion

Burke, J.,

delivered the opinion of the Court.

This is the defendants’ appeal from a judgment entered against them in the Superior Court of Baltimore City. The declaration contained the common counts only to’ which the defendants pleaded the general issue pleas, upon which issue was joined. Subsequently, the defendants filed the following additional plea, viz:

That at the time the plaintiff’s action was commenced the plaintiff was indebted to them in a large sum of money, growing out of the furnishing of material and work and labor with reference to the erection of the warehouse known as Numbers 28 — 30-32 ‘Hopkins Place, in the city of Baltimore, towit:

13.78 for failure to paint wall boxes; The sum of
50.80 for sundry cutting and patchingof walls made requisite . by the plaintiff failing to construct its beams and other structural iron work to conform to the plans and specifications; The sum of
5.95 for making, at the request of the plaintiff, certain templates; The sum of
687.70 paid to the Chesapeake Iron Works for flitch plates, which the plaintiff had agreed to furnish, and, nevertheless, failed so to do; The sum of
445.00 for setting steel beams, taking down and resetting the same, including the necessary cutting out and rebuilding in connection with the location of the The sum of *209 channels and beams for the stair landings;
The sum of 7.60 paid Deitrich Bros, for clean-out doors, which the plaintiff should have, but did not furnish;
#1,210.83 Forwarded, #1,210.83
The sum of 1,375.00 being the amount of liquidated damages paid by the defendants to the owners of the building by reason of their failure to complete the same as by the contract provided, the entire ' delay in' so completing said buildings having been occasioned by the negligence, default and wilful acts of omission and commission of the plaintiff;
The sum of 362/55 temporary canvas covering, and other protection to the Hopkins Place elevation, caused by the failure of the plaintiff to have fronts installed as required;
The sum of 225.00 cost of putting in temporary stair platforms, on account of the plaintiff’s failure to have permanent platforms-delivered on time;
The sum of 8,000.00 being the additional cost incurred by the defendants- in erecting said building, by reason of the manner of construction made requisite and the delay-occasioned' by the failure of the plaintiff to furnish the material when and as required by the defendants and in accord with the understanding and agreement had with the plaintiff; which said sums amounting in all to
--#11,173.38, exceeded the damages sustained by the said plaintiff by reason of the non-performance by the defendants of the said several supposed promises and undertakings in the declaration herein mentioned, and out of which said sums of money so due and owing from the said plaintiff to the said defendants, the said defendants are ready and willing and hereby offer to set-off and allow to the said plaintiff, the American Bridge Company, the full amount of said dam- *210 ages, according to the form of the statute in such cases made and provided, and claim judgment for such balance as may be found due to the defendants from the plaintiff on said account.

Issue was joined by the defendants upon the traverse of the plaintiff to this plea, and the case proceeded to trial, which resulted, after a great mass of testimony had been taken, in a judgment for the plaintiff for twelve hundred and seventy-five dollars and eighty-two cents ($1,275.82), from which this appeal is taken. Twenty-one bills of exceptions were reserved by the defendants. Eighteen of these relate to the rulings of the Court upon questions of evidence, and the remaining three to the action of the Court upon the prayers submitted by the respective parties at the close of the whole testimony.

The exceptions to testimony may be classified and grouped under three general heads, and in this way a separate discussion of them dispensed with; first, the exception to the refusal of the Court to permit the defendants to introduce in evidence the “general conditions” contained in the contract made between the defendants and the owners of the Daniel Miller Warehouse Building which the defendants had undertaken to erect; secondly, the admission in evidence of a certain statement and voucher sent by the defendants to the plaintiff; thirdly, to the exclusion by the Court of the testimony of expert witnesses, testifying as such, to show that the unit cost of labor in handling the timber and brick construction of the Miller Building was increased beyond the normal price paid for such labor» by reason of the failure of the plaintiff to deliver the material which was to be furnished by it in the prosecution of the work, with a view of thus establishing a loss or damage, which the defendants alleged they had suffered, and for which the plaintiff was sought to be held responsible under the last item of the defendants’ additional plea; fourthly, the ad-admission in evidence of certain original memoranda of superintendents of Wyatt & Nolting, the architects; made at the time, in the course of their duty, and reported daily to their employers as the work progressed — the persons who made these memoranda being out of the jurisdiction of the Court and their handwriting being proven.

*211 It ■ becomes necessary, in order to ascertain the legal principles which should control*the case, to understand the main and controlling facts disclosed by the record. On the 27th of May; 1904, the defendants entered into a contract with the owners of ground on Hopkins Place, in the city of Baltimore, for the erection of a large warehouse spoken of in the evidence as the Daniel Miller Building. This building was to be erected in accordance with the approved plans and specifications prepared by Wyatt & Nolting, who were the architects for the owners. The plans for the building were prepared, and were approved by Mr. E. D. Preston, the Building Inspector for the city, on June 9th, 1904, and it was upon these plans that the defendants bid for the erection’ of the building was based, and upon which the contract was awarded. On the 28th of April, 1904, the plaintiff, being one of the largest structural steel and iron concerns in the country, had obtained from the architects a set of plans with a view of submitting a bid for furnishing and erecting the structural and architectural iron work for the Miller Building. Subsequently it did submit a proposition to the defendants for furnishing and doing this work, and on June 23rd, 1904, a contract was entered into between the plaintiff and the defendants by which the plaintiff agreed to furnish and erect complete the steel and iron work for the building.

Only such portions of this contract as relate to the issues raised by the pleadings need be noticed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L & S Construction Co. v. Bradbury Homes, Inc.
118 A.2d 681 (Court of Appeals of Maryland, 1955)
Milkton v. French
150 A. 28 (Court of Appeals of Maryland, 1930)
Hammaker v. Schleigh
147 A. 790 (Court of Appeals of Maryland, 1929)
William B. Durm & Co. v. Pennsylvania Railroad
4 Balt. C. Rep. 661 (Baltimore City Court, 1928)
Myers v. Strowbridge Estate Co.
160 P. 135 (Oregon Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
69 A. 708, 108 Md. 200, 1908 Md. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stewart-v-american-bridge-co-md-1908.