McGregor v. J. A. Ware Construction Co.

87 S.W. 981, 188 Mo. 611, 1905 Mo. LEXIS 51
CourtSupreme Court of Missouri
DecidedMay 24, 1905
StatusPublished
Cited by14 cases

This text of 87 S.W. 981 (McGregor v. J. A. Ware Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGregor v. J. A. Ware Construction Co., 87 S.W. 981, 188 Mo. 611, 1905 Mo. LEXIS 51 (Mo. 1905).

Opinion

MARSHALL, J.

This is an action to recover $4,711.56 for work done by the plaintiff as a subcontractor under the defendant for doing certain excavation in the construction of the St. Louis, Peoria and Northern Railway, the defendant company being a subcontractor under the general contractor with the Railroad Company. The case was tried-by a referee, who found the facts in favor of the defendant and recommended a judgment in its favor. The plaintiff filed exceptions to the referee’s report, the circuit court overruled the exceptions and entered judgment for the defendant, and after proper steps the plaintiff appealed.

THE ISSUES.

The petition is in two counts, but the plaintiff makes no point in this court as to the judgment against him on the second count, and, therefore, no further notice will be taken of that count.

The first count alleges that on the 28th of May, 1897, the plaintiff entered into a contract with the defendant to do the work required in clearing and grading a portion of said railway, at the following prices: “Earth excavation, 9 cts. per cubic yard; loose rock, 30 cts. per cubic yard; clearing, $20 pér acre; over-hauling, 1-2 c. per cubic yard for each additional 100 feet after the first 300 feet of over-haul, the specifications of the Laclede Construction Company being part of and governing said agreement, a copy of said specifications being herewith filed as ‘Exhibit A.’ ”

The petition then alleges that under said contract, the plaintiff excavated 22,436 yards of loose rock, for which defendant had agreed to pay at the rate -of 30 cents per cubic yard, or a total of $6,730.80, and that the defendant had only paid plaintiff on account thereof the sum of $2,019.24, leaving a balance due of $4,711.56, for which the plaintiff asked judgment.

[616]*616The answer is a general denial of all .matters not expressly admitted. The answer then admits the execution of the contract referred to in the first count of the petition and the performance thereof by the plaintiff, and then sets up, that among the specifications in the contract of the Laclede Construction Company, which was made a part of plaintiff’s contract, it was provided as follows: “Classification of materials: The materials found in the excavation will be classed as solid rock, loose rock and earth, the chief engineer being, in every case, the final judge as to the class to which any material belongs. Solid rock mil include all loose boulders containing one cubic yard or more and all hard rock in compact strata or ledges exceeding six inches in thickness^ which, in the judgment of the'engineer can not be loosened except by blasting. Loose rock will include all loose boulders containing more than three cubic feet and less than one cubic yard, and all materials requiring the use of pick and bar, or which cannot be plowed with a strong 10-inch grading plow, well handled, drawn by a good six-horse team. Earth will include all materials of whatever kind .which does not clearly belong' to one or the other of the foregoing classes. Whenever rock of any kind is found in the excavation, the contractor shall, at once, notify the engineer in charge, so that he may make the necessary measurements to determine its quantity. If the contractor shall fail to give such notice the engineer may presume that the measurements taken at the time he first sees the material in question will give the true quantity. In case 'disputes or differences shall arise between the parties to this agreement as to the true intent and meaning thereof, or the sufficiency of the performance of any of the work to be done under it, or the classification of the work, or the price to be paid, all,disputes and differences shall be referred to the chief engineer of the construction company, who shah [617]*617consider and decide the same, and his decision shall he final and binding upon both parties.”

The answer further alleges that Robert Moore was the chief engineer in charge of the work and was the engineer referred to in the contract and specification^ and that he made his final estimate of the work done by the plaintiff and classified the materials and allowed the plaintiff for excavation nine cents per yard for earth excavations and awarded to plaintiff a total sum of $21,298.98, as the full amount which the plaintiff was entitled to under his contract, and that the defendant paid the same to the plaintiff after the work was done; that said chief engineer found that all the excavation done by the plaintiff under his contract was earth excavation, and that none of the materials excavated by the plaintiff consisted of loose rock, and the defendant claimed that the final estimate and finding of the chief engineer was final, binding and conclusive upon both of the parties to said contract. The reply to the answer is a general denial.

The case was referred to a referee to try all the issues and report. The referee reported, set out the contract between the plaintiff and defendant and the portions of the specifications contained in the contract of the Laclede Construction Company, which were made a part of the plaintiff’s contract, .and that the plaintiff had fully performed his contract and that the defendant had paid him therefor the sum of $21,298.98. The referee then reported as follows:

“ There, is no controversy between the parties respecting the quantity of materials excavated by the plaintiff, or the quantity hauled more than 300 feet, nor respecting the prices for the various kinds of materials or other work done by the plaintiff; nor respecting payments made to plaintiff by defendant, but the plaintiff contends that 22,436 cubic yards of the materials excavated by him was loose rock, for the excavation of which he was entitled to 30 cents per cubic yard, [618]*618whereas defendant contends that none of said materials was rock bnt that all of it was earth.

“Defendant paid the plaintiff the contract price for excavating earth, and unless some of the materials was loose rock, the plaintiff has been paid in full.

“I find that plaintiff excavated no loose rock but all material excavated by him was earth; that prior to the bringing of this action, defendant paid the plaintiff in full for all work done by him, in accordance with said contract of May 29, 1897, and as set forth in the answer of defendant, and in accordance with the classifications and final estimate of the engineer as provided in the specifications which form a part of said contract.

“I further find that Robert Moore was the chief engineer referred to in said specifications, and that Robert H. Cole was his assistant, resident engineer in charge of the work done by the plaintiff. Both Mr. Cole and Mr. Moore, the said engineers, decided that plaintiff had excavated no loose rock, but that all material excavated by him was earth:”

The referee thereupon recommended judgment for the defendant.

It is not necessary to set out, or even digest, the testimony adduced at the trial before the referee. It is sufficient-to say that the testimony on the part of the plaintiff gave some color to the claim that at least a part of the excavation consisted of what is designated in the contract and specifications as loose rock and not earth excavation, while the testimony on the part of the defendant showed that there was no loose rock excavated, bnt that some of the earth was hard or difficult to excavaté, yet did not come within the proper definition of the term, “loose rock,” as employed in the contract and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weiss v. Duro Chrome Corp.
207 F.2d 298 (Eighth Circuit, 1953)
Massman Construction Co. v. Lake Lotawana Ass'n
210 S.W.2d 398 (Missouri Court of Appeals, 1948)
Menke v. Thompson
140 F.2d 786 (Eighth Circuit, 1944)
Phillips Petroleum Co. v. Rau Const. Co.
130 F.2d 499 (Eighth Circuit, 1942)
Myers v. Union Electric Light & Power Co.
66 S.W.2d 565 (Supreme Court of Missouri, 1933)
Kennedy v. Bowling
4 S.W.2d 438 (Supreme Court of Missouri, 1928)
Dutton & Kendall Co. v. Hoffman
264 P. 1092 (Supreme Court of Colorado, 1928)
Kellner v. Schmidt
159 N.E. 821 (Illinois Supreme Court, 1927)
Morgan v. Goddard
214 N.W. 155 (Michigan Supreme Court, 1927)
State Ex Rel. Dolman v. Dickey
219 S.W. 363 (Supreme Court of Missouri, 1920)
Berger Manufacturing Co. v. Crites
165 S.W. 1163 (Missouri Court of Appeals, 1914)
Barham v. Bank of Delight
126 S.W. 394 (Supreme Court of Arkansas, 1910)
Stewart v. American Bridge Co.
69 A. 708 (Court of Appeals of Maryland, 1908)
McAndrews v. Chicago, L. S. & E. Ry. Co.
162 F. 856 (Seventh Circuit, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
87 S.W. 981, 188 Mo. 611, 1905 Mo. LEXIS 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgregor-v-j-a-ware-construction-co-mo-1905.