McCormick v. City of St. Louis

65 S.W. 1038, 166 Mo. 315, 1901 Mo. LEXIS 333
CourtSupreme Court of Missouri
DecidedDecember 21, 1901
StatusPublished
Cited by41 cases

This text of 65 S.W. 1038 (McCormick v. City of St. Louis) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCormick v. City of St. Louis, 65 S.W. 1038, 166 Mo. 315, 1901 Mo. LEXIS 333 (Mo. 1901).

Opinions

ROBINSON, J.

This is a suit against the defendant city of St. Louis, to recover an alleged balance of $22,323.49, composed in the main of claims for extra work and material furnished by plaintiff in driving and lining up what is termed in the contracts between the plaintiff and defendant, of an inlet tunnel and tower, at the Chain of Rocks, under the Missis— ippi river, to be used in connection with the city’s waterworks. For a fuller statement and history of the case We have adopted, in the main, that furnished by counsel for respondent as follows :

The amended petition on which the case was tried is in two counts. In the first count plaintiff alleges that on December 23, 1889, he entered into a contract with the city, known as contract No. 2474, for-the driving and lining of an inlet tunnel at the Chain of Rocks, the tunnel being a part of the waterworks system of the city. That by the terms of the contract the city’s water commissioner was empowered to make and to direct the making of alterations1 in the work, either before or after its commencement, and that if changes were made, the city was to pay plaintiff -a fair and reasonable price for any additional work thus occasioned. That during the execution of the work the water commissioner did require changes, which compelled plaintiff to excavate and move 2,401 cubic yards of material from the tunnel, at an increased cost to him of $6.75 per cubic yard, or an aggregate cost of $16,-206.75, on account of which he received $7,257.20, leaving still due a balance'of $8,949.55. That he also excavated 451 cubic yards of rock at the tunnel, and constructed 122.5 cubic yards of brick masonry therein, which brick masonry defendant-refused to measure and refused to pay for, and that under the terms of the contract plaintiff is entitled to $1,592.50 for the [321]*321masonry, and to $3,157 for the excavation, making together the sum of $4,749.57. This count of the petition also alleges that under the contract the water commissioner, upon the completion of the work, was required to cause a final estimate to be made of the total amount of the work, according to the terms and prices mentioned in the contract, and that after deducting all sums previously paid, or rightfully retained under the contract, the commissioner was to certify the balances as due the plaintiff from the city. That the water commissioner did not make the measurements nor allow the compensation to which plaintiff claims to be entitled, although requested by him so to do, nor did he, upon the completion of the work, make a determination of the respective quantities of the work claimed by plaintiff to have been executed, which failure and neglect of the commissioner it is alleged was fraudulent, in bad faith and collusive with defendant. It is also averred that in reference to these matters the commissioner acted dishonestly and corruptly. Judgment is asked on this count for $13,699.05.

The second count pleads that on December 23, 1889, plaintiff entered into contract No. 2475 with the city for the building of an inlet tower at the Chain of Rocks, and that plaintiff furnished a large amount of extra work and extra materials in the execution of this contract, at the directions of the defendant. It is charged that the following work done, and the following materials furnished by him in connection with this work, have not been paid for:

1. Repairing and scraping the inlet tower gates, “supplied by plaintiff in a defective condition” .............,....... $ 757.26

2. Cutting granite gateways in the inlet tower, and blacksmithing, and iron furnished for same .....................$208.04

On which plaintiff pleads he received... . 97.28

[322]*322And claims to be entitled to a balance of. $ 128.76

(Which balance should, clearly, have been stated to be $110.76.)

3.Iron work 4874 lbs. at 10c per lb......$487.40

On which plaintiff pleads he received. . 380.98

And claims to be entitled to a balance of. $ 106.42

4. Eor one cofferdam, which plaintiff claims to have had the right to remove upon the completion of the work, but which he avers he left at defendant’s request, as a protection to the inlet tower. 3,500.00

5. 400 cubic yards of rip-rap, in connection with the cofferdam............. 1,000.00

6. 50 tons of pig iron................ 750.00

7. For 24 cubic yards of rock excavation in the shaft of the inlet tower, at $100 per cubic yard.................... 2,400.00

The same allegations are then made respecting the duty of the water commissioner to make or cause a final estimate to be made; his failure to allow for the foregoing items, and that such failure was due to fraud, bad faith, and collusion with defendant, and that the commissioner acted dishonestly and corruptly. Judgment on this count is asked in the sum of $8,624.44.

The answer to the first count admits that defendant is a municipal corporation; admits that plaintiff entered upon the performance of said contract, and completed the same, but denies all other allegations in said count of the petition.

The answer thereupon avers that in the contract it was provided as follows:

“To prevent all disputes and litigation it is agreed by and between the parties to this contract, that the water commissioner shall, in all cases, determine the amount of the sev[323]*323eral kinds of work which are to be paid for under this contract; and he shall decide all questions which may arise relative to the execution of this contract, on the part of the contractor, and his estimates and decisions shall be final and conclusive.”

That on October 29, 1891, the water commissioner did finally estimate and decide the amount of work done by plaintiff under said contract No. 2474, and under ordinance 15024, to amount to $89,197.55, including all extras, and after deducting therefrom $80,092.94, previously paid plaintiff, certified that there was due plaintiff, upon final settlement, a balance of $9,104.61. That on October 30, 1891, the president of the Board of Public Improvements approved said final estimate, and certified the same to be correct; that on the same day said claim was audited for the said sum of $9,104.61 by the city auditor, in full payment of all claims against the city, under contract No. 2474 and ordinance 15024, and that thereafter the city treasurer paid the auditor’s warrant. An itemized account is made a part of the answer, showing in detail what work and materials the water commissioner allowed, and how he reached the balance to which he certified.

The answer also avers that on October 29, 1891, the water commissioner made his final estimate and decision of the amount of work done under said contract No. 2474 and under ordinance 15297, finding said work, with all extras, to amount to $17,810.65; and after deducting therefrom $9,996.00 previously paid, certified to a balance of $7,814.65, as the amount-due plaintiff upon a final estimate under said contract and ordinance. That on October 30, 1891, the president of the Board of Public Improvements approved said certificate, and on same day it was audited for said amount of $7,814.65 in favor of plaintiff, who received from the auditor a warrant upon the city treasurer in full payment of said final estimate, and thereafter the warrant was paid to plaintiff by the treas-[324]*324urea:. An itemized statement is again set forth in the answer, showing how said balance was reached.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schmalz v. Hardy Salt Co.
739 S.W.2d 765 (Missouri Court of Appeals, 1987)
Anselmo v. Manufacturers Life Insurance
595 F. Supp. 541 (W.D. Missouri, 1984)
Grant Renne & Sons, Inc. v. J. E. Dunn Construction Co.
633 S.W.2d 166 (Missouri Court of Appeals, 1982)
Durwood v. Dubinsky
291 S.W.2d 909 (Supreme Court of Missouri, 1956)
Phillips Petroleum Co. v. Rau Const. Co.
130 F.2d 499 (Eighth Circuit, 1942)
Hancock v. State Highway Commission
149 S.W.2d 823 (Supreme Court of Missouri, 1941)
Vilter Mfg. Co. v. Rolaff
110 F.2d 491 (Eighth Circuit, 1940)
United States ex rel. Tobin Quarries, Inc. v. Glasscock
27 F. Supp. 534 (E.D. Missouri, 1939)
Locust Realty Co. v. City of Kansas City
115 S.W.2d 205 (Missouri Court of Appeals, 1938)
State Ex Rel. Order of United Commercial Travelers of America v. Shain
98 S.W.2d 597 (Supreme Court of Missouri, 1936)
Buchanan v. Rechner
62 S.W.2d 1071 (Supreme Court of Missouri, 1933)
Wahl v. Cunningham
56 S.W.2d 1052 (Supreme Court of Missouri, 1932)
Laxton v. Retail Hardware Mutual Fire Insurance
48 S.W.2d 144 (Missouri Court of Appeals, 1932)
Bank of Oak Ridge v. Duncan
40 S.W.2d 656 (Supreme Court of Missouri, 1931)
James Shewan & Sons, Inc. v. United States
73 Ct. Cl. 49 (Court of Claims, 1931)
Pederson v. Thoeny
295 P. 250 (Montana Supreme Court, 1930)
Du Puy v. United States
35 F.2d 990 (Court of Claims, 1929)
State v. Sloan
274 S.W. 734 (Supreme Court of Missouri, 1925)
Stanford v. United States Inv. Corp.
272 S.W. 568 (Court of Appeals of Texas, 1925)
Ajax Rubber Co. v. White
264 S.W. 466 (Missouri Court of Appeals, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
65 S.W. 1038, 166 Mo. 315, 1901 Mo. LEXIS 333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccormick-v-city-of-st-louis-mo-1901.