Berger Manufacturing Co. v. Crites

165 S.W. 1163, 178 Mo. App. 218, 1914 Mo. App. LEXIS 110
CourtMissouri Court of Appeals
DecidedMarch 2, 1914
StatusPublished
Cited by4 cases

This text of 165 S.W. 1163 (Berger Manufacturing Co. v. Crites) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berger Manufacturing Co. v. Crites, 165 S.W. 1163, 178 Mo. App. 218, 1914 Mo. App. LEXIS 110 (Mo. Ct. App. 1914).

Opinion

JOHNSON, J.

This is an action to recover a remainder of $1531.79, due upon an account for certain patented building materials sold and delivered by plaintiff, a manufacturer in Canton, Ohio, to a firm of building contractors in Kansas City, composed of defendant’and Frank R. Beatty. Both members of the partnership were sued by plaintiff but service could not be obtained upon Beatty and the action proceeded against defendant Crites alone who filed an answer and counterclaim. At the conclusion of the evidence the court instructed the jury to find for plaintiff for the full amount of the demand in the petition and submitted certain issues of fact relating to the counterclaim which were resolved by the jury in favor of defendant. The verdict was for plaintiff on the petition for $1531.79, for defendant on the counterclaim in the sum of $1800, and ended with the recital “deducting the lesser amount from the greater we find the issues for the defendant in the sum of ($268.21) two hundred sixty-eight dollars and twenty-one cents.” Afterward defendant, in obedience to a peremptory suggestion from the court on the hearing of the motion for a new trial, entered a remittitur in a sum sufficient to equalize the claim of plaintiff and counterclaim of defendant, and judgment was rendered accordingly. Plaintiff appealed.

The Board of Education of Winfield, Kansas, let the contract to Crites and Beatty for the construction of a large school building for which plans and specifications had been prepared by architects in Kansas City and accepted by the board. The building was to be fireproof and the specifications called for concrete floors in the rooms, halls and corridors and gave the general contractors the option of “using the Berger metal lumber, or any other patented system of fireproofing in place of the system shown and specified, providing there are sufficient details and specifications filed with the proposals to permit them to form an [220]*220accurate opinion of the method contemplated and also to ascertain whether the system is durable and sufficient.”

The Berger system had been on the market about three years and the inventor was the manger of plaintiff’s “metal lumber department.” He examined the plans and specifications of the school building before submitting a bid to Grites and Beatty for the installation of his system in place of the reinforced concrete floors for which the specifications included details. The essential difference between reinforced concrete and plaintiff’s “metal lumber” construction is that in the former the tension is divided between the concrete and steel rods it embodies while in plaintiff’s system, the concrete is laid on a steel substructure and is not intended or relied upon to take any of the tension which, including the weight of the concrete, is borne entirely by the “metal lumber.”

The inventor thus describes the system: “The Berger fireproofing system, known as metal lumber, and which is referred to in this case, consists of pressed steel sections, with bearings, such as I-angles, T’s and so forth — and is designed to take the place of wooden joists- — they are used as joists, and placed sixteen inches on center — both in the joists and studs. On the top is used an expanded metal lath, ranging from number twenty to number twenty-four gauge, and the bottom of the joist is arranged with prongs, by means of which the ceiling metal lath, of number twenty to number twenty-four gauge iron is attached. That is used in all of these plans. In the joist proper, the joist is provided with bridging. The joist consists of two sections, riveted back to back. Between these rivets there is an aperture formed by the joist going back to back; and in that a nail can be placed, the same as in a wall, and a nail can be driven in that. The bridging comes in twenty-inch iron — which is a tension bridging — and should be nailed in between the [221]*221joists; and by nailing this one in the other, yon get a construction which is provided for three purposes— first, it is to hold the joists in line, in a vertical position, and afterwards the means of transferring any contingency loads on the joists to the joists beside it. Now, the joist lath and bridging constitutes the floor. The studs or columns of the construction also acts as bridging.”

Reduced to a more concise description the bed for holding the concrete is a reticulated steel mesh supported by steel joists or “I” beams.

The bid of plaintiff to furnish the materials for the floors for $12,000 was accepted by the contractors and the materials were delivered by plaintiff and put into the building by the contractors who mixed and laid the concrete in accordance with the requirements of the specifications. The concrete thus laid proved a failure, as the evidence of defendant tends to show, in two particulars, viz., first, on account of the lightness of the “metal lumber,” the bed sagged under the weight of the concrete which did not exceed the thickness prescribed in the specifications and thereby caused the concrete floor to crack in various places and, second, the spreading of thin concrete over a sievelike bed with nothing underneath to prevent drainage caused the water to drain away from the admixture and prevent the necessary coalescence of its elemental substances.

Expert evidence introduced by defendant supports the conclusion that the failure of the floors to conform to the standard of the specifications and their consequent rejection by the architects were due to one or both of such causes.

The evidence of plaintiff tends to show, first, that there was no deflection or sagging of the metal bed which repeated preliminary tests had demonstrated of sufficient strength to carry the intended load without substantial deflection and, second, that the lack of [222]*222coalescence was caused by the fault of defendant in putting too much water into the mixture. The inventor states that since it was not intended the concrete should possess tensility, the mixture should have contained only enough water to moisten its substances and not enough to cause drainage with consequent loss of cement and sand. In other words it should have been of the consistency of thick dough and devoid of all fluidity. The answer of the witnesses for defendant to this testimony is twofold, i. e., first, that defendant did not know that concrete suitable for pouring into moulds would be unsuited to the requirements of plaintiff’s system and received no instructions from plaintiff regarding such peculiar need of the system, and, second, that on discovering that fluid concrete would lose too much cement and sand in the drainage of water through the mesh, tried a mixture similar to that the inventor states should be used and found that it was too dry — the weather being very hot —to receive the finishing coat. The inventor asserts, in substance, that defendant did not put on the finishing coat at the proper time and that tests have shown no difficulty in obtaining satisfactory results where the work is done properly. The specifications contained provisions requiring all work to meet the approval of the school board and their architects and the contract between plaintiff and the contractors bound plaintiff to conform to these requirements. The Board of Education, prompted by the advice of .the architects, rejected the floors, had them relaid and deducted $1600 from the price the contractors were to receive for the building. The materials furnished by plaintiff were not removed from the construction.

The plans and specifications must be regarded as a part of the contract between plaintiff and the contractors. [Miller v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Price Brothers Lithographic Co. v. American Pack. Co.
381 S.W.2d 830 (Supreme Court of Missouri, 1964)
Davenport Ladder Co. v. Edward Hines Lumber Co.
43 F.2d 63 (Eighth Circuit, 1930)
Dutton & Kendall Co. v. Hoffman
264 P. 1092 (Supreme Court of Colorado, 1928)
Granette Products Co. v. Arthur H. Neumann & Co.
203 N.W. 935 (Supreme Court of Iowa, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
165 S.W. 1163, 178 Mo. App. 218, 1914 Mo. App. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berger-manufacturing-co-v-crites-moctapp-1914.