Granette Products Co. v. Arthur H. Neumann & Co.

203 N.W. 935, 200 Iowa 572
CourtSupreme Court of Iowa
DecidedMay 12, 1925
StatusPublished
Cited by9 cases

This text of 203 N.W. 935 (Granette Products Co. v. Arthur H. Neumann & Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Granette Products Co. v. Arthur H. Neumann & Co., 203 N.W. 935, 200 Iowa 572 (iowa 1925).

Opinion

Vermilion, J.

I. The amended and substituted petition alleged that the plaintiff and defendant entered into a written contract whereby the plaintiff undertook to manufacture and deliver to the defendant certain artificial architectural stone, to be used by defendant in the construction of a school building at Council Bluffs. It alleged that the greater part of the stone was delivered, and that the defendant refused to accept further stone, and elected to rescind the contract. The contract is set out. In the contract the plaintiff is designated as the subcontractor, and the defendant as the contractor, and it is provided as follows:

“Section I. The subcontractor agrees to furnish all labor and materials necessary to complete work as described in Section II of this agreement for the Council Bluffs High School, Council Bluffs, la., according to plans and specifications prepared by Proudfoot, Bird & Rawson, architects, located at Des Moines, Iowa.”
“Section II. The subcontractor agrees that the material to be furnished and work to be done by him is as follows: All of the ‘Granette’ Concrete Architectural stone trim, including all *574 sills,;;steps, etc., in lieu of Bedford stone as mentioned and called for in revised plans and specifications as prepared by the above mentioned architects. Sample of ‘Granette’ to be approved by architects. It is further agreed that the subcontractor will furnish setting plans and number all stones, also provide each stone with anchor and lewis holes as necessary. Setting plans to be submitted to architects, also ali finished product to -be same as approved sample, also all moulding to run true and comers square and straight. All of the above mentioned work to be subject to the approval of the above mentioned architects.”

The amended and substituted answer contained allegations that the plans and specifications for the building as prepared by •the architects were those referred to in the contract with plaintiff, and were furnished plaintiff; and portions of the specifications are set out, providing that the architects might require the contractor to remove from the premises such of his materials or work as in their opinion were not in, accordance with the plans and specifications, and to substitute satisfactory work and materials, and that the expense of so doing should be borne by the contractor, and that the decision of the architects as to the true intent and meaning of the plans and specifications should be final and binding on both parties to the contract, and that the term “contractor,” as used in the plans and specifications, should mean the person or persons who contracted for the performance of the work. It was alleged that the plaintiff had knowledge, at the time the contract in question was entered into, of a provision in the defendant’s contract for the construction of the building, to the effect that the contractor would remove from the grounds or building all materials condemned by the architects, whether worked or unworked, and take down all portions of the work which the architects should condemn as unsound or improper, or as in any way failing to conform to the drawings and specifications, and should make good all work damaged or destroyed thereby. It was alleged that the plaintiff had knowledge that the contract in question was entered into for the purpose of enabling defendant to fulfill the obligations assumed by the general contract, and that the approval of the architects required by the contract with plaintiff, by reason of such knowledge, and by reason of the custom then existing between con *575 tractors and subcontractors engaged in the business of constructing public buildings, meant the approval of the architects in accordance with the terms of the general contract. It was further alleged that the reference-to the plans and specifications in the contract sued on constituted an adoption by the parties thereto of the terms and conditions of the general contract and the plans and specifications so pleaded; and that plaintiff was thereby bound to perform the work in accordance with the plans and specifications and the general contract. It was alleged that the material furnished by plaintiff pursuant to its contract and the plans and specifications did not comply therewith, nor meet the approval of the architects, as required by the terms of its contract and the specifications and the general contract; and that, as a result thereof, the school district, acting by the -architects, after a considerable portion of the stone had been set in place, ordered its removal, and ordered defendant to discontinue receiving material from plaintiff. These allegations were also made a part of a counterclaim.

The foregoing allegations, except the allegation that the materials furnished by plaintiff did not comply with the contract between plaintiff and defendant and the plans and specifications, and did not meet with the approval of the architects, as required by plaintiff’s Contract and the plans and specifications, were, on motion of plaintiff, stricken from the answer and counterclaim. It is from this order that the defendant appeals.

The underlying question presented is whether, and, if so, to what extent, the plans and specifications for the construction of the building by the principal contractor, and the principal contract, were made a part of the contract in question. It is the contention of plaintiff that the contract between plaintiff and defendant was an executory contract for the manufacture and sale of material to correspond to' the sample, and in number of pieces, shape, and character, as required by the plans and specifications and complying with the express terms of the contract, and subject- to the approval of the architects; that the reference to the plans and specifications was only for the purpose of identifying the pieces of stone to be furnished. On the other hand, the defendant contends that it was a building subcontract ; and that the plans and specifications and the principal eon- *576 tract were made parts .of it; and that plaintiff was bound b.v the terms of the specifications and principal contract with respect to approval by the architects of the material furnished, and their right thereunder to condemn' the material after its use in the building, and making their decision final.

I. The contention that the plans and specifications became a part of the contract in question only to the extent, and for the. purpose, of identifying the materials to be furnished, puts, we think, too narrow a construction upon the- language of the contract. The contract expressly designates the plaintiff as a subcontractor. This alone would, perhaps, not be conclusive; but it undoubtedly is a circumstance entitled to weight in determining the character of the undertaking and the rights of the párties. The material to be furnished was an artificial stone, made in molds for this particular building, and admittedly to be according to certain specifications as to size and shape. The pieces were to be numbered, and a'setting plan furnished by plaintiff, to indicate their position in the building. The labor involved in preparing the necessary -molds and making the stone was, obviously, the chief element- of their Value, as compared with the raw materials of which they were composed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LaFontaine v. Developers & Builders, Inc.
156 N.W.2d 651 (Supreme Court of Iowa, 1968)
Miller-Piehl Equipment Co. v. Gibson Commission Co.
56 N.W.2d 25 (Supreme Court of Iowa, 1952)
L. H. Heiselt, Inc. v. Brown
120 P.2d 644 (Supreme Court of Colorado, 1941)
Wolfe v. Texas Co.
83 F.2d 425 (Tenth Circuit, 1936)
Waldman Produce, Inc. v. Frigidaire Corp.
157 Misc. 438 (Appellate Terms of the Supreme Court of New York, 1935)
Kunde v. O'Brian
243 N.W. 594 (Supreme Court of Iowa, 1932)
Lantz v. Goodwin
231 N.W. 331 (Supreme Court of Iowa, 1930)
Granette Products Co. v. Arthur H. Neumann & Co.
221 N.W. 197 (Supreme Court of Iowa, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
203 N.W. 935, 200 Iowa 572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/granette-products-co-v-arthur-h-neumann-co-iowa-1925.