Breen Stone Co. v. W. F. T. Bushnell Co.

135 N.W. 993, 117 Minn. 283, 1912 Minn. LEXIS 757
CourtSupreme Court of Minnesota
DecidedApril 26, 1912
DocketNos. 17,465—(44)
StatusPublished
Cited by2 cases

This text of 135 N.W. 993 (Breen Stone Co. v. W. F. T. Bushnell Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Breen Stone Co. v. W. F. T. Bushnell Co., 135 N.W. 993, 117 Minn. 283, 1912 Minn. LEXIS 757 (Mich. 1912).

Opinion

Philip E. Brown, J.

In 1910, the defendant erected a building in Aberdeen, South Da[284]*284lcota, known as the Dakota Farmer Building; the plans and specifications therefor being prepared by Ellerbe & Bound, a firm of architects of St. Paul, Minnesota, and the construction work being done by the Lepper Construction Company, under the supervision of one Arnold, the latter having been employed by the defendant to superintend such construction. On June 21, 1910, the plaintiff wrote the said Ellerbe & Bound as follows: “We will furnish all the cut stone for the new Dakota Farmer Building at Aberdeen, South Dakota, the same to be cut according to plans and specifications and ready to set in building, and delivered f. o. b. cars Aberdeen, South Dakota, for the sum of thirty-eight hundred dollars ($3,800.00) out of Bedford stone.”

On June 9, 1910, the defendant wrote the plaintiff as follows: “I have before me your letter of June 2d, addressed to Ellerbe & Bound, Architects, St. Paul, Minnesota, offering to furnish cut stone according to plans and specifications for the new Dakota Farmer Building at Aberdeen for the sum of $3,800.00 f. o. b. Aberdeen. I beg to advise that we wish to accept this, proposition, and just as soon as Mr. Ellerbe can prepare you a set of plans he will send them to you. Mr. Ellerbe informs us that you are in position to get out the work very promptly, and, of course, this acceptance is subject to that understanding.”

To this the plaintiff replied, under date of June 10 as follows: “We have your letter of June 9 th, awarding us the contract for the cut stone for the new Dakota Farmer Building at Aberdeen, according to plans and specifications by Ellerbe & Bound, for the sum of $3,800.00, f. o. b. cars Aberdeen, for which we wish to thank you.” The balance of this letter was devoted to the matter of the time it would take to get the stone out, and closed with an assurance that the plaintiff could arrange to get the stone out as fast as the contractor would need it.

The plans and specifications referred to in this correspondence provided, among other things, as follows:

“32. Cut Stone. All window sills, main entrance, including columns, bases, caps, lintels, moulded jambs, entabulatures, steps, and [285]*285balustrades; tbe base up to the water table, water table, and cornice with moulded medallions, and carved letters, and window casings on the main front and two sides returns, and wherever stone is indicated on plans and sections shall all be composed of the best quality blue Bedford stone of uniform color and hardness, free from sand holes and rust, and cut so as to lay on its natural bed and set in the wall. All stone shall be worked in accordance with the detail drawings, with true surfaces and sharp angles and straight lines. All sills shall he cut with lugs, and all sills and projecting courses shall be carefully fitted together at joints and no joint to exceed 3/16" in width. All stone to have a bearing on the wall of at least 5", and in all cases 1 — 3 more than its projections. No patching to be allowed. All exposed surfaces to be rubbed to a uniform smooth surface.”

As to payments, paragraph 11 of these plans and specifications provided: “Payments will only be made upon certificate of the architect and in accordance with the terms of the contract. No payments made on account of work during its progress and no prior inspection shall be construed as an acceptance of the work executed by the contractor. * * * ”

And in the preliminary specifications it is provided: “Where the word ‘contractor’ occurs in this specification, it shall be taken to mean the person, firm, or corporation, who has entered into contract with the owner for that portion of the work referred to in the particular section or paragraph of the specification wherein the work occurs.”

Paragraph 5 refers to the drawings, and makes it the duty of the contractor to notify the architects in the event of mistakes, omissions, etc., in the drawings, and of anything necessary to a clear understanding of the work to be done, or of errors as to “instruments furnished or in work done by other contractors.”

Pursuant to the agreement above set forth, the plaintiff proceeded to furnish the stone called for thereby, and prior to the bringing of this action delivered f. o. b. cars at Aberdeen all the stone contracted by it to be delivered, all of which stone was unloaded and [286]*286used in the said building by the said Lepper Construction Company; and prior to such use the defendant, its architects, and its superintendent knew that practically all of the stone which the defendant thereafter claimed to be defective and not in accordance with the said plans and specifications did not so comply with such plans and specifications; that is, substantially all the alleged defects and shortcomings of the stone were known by the defendant before the stone was used.

The plaintiff brought this action to recover an alleged balance of the purchase price of the said stone of $368.01, and alleged in its complaint, in substance, the making of a contract with the defendant for the delivery of the said stone, the delivery of the stone, the payment by the defendant of $3,431.99 on the purchase price thereof, and the indebtedness of the defendant for a balance of $368.01.

The defendant, in its answer, admitted the making of the contract, the alleged payment on account thereof, and then, by way of defense, alleged that the plaintiff had neglected to comply with the plans and specifications, and had failed to obtain a certificate from the architects that the material furnished by the plaintiff complied with such plans and specifications, and that certain unnecessary delay occurred in the furnishing of the stone, to the damage of the defendant in the sum of $500. And, further answering, the defendant, by way of defense and counterclaim, alleged the failure of the plaintiff to comply with the terms of the contract, to the damage of the defendant in the sum of $500, and demanded judgment against the plaintiff in the sum of $131.99. The plaintiff’s reply denied the allegations of the answer. The plaintiff had a verdict for $355.37, and this appeal is from an order denying the defendant’s alternative motion for a judgment notwithstanding the verdict or for a new trial.

1. The correspondence of the parties above set out, and so much of the plans and specifications as may, by reference, be deemed to be incorporated therein, constitutes the sole expression of their agreement, and, standing alone, it is questionable whether such correspondence shows that the minds of the parties ever met in contrac[287]*287tual coi3ipact.'' However, the pleadings concede the existence of an express contract, and these letters, as above stated, constitute the sole expression thereof, and the intent of the parties 3nust be sought therefro3n.

It is unquestionably true, as contended by the defendant, that if the contract conte3nplated that the plaintiff should procure the architects’ certificate as a condition precedent to the right to demand payment, then the plaintiff was not entitled to a verdict in this action; for it is admitted that the plaintiff procured no such certificate. The plans and specifications referred to are too voluminous to set out herein in full; but we are satisfied, from a careful consideration thereof, that paragraph 11, above quoted, has no application to this ease.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lawson & Nelson Sash & Door Co. v. Kraus-Anderson of St. Paul Co.
156 N.W.2d 208 (Supreme Court of Minnesota, 1968)
Granette Products Co. v. Arthur H. Neumann & Co.
203 N.W. 935 (Supreme Court of Iowa, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.W. 993, 117 Minn. 283, 1912 Minn. LEXIS 757, Counsel Stack Legal Research, https://law.counselstack.com/opinion/breen-stone-co-v-w-f-t-bushnell-co-minn-1912.