Lawson & Nelson Sash & Door Co. v. Kraus-Anderson of St. Paul Co.

156 N.W.2d 208, 279 Minn. 218, 1968 Minn. LEXIS 1182
Supreme Court of Minnesota·Decided February 2, 1968·No. No. 40,668·Published

Opinion

Rogosheske, Justice.

Plaintiff, as a subcontractor, brought suit against defendant, the general contractor, to recover the contract price for its manufacture of a part of the steeple of St. Joseph’s Catholic Church in Browerville. The steeple had been blown off by a windstorm in August 1962. Defendant was awarded the general contract to reconstruct the steeple pursuant to plans and specifications prepared by an architect. The work was to be completed in 120 days from July 3, 1963. On July 17, defendant entered into a subcontract with plaintiff to furnish labor and materials for an octagonal, spheroid dome and a base to hold it, to be manufactured ac[219] cording to the plans and specifications. Upon delivery to the site, these parts, which included eight ribs and four of the panels forming the dome, were to be hoisted to the top of the steeple with a large crane and thereupon incorporated by defendant into the steeple. The remaining four panels were then to be completed by defendant.

Upon plaintiff’s delivery on September 27, defendant found the construction of the dome to be defective. The ribs were not properly made, did not fit into the base, and did not give the dome the correct shape. At the time of delivery, rented scaffolding was in place around the steeple in readiness to complete the work in the time required, and arrangements had been made to rent a crane, which was delivered before the end of September. Choosing to avoid delay and to make use of the rented crane and scaffold, defendant placed the parts upon the steeple and, with knowledge of the defects, elected to retain possession of the dome and correct the deficiencies of plaintiff’s performance at the site. Upon defendant’s subsequent refusal to pay the contract price, plaintiff instituted this action. Defendant counterclaimed for damages of $5,523.45, its alleged cost of correcting the defects.

The issues of whether plaintiff “faithfully performed” its contract; whether plaintiff’s defective performance was excused because of defendant’s and the architect’s claimed approval of plaintiff’s interpretation and execution of the plans during the process of manufacturing the parts; whether defendant accepted plaintiff’s performance and waived its claim for damages; and whether defendant acted unreasonably in correcting the defects were submitted to the jury upon the theory that the subcontract was “not one for the sale of goods” governed by the Uniform Sales Act, Minn. St. 1961, § 512.01, et seq., but was for “work, labor, and materials” governed by the rules relating to budding contracts. As authorized by the court’s instructions, the jury returned a general verdict in favor of defendant for substantially the full amount of its counterclaim, offsetting the subcontract price of $4,200.

On appeal from a denial of its alternative motion for judgment n. o. v. or a new trial, plaintiff does not dispute the amount of defendant’s damages resulting from its admitted defective performance of the subcontract, nor does plaintiff raise any issues with respect to the sufficiency of the notice of the breach or whether defendant acted unreasonably in remedy[220] ing the defects in mitigation of its counterclaim for damages. Further, as we understand, plaintiff agrees that the questions submitted were jury issues and that the evidence sustains the jury’s findings, and does not challenge defendant’s recovery under rules governing defective performance of a building contract if such rules are applicable. Rather, the single question presented is whether the undisputed fact of defendant’s election to retain the parts manufactured by plaintiff and incorporate them into the building with knowledge of the defects constitutes an acceptance in full satisfaction of the contract as a matter of law which binds defendant to pay the contract price and waives its right to recover damages for the breach.

Plaintiff relies solely upon Breen Stone Co. v. W. F. T. Bushnell Co. 117 Minn. 283, 135 N. W. 993.1 In that case, the subcontractor agreed to furnish in accordance with plans and specifications cut building stone to a general contractor for use in the construction of a building in Aberdeen, South Dakota. Of the 700 stones furnished, a small number included in the first carload shipment were admittedly defective. The general contractor, with knowledge of the defects, accepted and used the stone in the building and made payment of all but $368 of the $3,800 contract price. Upon the subcontractor’s suit for the balance of the contract price and defendant’s counterclaim for $500 damages, the jury found for plaintiff and awarded the balance due. Upon appeal, the court affirmed and held that while there may have been error in submission of the case to the jury under rules governing building contracts, the error was harmless because the contract was not a building contract but one of sale and the contractor’s acceptance and use of the defective stone waived the contractor’s claim for damages for known defects. This holding was reached despite evidence, as an examination of the record reveals, that [221] the general contractor notified the subcontractor of the defects claimed when the shipment of the stone arrived at the building site.2 The trial court charged the jury that if it found that the plaintiff had not substantially performed the contract it could award the defendant his counterclaim. The issue of acceptance was not presented to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Lawson & Nelson Sash & Door Co. v. Kraus-Anderson of St. Paul Co., 156 N.W.2d 208, 279 Minn. 218, 1968 Minn. LEXIS 1182 (Mich. 1968).

156 N.W.2d 208 (Lawson & Nelson Sash & Door Co. v. Kraus-Anderson of St. Paul Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Elliott v. Caldwell
9 L.R.A. 52 (Supreme Court of Minnesota, 1890)
Schwartz v. Church of Holy Cross
62 N.W. 266 (Supreme Court of Minnesota, 1895)
St. Anthony Lumber Co. v. Bardwell-Robinson Co.
62 N.W. 274 (Supreme Court of Minnesota, 1895)
Breen Stone Co. v. W. F. T. Bushnell Co.
135 N.W. 993 (Supreme Court of Minnesota, 1912)