Ashland Lime, Salt & Cement Co. v. Shores

81 N.W. 136, 105 Wis. 122, 1899 Wisc. LEXIS 357
CourtWisconsin Supreme Court
DecidedDecember 15, 1899
StatusPublished
Cited by36 cases

This text of 81 N.W. 136 (Ashland Lime, Salt & Cement Co. v. Shores) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ashland Lime, Salt & Cement Co. v. Shores, 81 N.W. 136, 105 Wis. 122, 1899 Wisc. LEXIS 357 (Wis. 1899).

Opinion

Maeshall, J.

Appellant’s counsel contend that the trial' court erred in confirming the report of the referee as to the following: (1) That the principal contract was substantially performed.; (2) that the contract with the Northern Manufacturing Company was substantially performed; (3) that the architect’s certificate was waived; (4) that the damages-to the principal contractor by failure of the Northern Manufacturing Company and its assignee to perform the subcontract were $1,000; (5) refusing to apply, on the claim of the Ashland Lime, Salt & Cement Company, payments made to such company by the principal contractor of moneys furnished such contractor by appellant, Shores; (6) the contract for the plumbing work by Dullanty was substantially pen formed.

1 and 2. The first two. assignments of error can best be considered together. They are mainly ruled on the undisputed evidence by Laycock v. Moon, 97 Wis. 59, and Laycock v. Parker, 103 Wis. 161. The doctrine declared in those cases may be briefly stated thus: Where a building contract provides that the building shall be constructed according to certain plans and specifications to the satisfaction of the supervising architect, who shall inspect all material and work as the building is constructed, with power to reject any material or work not deemed by him to be in compliance with the contract, and to. require unsatisfactory' con[128]*128structions to be removed and the work done over in a satisfactory manner, the manifest' intent is that unsatisfactory material or. construction shall be. promptly rejected, and that the architect shall not, by silence, allow unsatisfactory construction to proceed to a point where its removal from the building will be attended with serious loss to the builder, and then reject it; that a failure to reject material or work seasonably, and in the manner contemplated by the contract, operates as a waiver of defects in regard thereto and an irrevocable acceptance of such material or work as satisfactory under the contract, in the absence of some clear, unmistakable provision in such contract to the contrary. That is a reasonable and just doctrine to apply in cases like this. If the owner stipulates for inspection and approval of the work under a building contract as the building is constructed, and for a representative of his own to compel compliance with the contract at every step, if such representative fails to perform his duty the loss should fall on the owner of the building, and not be shifted to the builder, who may have been lured into the belief that his work and material were satisfactory till too late to remedy defects therein without .serious loss. The owner should look to his architect. He should be, and is, bound the same as if he were upon the ground himself, charged with the duty of accepting or rejecting material or construction as soon as there is a reasonable opportunity for inspection of it. That is but an application >of the elementary principle, that where property is delivered by one person to another, as fulfilling an executory contract between them requiring such delivery, and the latter neglects to notify the former that the property is not accepted as complying with the contract within a reasonable time after .a fair opportunity to inspect it, an acceptance will be inferred. Pratt v. Peck, 70 Wis. 620; Barton v. Kane, 17 Wis. 37; Locke v. Williamson, 40 Wis. 377; Olson v. Mayer, 56 Wis. 551. What is a reasonable time for inspection and rejection, [129]*129must necessarily be governed by tbe nature of the contract •and the consequences of delay, and all the circumstances. Under a building contract requiring constant presence and oversight of the work by a supervising architect, for the owner, for the very purpose of preventing any unsatisfactory material being wrought into the building or unsatisfactory construction remaining a part of it, a reasonable time in which to decide such matters is limited to a reasonable time for proper inspection. Any considerable delay in that regard must operate, by all equitable considerations, as an acceptance, except as to defects not discoverable by reasonable attention to the duties of inspection.

The foregoing is in accordance with authorities elsewhere. Wait, Engineering Jur. §§ 467, 468; Wright v. Meyer, 25 S. W. Rep. 1122; Linch v. Paris, L. & G. E. Co. 80 Tex. 23. In the latter case it was said that ‘ where the owner, under the provisions of a building contract, has a representative •on the ground to inspect material and workmanship as operations progress, and with authority to reject any not ■deemed by him to be in accordance with such contract, and to compel a forfeiture of unsatisfactory work and its removal from the building and grounds, prompt action on the part of such architect is demanded, and any delay to the prejudice of a contractor will operate as a waiver of defects.’ That is on all fours with the case before us. In Wright v. Meyer it is said, on the same subject, “ When the architect is present and has knowledge of the character of material being placed in the improvement without objection at the time, his conduct is an approval of the same which cannot be revised by him to the prejudice of the contractor.”

There is another significant feature about the contract under consideration. The progress certificates were not mere approximate estimates of the value of labor and materials wrought into the building during the previous months, which, under many authorities, are subject to subsequent [130]*130revision, leaving out tbe question of estoppel. By tbe terms of tbe contract tbe monthly estimates were confined to sucb parts of tbe building as bad been constructed so as to satisfy tbe calls of tbe contract. Sucb certificates, without some clear saving clause, are -conclusive in the absence of fraud or mistake. Hudson, Building Contracts, 285. Here there is a clause to tbe effect that no certificate, except tbe final certificate, shall be conclusive evidence of tbe acceptance of tbe contract, either in whole or in part, against any claim of tbe owner. That, however, must be considered, if possible, in connection with tbe previous clause confining progress certificates to satisfactory work, so as to make the two clauses consistent and give significance to each. That can only be done by bolding that tbe latter clause was intended to limit tbe conclusive effect of progress certificates to patent defects, sucb as were discoverable by tbe exercise of ordinary care. That is a reasonable construction of tbe contract. Most of tbe defects complained of were of that character. Tbe progress certificates show an acceptance of all tbe work done except about $600 out of $30,570, tbe total contract price and tbe value of all extras. Tbe accepted work covered more than tbe original contract price by about $1,500.

A careful reading of tbe contract leads to tbe conclusion that tbe only final certificate contemplated by the parties was tbe last in tbe seibes of progress certificates. There is no call for a final certificate covering all tbe work. The-only place a final certificate is mentioned is where it is said that no certificate except tbe final certificate shall be conclusive evidence of performance of tbe contract. Under sucb a contract tbe last progress certificate is to all intents and purposes tbe final certificate and tbe only final certificate-that is required.

Now it is undisputed that fbe supervising architect, John W. Foster, did not, from tbe beginning to tbe end of tbe [131]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A-G-E Corp. v. State Ex Rel. State Department of Transportation
2006 SD 66 (South Dakota Supreme Court, 2006)
W. G. Slugg Seed & Fertilizer, Inc. v. Paulsen Lumber, Inc.
214 N.W.2d 413 (Wisconsin Supreme Court, 1974)
Wiggins Construction Co. v. Joint School District No. 3
151 N.W.2d 642 (Wisconsin Supreme Court, 1967)
Sid Grinker Co. v. Craighead
146 N.W.2d 478 (Wisconsin Supreme Court, 1966)
City of Wauwatosa v. Jacobus & Winding Concrete Construction Co.
271 N.W. 21 (Wisconsin Supreme Court, 1937)
Milwaukee County v. H. Neidner & Co.
263 N.W. 468 (Wisconsin Supreme Court, 1936)
J. G. Jansen, Inc. v. Rilling
232 N.W. 887 (Wisconsin Supreme Court, 1931)
Granette Products Co. v. Arthur H. Neumann & Co.
221 N.W. 197 (Supreme Court of Iowa, 1928)
White v. Mitchell
213 P. 10 (Washington Supreme Court, 1923)
Collins v. Ramish
188 P. 550 (California Supreme Court, 1920)
School District of Eau Claire v. Blystone
170 N.W. 721 (Wisconsin Supreme Court, 1919)
Keachie v. Starkweather Drainage District
170 N.W. 236 (Wisconsin Supreme Court, 1919)
Grant Marble Co. v. Marshall & Ilsley Bank
165 N.W. 14 (Wisconsin Supreme Court, 1918)
Stewart v. Breckenridge
169 P. 543 (Supreme Court of Colorado, 1917)
Township of Rockland v. Oxnam
164 N.W. 494 (Michigan Supreme Court, 1917)
Quast v. Guetzkow
159 N.W. 810 (Wisconsin Supreme Court, 1916)
Lindenmann v. Kopczynski
144 N.W. 196 (Wisconsin Supreme Court, 1913)
Oscar Smith & Sons Co. v. Janesville Batting Mills
137 N.W. 966 (Wisconsin Supreme Court, 1912)
Pippy v. Winslow
125 P. 298 (Oregon Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
81 N.W. 136, 105 Wis. 122, 1899 Wisc. LEXIS 357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ashland-lime-salt-cement-co-v-shores-wis-1899.