City of Wauwatosa v. Jacobus & Winding Concrete Construction Co.

271 N.W. 21, 223 Wis. 401, 110 A.L.R. 131, 1937 Wisc. LEXIS 9
CourtWisconsin Supreme Court
DecidedJanuary 12, 1937
StatusPublished
Cited by7 cases

This text of 271 N.W. 21 (City of Wauwatosa v. Jacobus & Winding Concrete Construction Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Wauwatosa v. Jacobus & Winding Concrete Construction Co., 271 N.W. 21, 223 Wis. 401, 110 A.L.R. 131, 1937 Wisc. LEXIS 9 (Wis. 1937).

Opinion

Nelson, J.

All of the testimony having been adduced by the plaintiff, there is little, if any, dispute as to the facts. So many of the facts as are necessary to an understanding of the opinion will be summarized. The plaintiff is a municipal corporation. Jacobus & Winding Concrete Construction Company, hereafter called the “company,” is a Wisconsin corporation engaged in the general construction business. On or about August 3, 1928, the city and the company entered into a contract whereby the company agreed to grade and pave with re-enforced concrete Hawthorne avenue from Greenfield avenue to the west limits of the city, at the agreed [403]*403price of seventy cents per cubic yard for excavating, seventy cents per cubic yard for filling, and one dollar and seventy-six cents per square yard for paving, including integral curb and gutter, all in accordance with plans and specifications theretofore approved by the common council of the city. C. C. Jacobus and D. C. Jacobus signed the contract as sureties. The contract and specifications contained many provisions clearly indicating that the city engineer and board of public works should have complete control and supervision of the work. Some of such provisions are as follows:

“No work shall be done under this contract except in the presence of the city engineer or his representative. . . .
“The city engineer is authorized whenever he deems it proper or necessary in the execution of the work to make any alteration. . . .
“The contractor shall perform all the work herein specified under the direction and superintendence of the city engineer and to his entire satisfaction, approval and acceptance, and to that of the board of public works.
“All material to be incorporated in the work, all labor performed, and all appliances, tools and methods used shall be subject to the inspection and approval or rejection of the city engineer.
“The city engineer shall decide all questions relating to measurements, the materials used, the character of the work performed, and as to whether the rate of progress is such as to comply with these specifications.
“If any authorized agent of the city engineer shall point out to the contractor any neglect or disregard of the specifications, such defect shall at once be remedied and further defective work shall at once be discontinued; but the right of final acceptance or condemnation of the work will not be waived by any reason thereof nor by any other act of the city of Wauwatosa by its officers or agents. . . .
“No concrete shall be deposited until the subgrade is checked and accepted by the city engineer.”

On October 3, 1928, the company commenced work under the contract and completed the work seven days thereafter. [404]*404During the progress of the work, either the city engineer or his assistant or representative, the inspector on the job, inspected the work. The work was all performed in the open, and any deficiency in the thickness of 'the concrete was obviously easily discoverable by reasonable attention to the duties of inspection. The company did not conceal, or attempt in any manner to conceal, from the plaintiff, its officers, or representatives, the manner or method of doing the work or the quantity or quality of the material used. On November 2, 1928, the city engineer certified to the board of public works that the company had completed the work “all in accordance with the plans and specifications,” but recommended that the sum of $300 be withheld from the amount due the company to insure the trimming up of the grade of the sidewalk portions of the street and cleaning the manholes. The board of public works thereafter on the same day adopted a resolution which provided “that the work of grading and paving” this street “be and the same -hereby is accepted,” and provided for the withholding of the $300 as recommended by the city engineer. On November 6th, following, the common council adopted a resolution providing for the issuance of special improvement certificates and for the payment of the city’s share of the contract price. The resolution recited that the “grading and paving has been done pursuant to directions of the common council . . . and in accordance with the terms of written contracts heretofore entered into.”

The concrete was laid in two slabs, each of which ran from the curb line to the center of the street. About two years after the pavement was accepted the slab on one side of the street settled slightly, and the city deemed it necessary to repair the unevenness by spreading a thin layer of asphalt at the places where the unevenness existed. The city thereafter caused cores to be cut from the pavement, most of which revealed that the pavement at the places from which the cores [405]*405were cut was not as thick as the contract provided. At the time of the trial a number of other cores were cut out from other points in the street. Most of these revealed a shortage in the thickness of the pavement.

Prior to the laying of the concrete, the street was graded in accordance with the grades furnished by the city engineer or his assistants.

The court specifically found as follows:

“8. That the pavement as laid has been in constant use since the completion of said contract and that at the present time is in apparent good condition. That there is no evidence that it is not adequate for the use intended. That there is no evidence from which it can be determined that the pavement as constructed does not substantially comply with the contract between said parties as to thickness thereof. That the evidence fails to show that the departure from the specified thickness of the concrete were of such nature or extent as to imply dishonesty or fraud.”

The court concluded that by its acceptance of the work as substantially performed under the terms of the contract, and the payment of the amounts due thereunder, the city waived any claim for damages that it might have had because of a departure from the terms of said contract, and is estopped from asserting any claim for damage against the defendant.

The city assigns numerous errors and makes numerous contentions, all of which the court has carefully considered, but which in our view need not be specifically discussed considering the disposition which must, in our opinion, be made of this case.

The plaintiff seeks to recover a proportion of the amount paid the company by it and the property owners based on the shortage in the thickness of the pavement, which shortage it asserts is evidenced by the cores cut from the street. The court below was of the opinion that the plaintiff failed to prove any damages, it, apparently, not being greatly impressed by the testimony of the engineers who computed the [406]*406damages upon the basis of an engineering formula “that the strength [and therefore the value] of a beam is proportional to the square of the diameter.”

In our view this case is ruled by a principle of law which renders it unnecessary for us to consider many of the errors assigned by the plaintiff, none of which relate to that principle of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Becker v. Crispell-Snyder, Inc.
2009 WI App 24 (Court of Appeals of Wisconsin, 2009)
Ekstrom v. State
172 N.W.2d 660 (Wisconsin Supreme Court, 1969)
City of Granville v. Kovash, Incorporated
118 N.W.2d 354 (North Dakota Supreme Court, 1962)
E. H. Marhoefer, Jr., Co. v. Mount Sinai, Inc.
190 F. Supp. 355 (E.D. Wisconsin, 1961)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Osceola v. Gjellefald Construction Co.
279 N.W. 590 (Supreme Court of Iowa, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
271 N.W. 21, 223 Wis. 401, 110 A.L.R. 131, 1937 Wisc. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-wauwatosa-v-jacobus-winding-concrete-construction-co-wis-1937.