Laycock v. Moon

72 N.W. 372, 97 Wis. 59, 1897 Wisc. LEXIS 24
CourtWisconsin Supreme Court
DecidedSeptember 28, 1897
StatusPublished
Cited by17 cases

This text of 72 N.W. 372 (Laycock v. Moon) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laycock v. Moon, 72 N.W. 372, 97 Wis. 59, 1897 Wisc. LEXIS 24 (Wis. 1897).

Opinion

Newmah, J.

The plaintiff was bound, by his contract, to complete his job to the “entire satisfaction” of the defendant and his architect. The defendant and his architect were reciprocally bound to make inspection of the work and materials, as the work progressed. They had the power to accept or reject work of materials, and to require unsatisfactory work to be redone in a satisfactory manner, and unsatisfactory materials to be removed and their places supplied-with other materials, such as should be in conformity with the contract, and satisfactory. This all clearly implies that the work and materials were to be accepted or rejected at the-time of such inspection, and during the progress of the work. It was no doubt intended, and the spirit of the contract implies, that work or materials which were not in conformity with the contract, and were not satisfactory, and, for that reason, were to be rejected, should be rejected at once, to-the end that all faults might be corrected without loss or detriment to either party. This provision was a prudent precaution against the surprise of a suppressed dissatisfaction sprung at the end of the work. It was intended to-' prevent such surprises by requiring inspection pari passu, as-the work went on, and a prompt rejection of either work or materials not conformable with the contract. This provision of the contract was, in effect, an affirmative stipulation by the defendant to accept or reject, as the work progressed, such as should be deemed not conformable with the contract, and unsatisfactory. Failure to express dissatisfaction [63]*63as the work progressed might fairly be interpreted as acceptance. Such acceptance must be deemed final and irrevocable ; else the plaintiff may be lured on, by a delusive appearance, into expenditures for the completion of an expensive-work, which is foredoomed to rejection. This stipulation of the contract was intended to avert from him such ill-fortune.-

Clearly, the defects claimed in the foundation wall, such as too small footing stones and the absence of slushing of the mortar, were obvious to the stipulated inspection. It is also clear that whatever-dissatisfaction was expressed was heeded and the fault amended, so that no expressed dissatisfaction rested on the work as it progressed, or within a reasonable time after its completion. The architect expressed his entire satisfaction with the work. If the defendant failed at times to inspect the work, that may have been to his own loss. He must be bound, nevertheless, by the acquiescence of the architect who represented him. There was no conflict in the testimony which tends to show that the work was accepted, and the question needed not to have gone to the jury. Eor that reason it is unnecessary to examine the charge of the court. If wrong, it did thé defendant no harm.

Such matters relating to the completion of the work as the pointing, cleaning, and staining of the walls might be waived by the defendant. Apparently, they were so waived. At least, the verdict of the' jury must be deemed to have settled that question.

Ho reversible error is found.

By the Court. — The judgment of the circuit court is affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A-G-E Corp. v. State Ex Rel. State Department of Transportation
2006 SD 66 (South Dakota Supreme Court, 2006)
Stevens Construction Corp. v. Carolina Corp.
217 N.W.2d 291 (Wisconsin Supreme Court, 1974)
City of Wauwatosa v. Jacobus & Winding Concrete Construction Co.
271 N.W. 21 (Wisconsin Supreme Court, 1937)
Milwaukee County v. H. Neidner & Co.
263 N.W. 468 (Wisconsin Supreme Court, 1936)
Granette Products Co. v. Arthur H. Neumann & Co.
221 N.W. 197 (Supreme Court of Iowa, 1928)
Keachie v. Starkweather Drainage District
170 N.W. 236 (Wisconsin Supreme Court, 1919)
Corse v. Linke
133 N.W. 598 (Wisconsin Supreme Court, 1911)
City St. Improvement Co. v. City of Marysville
101 P. 308 (California Supreme Court, 1909)
Siebert v. Roth
95 N.W. 118 (Wisconsin Supreme Court, 1903)
Schliess v. City of Grand Rapids
90 N.W. 700 (Michigan Supreme Court, 1902)
Ashland Lime, Salt & Cement Co. v. Shores
81 N.W. 136 (Wisconsin Supreme Court, 1899)
Pritzlaff Hardware Co. v. Berghoefer
79 N.W. 564 (Wisconsin Supreme Court, 1899)
Laycock v. Parker
79 N.W. 327 (Wisconsin Supreme Court, 1899)
McAlpine v. Trustees of St. Clara Female Academy
78 N.W. 173 (Wisconsin Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
72 N.W. 372, 97 Wis. 59, 1897 Wisc. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laycock-v-moon-wis-1897.