Laycock v. Parker

79 N.W. 327, 103 Wis. 161, 1899 Wisc. LEXIS 190
CourtWisconsin Supreme Court
DecidedMay 16, 1899
StatusPublished
Cited by108 cases

This text of 79 N.W. 327 (Laycock v. Parker) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laycock v. Parker, 79 N.W. 327, 103 Wis. 161, 1899 Wisc. LEXIS 190 (Wis. 1899).

Opinion

Dodge, J.

1. Certain of the findings are very sweeping in their effect upon the rights of the parties, and from their correctness or incorrectness would result very different rules of law in the decision. We find no clear preponderance of the evidence against the finding of the court that the defendant E. H. Parker was from beginning to end the agent of the defendant Anna E. Parker, his wife, in regard to all matters involved in the construction of this building, and in the making of modifications or carrying out of the contract. Where we so concur with the court below no good purpose can be served by a discussion of the evidence here. It is sufficient to state such concurrence. It may, however, be said generally that the conduct of the husband and wife is such as to raise an almost irresistible inference that she had full knowledge that he was assuming to act for her, and, if so, his conduct in so doing, and her silence and nonattendance, are the most cogent evidence as to the actual understanding between them that he should take full charge. Neither do we find any preponderance of evidence against the finding of the court that the provisions of the contract were waived by both parties, requiring written orders of the architects in advance for changes, and requiring the certificates of the architects as a prerequisite of payments on the contact, and with reference to the fixing of the value of changes and omissions by the architects. Nor can we feel justified in disturbing the findings of the court as to the unfairness, dishonesty, andgross incorrectness of the acts of the architects in certifying to certain pretended computations some six months after the suit was commenced, or in then [168]*168declaring their dissatisfaction with the work done. On the other hand, we think it must be understood that the finding of a declaration of satisfaction made by the defendant E. II. Parker, in company with his architect, after a full examination of the building, in the light of the other evidence, constituted a finding that the defendant and the architect were satisfied, and accepted the building as a substantial compliance with the contract, which finding has sufficient support in the evidence. We also find abundant support in the evidence for the further general findings that all omissions of material or work required by the contract, which did not occur upon the order of the defendant, occurred inadvertently and unintentionally; that the contractors acted honestly and in good faith, and made no wilful departure from the plans and specifications; that neither architects nor defendants, though having full knowledge, made any complaint about the' way the work was being done; that before the commencement of the action the contractors fully and substantially completed their contract in substantial compliance with the terms thereof, and constructed a good and suitable building, which was taken possession of in January, 1894, and has ever since been occupied for the purposes for which it was erected, and that it is reasonably well adapted for such purposes; that the contractors made all changes, and did all work required to complete said building, requested or required of them by either the architects or the defendants; and that the defendants took possession and accepted the building as a completed building. The omissions not authorized by defendant, which the court found to have occurred, are of the most trifling character, amounting to only about $39, which is allowed on the counterclaim. ■

The evidence is extremely voluminous, and the method of printing the same by classification under the items of appellant’s assignments of error has made difficult the examination thereof upon any other lines, and continual reference to [169]*169the manuscript bill of exceptions bas been found necessary. This' arrangement of the case is not to be approved. We-have, however, examined the same with great care, and on most subjects more than once. The case was tried with thoroughness before a competent referee, J. C. Gores, Esq.,, who evidently gave it the fullest consideration,, having before him the various witnesses, whose direct conflict as to-facts, and especially as to matters of opinion, runs throughout the case. He had, in addition, the advantage of personal knowledge of the character, intelligence, and fairness of' many of them, and it is obvious that he considered some of them entitled to little or no credit. He had the further advantage, of which this court is deprived, of the explanation and immediate application of testimony to the plans, which is, of course, impossible to fully accomplish in the transcript of the testimony. In many instances it is extremely difficult from the record to ascertain the exact item of construction to which witnesses testify. That difficulty did not rest upon the referee, who had the plans to which the witness, referred open before him, and could assure himself of the subject about which testimony was being given. The trial before the referee was followed by an argument before the-circuit court, extending, we are told, over a period of nine days, where again all of these advantages, of which this court is deprived, except the actual presence of the witnesses, existed in favor of a correct understanding of the details by the circuit judge, who doubtless was further aided by his-personal knowledge of, and acquaintance with, some of the principal witnesses. The consideration by the court was not perfunctory or general, for he went into the details, and modified certain of the allowances. A case can hardly be suggested where'it would be more perilous for an appellate court, upon printed evidence confused as this, and without, the opportunity to judge from observation as to the fairness,. [170]*170intelligence, or credibility of witnesses, to attempt to correct the conclusions, reached below as to tbe weight or preponderance of the evidence on specific items or subjects, unless an error in that respect appears with great clearness and •certainty.

As a result of those general findings, the conclusion is irresistible that the plaintiff is entitled to recover the contract price of the building, together with the reasonable market value of the additions and extras ordered by the defendant, less the reasonable value of the work and materials •omitted, from which should also be' deducted the amount found by the court upon defendant’s counterclaim for delay in completion, and value of use of defendant’s heating plant; which is substantially the general conclusion reached by the court below. Laycock v. Moon, 97 Wis. 59; Bannister v. Patty's Ex'rs, 35 Wis. 215; Trowbridge v. Barrett, 30 Wis. 661; Smith v. Alker, 102 N. Y. 87; Smith v. Guggerty, 4 Barb. 614; Sinclair v. Tallmadge, 35 Barb. 602; Flaherty v. Miner, 123 N. Y. 382.

The defense tendered consists: first, in the claim that many of the items allowed to the plaintiff as extras are not-properly such, or that they "have been allowed at too high n price; second, that many omissions other than those allowed by the court below occurred, and that deduction .should be made therefor, also that the amounts allowed for certain of the omissions are less than their reasonable value; and, third, a series of claims for damages of a more general character. The findings classify these respective claims in much detail, defining what pf the extras and what of the ■omissions occurred, and the reasonable value of each item.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trease v. Tri-State Adjustments, Inc.
934 F. Supp. 2d 1016 (E.D. Wisconsin, 2013)
LINDQUIST FORD, INC. v. Middleton Motors, Inc.
665 F. Supp. 2d 1009 (W.D. Wisconsin, 2009)
Staver v. Milwaukee County
2006 WI App 33 (Court of Appeals of Wisconsin, 2006)
Crest Inc. v. Costco Wholesale Corp.
128 Wash. App. 760 (Court of Appeals of Washington, 2005)
Bouten Construction Co. v. H.F. Magnuson Co.
992 P.2d 751 (Idaho Supreme Court, 1999)
Taylor v. Shigaki
930 P.2d 340 (Court of Appeals of Washington, 1997)
Colonial Imports v. Carlton Northwest, Inc.
921 P.2d 575 (Court of Appeals of Washington, 1996)
Erickson Ex Rel. Wightman v. Gundersen
515 N.W.2d 293 (Court of Appeals of Wisconsin, 1994)
Allison v. Ticor Title Insurance
979 F.2d 1187 (Seventh Circuit, 1992)
R.S. Deering Mechanical Contractors v. Livesey Co.
468 N.W.2d 758 (Court of Appeals of Wisconsin, 1991)
Little v. Roundy's, Inc.
449 N.W.2d 78 (Court of Appeals of Wisconsin, 1989)
Nicholson v. Home Insurance Companies, Inc.
405 N.W.2d 327 (Wisconsin Supreme Court, 1987)
Leliefeld v. Panorama Contractors, Inc.
728 P.2d 1306 (Idaho Supreme Court, 1986)
Waukesha Concrete Products Co. v. Capitol Indemnity Corp.
379 N.W.2d 333 (Court of Appeals of Wisconsin, 1985)
United Nuclear Corp. v. Allendale Mutual Insurance
709 P.2d 649 (New Mexico Supreme Court, 1985)
Johnson v. Skelly Oil Co.
359 N.W.2d 130 (South Dakota Supreme Court, 1984)
Johnson v. Pearson Agri-Systems, Inc.
350 N.W.2d 127 (Wisconsin Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
79 N.W. 327, 103 Wis. 161, 1899 Wisc. LEXIS 190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laycock-v-parker-wis-1899.