Flaherty v. . Miner

25 N.E. 418, 123 N.Y. 382, 33 N.Y. St. Rep. 681, 78 Sickels 382, 1890 N.Y. LEXIS 1744
CourtNew York Court of Appeals
DecidedOctober 28, 1890
StatusPublished
Cited by25 cases

This text of 25 N.E. 418 (Flaherty v. . Miner) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flaherty v. . Miner, 25 N.E. 418, 123 N.Y. 382, 33 N.Y. St. Rep. 681, 78 Sickels 382, 1890 N.Y. LEXIS 1744 (N.Y. 1890).

Opinion

Earl, J.

In June, 1881, the plaintiff entered into a written contract with the defendants to excavate and remove the earth and boulders from certain lots in the city of FTew York, upon which they were to erect a building. It was provided in the contract that they should pay him $3,500 for the work, in payments as it progressed. It was also provided that before he could demand any payment he should obtain the certificate of the architect employed by them, tie entered upon the execution .of the contract, and during the progress of the work, received from them $900. After their refusal to pay him the balance of the contract price he brought this action to recover the same.. He alleged in his complaint that all the portions of the contract relating to the certificate of the architect were inserted therein by mistake, and, besides other relief, he prayed that the contract should be reformed by striking therefrom so much as related to the architect’s certificate. The answer put in issue all the material allegations of the complaint, and the plaintiff noticed the action for trial at a Special Term as an equity action. At that term the defendants appeared, and, claiming a jury trial, moved that the case be stricken from the Special Term calendar; and upon their stipulation that it ipight be tried at a Circuit before a jury with the same effect as if tried at an equity term of the court as to the reformation of the contract, the court ordered the case to be stricken from the calendar ;■ and it was thereafter moved for trial at a Circuit Court, and at the commencement of the trial plaintiff’s comisel handed to the. court the stipulation just referred to. Thereupon the defendants’ counsel stated as follows: “ That he claimed in this action that the issues in the case were triable *387 by jury, and he claimed such trial; that there was no necessity for any reformation of the contract, and no claim was made by the defendants that the plaintiff was to erect a building which cost between $50,000 and $60,000, while this contract- was for but $3,500; that the defendant makes no claim that the plaintiff was to do anything other than the excavating, digging, removing of all earth, boulder and other matter, and leave sand for completion oí work on the premises 312 and 314 Eighth avenue, for the sum of $3,500, payments to be made as the work progressed: that the contract did not include underpinning of adjoining premises, and rocks were to be removed by other parties.” The court then directed that the trial should proceed before the jury.

Upon the trial the plaintiff offered evidence bearing upon the issue as to the reformation of the contract, and the defendants’ counsel objected to such evidence, and, upon his objection, it was excluded, and no evidence was received bearing upon that issue. The trial proceeded, and it was undisputed that the plaintiff had been paid only $900, and the jury awarded hiña a verdict for $2,000 besides. interest. Judgment upon the verdict having been affirmed, the defendants have brought this appeal, and they now claim, among other things, that the plaintiff was not entitled to payment without the production to them of the architect’s certificate, as required in the contract as originally drawn.

We think the counsel for the plaintiff is right in his claim that that portion of the contract requiring the production of the certificates must be deemed to have been stricken from the contract, and thus that the contract was reformed in reference thereto. We think that is the plain purport and effect of the stipulation given at the commencement of the trial, and that it was so understood by the defendants’ counsel when, upon Ms objection, all the evidence offered on the part of the plamtiff upon the issue as to 'the reformation of the contract was excluded by the court. After what took place upon the trial, it would be extremely unjust now to hold that the plaintiff was bound by so much of the contract as he claimed was inserted *388 by mistake, and the case should now be treated as if the contract had been reformed as prayed in the complaint.

Thus the only issue to be tried at the Circuit was, whether the plaintiff had performed his contract. Upon that issue, the plaintiff gave evidence tending to show that he had performed his contract, and that the defendants promised to pay him the balance of the contract price. The defendants gave evidence tending to show that he had not performed liis contract, and that they had been obliged to expend considerable sums of money to complete the work which he had contracted to do ; and the trial judge charged the jury that, if he had not substantially performed Ms contract, he could not recover the balance of the contract price; but that, .if he had substantially performed the contract, although a small and unimportant portion thereof remained to be performed, he could recover the balance of the contract price less the expense of performing the portion left unperformed by him. There was no exception to the rule of law thus laid down, and there could be no valid exception thereto. (Glacius v. Black, 50 N. Y. 145; Heckmann v. Pickney, 81 id. 211; Nolan v. Whitney, 88 id. 648 ; Whelan v. Ansonia Clock Co., 97 id. 293.)

It is true that the jury apparently allowed the defendants $600 for the expense of doing work which the plaintiff was bound, under his contract, to do; and if it had appeared upon the trial, without dispute, that such a substantial portion' of the work remained undone, and the objection had been- props erly taken, it may well be that the plaintiff could not have recovered upon the theory of a substantial performance. But there is no exception which now presents the point to us. There was proof upon the trial tending to show substantial performance. The proper rule of law was laid down to the jury, and there is no exception wliicli we can consider upon wMch the defendants can claim that the judgment should now be reversed because there was not substantial performance. The trial judge could have set aside the verdict, because- the jury either misconceived the facts or his instructions upon the law. But this court reviews only exceptions pointing out errors.

*389 There was also evidence from which the jury could have inferred that the defendants waived any further performance on the part of the plaintiff. He testified that when he left there was some -more work to be done, and that the defendants promised to send him word ivhenever they wanted any more of the earth removed, and that they never sent him word. The evidence showed that subsequently, some two or three months after he left the work, he sent men and teams to the ■ lots to remove more of the earth, and that the defendants prohibited such removal at that time. For this reason, therefore, the jury could have found upon the evidence that the defendants waived further performance of the contract on the part of the plaintiff.

There was still another groirnd upon which the plaintiff could have been excused from complete performance in case the performance was in fact incomplete. The contract required the defendants to make the plaintiff payments as the work progressed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People Ex Rel. Rapid Transit Subway Construction Co. v. Craven
104 N.E. 922 (New York Court of Appeals, 1914)
New Publication Co. v. Stern
127 N.Y.S. 393 (Appellate Terms of the Supreme Court of New York, 1911)
Harris Lumber Co. v. Wheeler Lumber Co.
115 S.W. 168 (Supreme Court of Arkansas, 1908)
Hebert v. Dewey
77 N.E. 822 (Massachusetts Supreme Judicial Court, 1906)
Condon v. Church of St. Augustine
112 A.D. 168 (Appellate Division of the Supreme Court of New York, 1906)
Desmond-Dunne Co. v. . Friedman-Doscher Co.
56 N.E. 996 (New York Court of Appeals, 1900)
Bird v. St. John's Episcopal Church of Elkhart
56 N.E. 129 (Indiana Supreme Court, 1900)
Laycock v. Parker
79 N.W. 327 (Wisconsin Supreme Court, 1899)
Shepard v. Mills
70 Ill. App. 72 (Appellate Court of Illinois, 1897)
Ringle v. . Wallis Iron Works
44 N.E. 175 (New York Court of Appeals, 1896)
Bradford v. Whitcomb
32 S.W. 571 (Court of Appeals of Texas, 1895)
Canavan v. Dwyer
35 N.Y.S. 763 (New York Court of Common Pleas, 1895)
Andersen v. Petereit
33 N.Y.S. 741 (New York Supreme Court, 1895)
Duell v. McCraw
33 N.Y.S. 528 (New York Supreme Court, 1895)
Keeler v. Herr
41 N.E. 750 (Illinois Supreme Court, 1895)
Wolfe v. Horn
33 N.Y.S. 173 (New York Court of Common Pleas, 1895)
Brady v. Cassidy
29 N.Y.S. 45 (New York Court of Common Pleas, 1894)
Lewis v. Yagel
28 N.Y.S. 833 (New York Supreme Court, 1894)
Ansonia Brass & Copper Co. v. Gerlach
28 N.Y.S. 546 (New York Court of Common Pleas, 1894)
Smith v. Corn
23 N.Y.S. 326 (New York Court of Common Pleas, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
25 N.E. 418, 123 N.Y. 382, 33 N.Y. St. Rep. 681, 78 Sickels 382, 1890 N.Y. LEXIS 1744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flaherty-v-miner-ny-1890.