Duell v. McCraw

33 N.Y.S. 528, 86 Hun 331, 93 N.Y. Sup. Ct. 331, 67 N.Y. St. Rep. 163
CourtNew York Supreme Court
DecidedMay 4, 1895
StatusPublished
Cited by3 cases

This text of 33 N.Y.S. 528 (Duell v. McCraw) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duell v. McCraw, 33 N.Y.S. 528, 86 Hun 331, 93 N.Y. Sup. Ct. 331, 67 N.Y. St. Rep. 163 (N.Y. Super. Ct. 1895).

Opinion

MERWIN, J.

This action is brought to recover a balance claimed to be due on a building contract. On the 24th October, 1890, the plaintiff Duell and the defendant entered into a contract, in writing, for the erection by Duell, on or before April 1, 1891, of a store and tenement block on a lot of defendant on State street, in the city of Binghamton. Specifications and drawings were attached that were made by an architect, Mr. Reynolds. The work was to be done under his direction, to his satisfaction, and to be testified by his certificate. The price was $7,150, of which $400 was payable when the foundation was completed, $500 when the frame was up and sheathed, $1,000 when the brickwork was finished, $1,000 when the block was inclosed, $1,000 when the block was plastered, $1,000 when the block was cased and trimmed, and the balance, of $2,250, when the block was completed, “provided that in each of the said cases a certificate be obtained from the architect that the payment is due.” The sixth clause of the contract was as follows:

“Sixth. Should any dispute arise respecting the true construction or meaning of the drawings or specifications, the same shall be decided by the architect, and his decision shall be final and conclusive; but, should any dispute arise respecting the true value of extra work or work omitted, the same shall be valued by two competent persons,—one employed by the owner, and the other by the contractor,—and those two shall have power to name an umpire, whose decision shall be binding on all parties.”

The tenth or last clause was as follows:

“Tenth. The last payment on this contract shall not be paid until all charges for extra work and allowances for omissions have been rendered,' agreed to, and certified by the architect.”

Soon after the contract was executed, the work was commenced, the plaintiff Carrington having, by transfer from Duell, with consent of defendant, become owner of a one-half interest. The rear of [530]*530the lot was low ground, and in the specifications there was the following clause:

“The ground being soft where rear of building is located, it will be necessary to dig a trench four feet deep and six feet wide, and fill with concrete two feet deep, composed of broken stone and the proper proportions of Howe’s cave cement, and as directed by architect. The water in the cave will have to be drawn back and kept pumped out until the foundation is complete. Concrete foundation to be extended 40 feet on either side of building, if considered necessary by architect.”

It was soon found that the character of the ground where the rear wall was to be located was such that the concrete foundation specified in the specifications would not answer the purpose. The plaintiffs so informed the defendant, who replied that they must consult the architect about any changes in the foundation. Thereupon the architect, at the expense of the defendant, caused rows of spiles to be driven as a basis for the rear foundation wall, and upon these the plaintiffs, by direction of the architect, built the wall; and it was agreed between the plaintiffs and the architect, acting for the defendant, that the sum of $65 should be' allowed by the plaintiffs to the defendant out of the contract price for the concrete not used tunder the rear wall, as called for by the specifications. The work proceeded, and on or before January 26, 1891, the foundation walls were completed, and soon thereafter they were inspected, measured, and accepted by the architect; and on the 27th March, 1891, he issued his certificate No. 1, stating that $500 was due the plaintiffs. This amount included the first payment of $400 on the contract, and the delay in issuing the > certificate was occasioned by the filing of a lien by the mason who constructed the walls. On this certificate the defendant paid $485. On the 21st February, T891, the architect issued his certificate No. 2, for $500; on March 1, 1891, his certificate No. 3, for $1,000; and on March 24, 1891, his certificate No. 4, for $1,000. And the defendant paid the plaintiffs the full amount of these certificates. After the issuing of these certificates, a dispute arose between defendant and one Lee over the materials furnished by him for the plastering in the building, and the architect issued no certificate for the payment due when the plastering was completed, and has never issued any further certificates. It is not claimed that the plaintiffs are responsible for the contest with Lee. The defendant afterwards, without a certificate from the architect, paid the plaintiffs, on the 18th April, 1891, the sum of $500; on April 30th, $1,000; on May 10th, $245; on May 13th, $125; and on May 23d, $600. These payments amounted to $5,455. Adding thereto the amount of the claim of Lee, $579.35, which the defendant assumed, also the sum of $65, allowed, as hereinbefore stated, on account of not using concrete, and the sum of $105, agreed to be deducted from the contract price on account of changes made soon after the execution of the contract, there remained of the contract price the sum of $945.65. The building was not completed by April 1st, but the delay, as the referee properly finds, is not chargeable to plaintiffs, as it was mainly occasioned by the change in the basis of the foundation wall. The main controversy at the trial was in relation to [531]*531the settling oí the rear, side, and center walls, its cause, and the consequent injury to the building, and also over the question of acceptance.

There is no doubt that the walls settled to some extent, but the evidence is conflicting as to how much, and also as to the effect. The defendant claimed that the settling was mainly due to the improper foundation of the side and center walls, and the failure to bind the center to the rear wall; while the claim of the plaintiffs was that the settling was attributable to the manner in which the piling was placed by the defendant under the rear wall, and the failure to place it to some extent under the other walls. The main defect claimed to exist in the foundation of the side and center walls was the failure to lay a concrete basis. This was not required by the architect, and the defendant suggests that he had no discretion to dispense with it under the terms of the specification on that subject above quoted. We are, however, inclined to think that he had. That was his interpretation of the provision, and under the contract, in case of doubt in the construction or meaning of the drawing or specifications, he was the arbiter. He accepted the walls knowing the concrete was not there.

It is also claimed that the base course under the side and center walls does not conform to the specifications. It is, however, in effect, found that they were constructed under the direction of the architect, and that when he gave the certificate ¡No. 1, which covered the first payment, he knew that the base course was not in all respects such as was called for by the plans and specifications, and. he knew the general character, size, and quality of the base courses complained of. The defendant claims that, in regard to these base courses and their foundation, the plaintiffs were guilty of concealment and fraud; but the referee declines to so find, and this finding should not, we think, be disturbed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vacuum Cleaner Co. v. Broadway Cortlandt Co.
78 Misc. 174 (Appellate Terms of the Supreme Court of New York, 1912)
Tilden v. Buffalo Office Building Co.
27 A.D. 510 (Appellate Division of the Supreme Court of New York, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
33 N.Y.S. 528, 86 Hun 331, 93 N.Y. Sup. Ct. 331, 67 N.Y. St. Rep. 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duell-v-mccraw-nysupct-1895.