Tilden v. Buffalo Office Building Co.

27 A.D. 510
Appellate Division of the Supreme Court of the State of New York·Decided July 1, 1898·Published·Cited by 3 cases

Opinion

Adams, J.:

On the 26th of April, 1893, the plaintiff, who is a contractor, entered into , a written contract with one John H. Smith to erect a . large office building in the city of Buffalo. By the terms of this contract the building was to be completed by the 10th day of April, 1894, and the price to be paid therefor was $124,000.

In the month of August following the execution of the contract the defendant was duly substituted as a party thereto in the place of Smith, who was at that time the defendant’s president, and this action is brought to recover a balance of $3,117.45, which it is . claimed is due the plaintiff upon the contract, and for extra work done and materials furnished by him, after deducting the sum of $371.27 for work and materials embraced in the contract which were' omitted by direction of the defendant.

The plaintiff’s demand consists of seven items, the first of which is for a balance of $1,700, claimed to be due upon the contract proper, and the remainder are for “ extra:- work.” W ith the exception [512] of the item of $459.25 for “extra work and materials, concrete in, quicksand pockets,” the correctness of the plaintiff’s claim was not disputed upon the trial, but it was, nevertheless, asserted by the defendant that it was under no legal liability to pay the same for the reason that, at the'time'this action was commenced, the plaintiff had omitted to furnish the certificate of the architects which was-required by the contract as a condition precedent to final payment, and for the further reason that the item of $459.25, above mentionedj was for work and materials which were, properly embraced in, and contemplated by, the contract. It was further contended that the plaintiff had failed to comply with the requirements of the contract in regard to the quality of pine used for flooring, in consequence of which the defendant claimed to have suffered damage in the sum of $1,000, and this amount was set up in its answer by way of counterclaim to the plaintiff’s demand.

The record in the case brings up for review several questions pertaining to these various defenses which arose during the progress of, the trial, and in the decision of which it is alleged error was committed by the learned trial court which was prejudicial to the defendant’s interest. To the consideration of these questions we will now direct our attention.

So far as the defense relied upon by way of counterclaim, is concerned, but little need be'said. The contract and specifications provided that:

The finished wood floors of the entire building are to be of clear Georgia or Southern pine, thoroughly seasoned and kiln dried,matched and laid closely, and blind nailed to place. This flooring must be l-g-" thick, and the face not over 8" wide.
, This flooring must be of the very best selection, every board quarter-sawed, sometimes called riff-sawed,’ and, unless it is perfectly well matched so that it lays thoroughly even and smooth, it must be hand planed - after being laid.”

The evidence on the part of the defendant tended to show that the material used in the floors was of an inferior quality to that above specified, in that it was what is termed “ sappy,” and that, in consequence of this defect, it very soon changed color and looked dark and dingy. - '

It was, however, made to appear upon the trial that there are sev[513] eral grades of “Georgia or southern pine;” that the only grade which does not contain any sap is what is termed “heart-face” lumber, which is never used unless specifically mentioned, in the contract ; that the next grade, which is termed “ first and second clear,” contains ten per cent of sap, and a number of witnesses called by the plaintiff testified that the term “ clear Georgia or southern pine ” meant this grade, and that this was the grade used by the plaintiff in fulfilling his contract.

It was further contended by the plaintiff that the change in the color of the flooring was due to the fact that it had been improperly treated by the defendant after ■•it was laid, and some evidence was given tending to sustain this contention.

It is very apparent, therefore, that as respects this particular feature of the case an issue of fact was raised, and as this issue was submitted to the jury in a charge which was exceedingly fair, it must be deemed settled, by the verdict.

The defendant’s contention in respect of the claim for extra work in the “ quicksand pockets ” is subject to very much the same stricture. It seems that the original specifications provided that:

“ If any pockets of quicksand are found this contractor shall excavate the same and then fill in solidly with cement concrete and broken stone.”

This provision was objected to by the "plaintiff before bidding for the work, and the architects thereupon assured Mm that it was a mistake which would be corrected and that he might bid upon the assumption that he would not have to" fill the quicksand pockets over one cubic yard in size without extra compensation. Subsequently the specifications were corrected so as to read:

“ If any pockets of quicksand are found not larger than one cubic yard, this contractor shall excavate the same, and then fill in solidly with cement concrete and broken stone.”

The defendant claimed that this alteration, was unauthorized and was made by the architects without its knowledge and consent, but Mr. Smith testified that at the time the contract. was signed it was understood that the architects were to prepare new specifications to conform to several changes which had been agreed upon, and it is conceded that a copy of the specifications as so amended and which [514] contained the alteration respecting the sand pockets was thereafter delivered to each of the parties, and that the one delivered to Smith was retained by him during the progress of the work, although he claims that he did not discover this particular' change or .hear anything in regard to it until the plaintiff presented his claim for extra work. .

On the other hand, however, the-plaintiff and his assistant, Mr. Flynn, both testified that Smith was present at the office of the architects when the subject was discussed and that it was then stated by Mr. Green, one of the •architects, that the new specifications should be changed so as to conform to the assurance which had theretofore been given to .the plaintiff.

Upon the trial it was contended by the plaintiff’s counsel that the -architects were authorized, as matter of law, to make this change, -but the court expressly instructed the jury that such was not the ■case, and that so far as this item was concerned the plaintiff could not recover, unless they were satisfied from the evidence that Smith knew, and assented to, the change in the specifications at or before the time when the contract was actually signed. . As has been indicated, the evidence upon this branch of the case was quite conflicting, and this being so, no - sufficient reason is presénted for interfering with .the verdict, which in effect finds that the alteration was made with the knowledge and acquiescence of the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Tilden v. Buffalo Office Building Co., 27 A.D. 510 (N.Y. Ct. App. 1898).

27 A.D. 510 (Tilden v. Buffalo Office Building Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Collins v. Ramish
188 P. 550 (California Supreme Court, 1920)
Vacuum Cleaner Co. v. Broadway Cortlandt Co.
78 Misc. 174 (Appellate Terms of the Supreme Court of New York, 1912)
Bell v. Fox
129 A.D. 405 (Appellate Division of the Supreme Court of New York, 1908)