Tilden v. Buffalo Office-Building Co.

50 N.Y.S. 511
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 26, 1898
StatusPublished
Cited by2 cases

This text of 50 N.Y.S. 511 (Tilden v. Buffalo Office-Building Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tilden v. Buffalo Office-Building Co., 50 N.Y.S. 511 (N.Y. Ct. App. 1898).

Opinion

ADAMS, J.

On the 26th of April, 1893, the plaintiff, who is a contractor, entered into a written contract with one John H. Smith to erect a large office building in the city of Buffalo. By the terms of this contract the building was to be completed by the 10th day of April, 1894, and the price to be paid therefor was $124,000. In the month of August following the execution of the contract the defendant was duly substituted as a party thereto in the place of Smith, who was at that time the defendant’s president, and this action is brought to recover a balance of $3,117.45, which it is claimed is due the plaintiff upon the contract, and for extra work done and materials furnished by him, after deducting the sum of $371.27 for work and materials embraced in the contract which were omitted by direction of the defendant. The plaintiff’s demand consists of seven items, the first of which is for a balance of $1,700, claimed to be due upon the contract proper, and the remainder are for “extras.” With the exception of the item of $459.25 for “extra work and materials, concrete in quicksand pockets,” the correctness of the plaintiff’s claim was not disputed upon the trial; but it was nevertheless asserted by the defendant that it was under no legal liability to pay the same, for the reason that at the time this action was commenced the plaintiff had omitted to furnish the certificate of the architects which was required by the contract as a condition precedent to final payment, and for the further reason that the item of $459.25 above mentioned was for work and materials which were properly embraced in and contemplated by the contract. It [512]*512was further contended that the plaintiff had failed to comply with the requirements of the contract in regard to the quality of pine used for flooring, in consequence of which the defendant claimed- to have suffered damage in the sum of $1,000, and this amount was set up in its answer by way of counterclaim to the plaintiff’s demand. The record in the case brings up for review several questions pertaining to these various defenses which arose during the progress of the trial, and in the decision of which it is alleged error was committed by the learned trial court which was prejudicial-to the defendant’s interest. To. the consideration of these questions we will now proceed to direct our attention. -

So far as the defense relied upon by way of counterclaim is concerned, but little need be said. The contract and specifications provided that:

“The finished wood floors of the entire building are to be of clear Georgia or Southern pine, thoroughly seasoned and kiln-dried, matched and laid closely, and blind-nailed to place. This flooring must be 1%" thick, and the face not over 3" wide. This flooring must be of the very best selection, every board quarter-sawed,. sometimes called ‘riff-sawed’; and unless it is perfectly well, matched, so that it lays thoroughly even and smooth, it must be hand-planed .after being laid.”

The evidence on the part of the defendant tended to show that the material used in the floors was of an inferior quality to that above specified, in that it was what is termed “sappy,” and that, in consequence of this defect, it very soon changed color, and looked dark and dingy. It was, however, made to appear upon the trial that there are several grades of Georgia or Southern pine; that the only grade which does not contain any sap is what is termed “heart-face” lumber, which is never used unless specifically mentioned in the contract; that the next grade, which is termed “first and second clear pine,” contains 10 per cent, of sap; and a number of witnesses called by the plaintiff testified that the term “clear Georgia or Southern pine” meant this grade, and that this was the grade used by the plaintiff in fulfilling his contract. It was further contended by the olaintiff that the change in the color of the flooring was due to .the fact that it had been improperly treated by the defendant after it was laid, and some evidence was given tending to sustain this contention. It is very apparent, therefore, that, as respects this particular feature of the case, an issue of fact was raised, and, as this issue was submitted to the jury in a charge which was exceedingly fair, it must be deemed settled by the verdict.

The defendant’s contention in respect of the claim for extra work in the “quicksand pockets” is subject to very much the same ■stricture.' It séems that the original specifications provided that, •“if any pockets of quicksand are found, this contractor shall excavate the same, and then fill in solidly with cement, concrete, and broken stone.” This provision was objected to by the plaintiff before bidding for the work, and the architects thereupon assured him that it was a mistake which would be corrected, and that he might bid upon the assumption that he would not have to fill the quicksand pockets over one cubic yard in size without extra compensation. Subsequently the specifications were corrected so as to read: “If any pockets of [513]*513quicksand are found not larger than one cubic yard, this contractor shall excavate the same, and then fill in solidly with cement, concrete, and broken stone.” The defendant claimed that this alteration was unauthorized, and was made by the architects without its knowledge of consent; but Mr. Smith testified that at the time the contract was signed it was understood that the architects were to preparemew specifications to conform to several changes which had been agreed upon; and it is conceded that a copy of the specifications as so amended, and which contained the alteration respecting the sand pockets, was thereafter delivered to each of the parties, and that the one delivered to Smith was retained by him during the progress of the work, although he claims that he did not discover this particular change, or hear anything in regard to it, until the plaintiff presented his claim for extra work. On the other hand, however, the plaintiff and his assistant, Mr. Flynn, both testified that Smith was present at the office of the architects when the subject was discussed, and that it was then .stated by Mr. Green, one of the architects, that the new specifications should be changed so as to conform to the assurance which had theretofore been given to the plaintiff. Upon the trial it was contended by the plaintiff’s counsel that the architects were authorized, as matter of law, to make this change, but the court expressly instructed the jury that such was not the case, and that, so far as this item was concerned, the plaintiff could not recover, unless they were satisfied from the evidence that Smith knew, and assented to, the change in the specifications at or before the time when the contract was actually signed. As has been indicated, the evidence upon this branch of the case was quite conflicting, and, this being so, no sufficient reason is presented for interfering with the verdict, which, in effect, finds that the alteration was made with the knowledge and acquiescence of the defendant.

We come, therefore, to a consideration of what may doubtless be regarded as the paramount question in the case. At the time the plaintiff presented his claim, and demanded payment thereof, the structure had been completed, and was in the possession of the defendant. This fact makes it perfectly obvious that the amount claimed was in full satisfaction of all moneys which the plaintiff would-be entitled to receive under his contract. In short, it was the “final payment” which the plaintiff was demanding, and both he and the defendant so understood it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCandless v. Furlaud
296 U.S. 140 (Supreme Court, 1935)
Collins v. Ramish
188 P. 550 (California Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
50 N.Y.S. 511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tilden-v-buffalo-office-building-co-nyappdiv-1898.