Anderson v. Meislahn

12 Daly 149
CourtNew York Court of Common Pleas
DecidedJune 25, 1883
StatusPublished
Cited by7 cases

This text of 12 Daly 149 (Anderson v. Meislahn) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson v. Meislahn, 12 Daly 149 (N.Y. Super. Ct. 1883).

Opinion

Charles P. Daly, Chief Justice.

In the testimony, which is voluminous, there is considerable contradiction upon many points, such as the extent, nature and value of omissions and changes, the circumstances under which they occurred, the statement of the architect as to the reasons why he refused to give the last certificate, and other matters, in respect to all of which it must be assumed that the referee believed the plaintiff’s witnesses and discredited those of the defendant, where they were in conflict. The conclusions of the referee as to the facts where the testimony is thus conflicting will have to be taken as correct. We have the right to review a referee’s findings upon questions of fact where he has found on conflicting evidence; but we do so only in extreme cases, where it is clearly manifest to the appellate court that he was wrong; and this is not one of those cases. He saw the witnesses, heard them testify, and, by consent of the parties, inspected every part of the building in respect to which evidence had been given. He had, therefore, advantages in passing upon disputed questions of fact which an appellate court cannot have.

A material circumstance in this case is that by the contract the plaintiff was to erect the buildings in conformity with the drawings and specifications made by Morell, the architect, “in a good, workmanlike and substantial manner, to the satisfaction and under the direction of the architect,” to be authenticated by a certificate in writing. The work was to be paid for in nine payments, in certain stages, as it progressed; and it was further provided that “ in each of the said cases ” or stages of the work, when the payments [152]*152became due and payable, a certificate was to bé obtainéd, signed by the architect. Eight of those certificates were given, in which the. architect certified in writing that the plaintiff was entitled to the payment, which must be regarded as certifying that the work, up to the time of each of these payments, had been done agreeably to the drawings and specifications, in a workmanlike and substantial manner, under the direction and to the satisfaction of the architect. The parties having selected their own umpire, who was to ascertain and determine whether the contract had in these respects been complied with, his certificate should be re? garded as conclusive and binding upon the defendant, unless the defendant could show it was obtained by fraud or mistake, or it appeared that the contract had not as a whole been substantially complied with. See Wyekoff v. Myers, affirming judgment of this court (44 N. Y. 145) ; Butler v. Tucker (24 Wend. 449), in which it is said that “ when parties fix on an umpire and agree to abide by his decision, neither of them, without the consent of the other, can withdraw the question of performance from the common arbiter;” Smith v. Brady (17 N. Y. 175, 176); Grlacius v. Black (50 N. Y. 151).

Unless something, such as above stated appears, the certifi-. cate is conclusive, and the inquiry as to non-performance is limited to what was required to be done to entitle the plaintiff to the last payment, the architect having refused to give a certificate to entitle the plaintiff to receive that payment;

The architect testifies that a list was kept by the defendant and himself of the omissions, &c., the main portion by the defendant. He says: “ All along, during the progress of the work, we had an express understanding that that should be done; and when the defendant objected to certain things, my answer was that ‘ everything may be adjusted at. the last under the clause in the contract of omissions and deviations, and I think you will have no difficulty in doing it,’ or something to that effect; ‘ we will keep a list as the work goes on; ’” and that the defendant did so; and that he, the architect, also kept a list as to some things.

[153]*153It does not appear that the plaintiff was a party to this understanding; and there is no such clause in the contract. The contract simply provides that, “ should the owner, at any time, during the progress of the building, request any alteration, deviation, additions or omissions from the contract, he shall be at liberty to do so; and the same shall in no way affect or make void the contract, but will be added to or deducted from the amount of the contract, as the case may be, by a fair and reasonable valuation.” This clause relates only to omissions or deviations requested by the defendant; and there is nothing in it authorizing the defendant and the architect to keep a list of omissions and deviations and have them adjusted, as he says, at last under this clause of the contract.' That he did not in fact so understand it, or that any such right existed, is evident from, his statement that he told the plaintiff (which the plaintiff denied) or his lawyer when the final certificate was applied for, that he “ would give a conditional certificate, giving himself and the defendant the right to go back to these omissions.” Instead of keeping a list of these alleged deviations or omissions, as the work went- on, it was the plain duty of the architect, before a payment was to be made and the certificate given, to see that the work so far had been done in accordance with the contract, and to refuse to give the certificate at that stage if there were omissions or deviations unauthorized by the contract, and in good faith to make known tó the plaintiff the nature of the objections, that he might then supply the omissions or correct the deviations before further progress was made in the building, when it might be impossible to do so. The architect himself testified that, in an interview with the plaintiff, at which he refused to give the certificate for the last payment, he had not, prior to that time, informed the plaintiff of all the particulars in which the plaintiff had not performed his contract; that there was then no other way than to arrange differences, the remedying of defects being then out of the question; and that all he and the defendant wanted was a fair allowance in consideration of the [154]*154changes and substitutions. The architect testified that prior to the interview with Christian, which was when the last certificate was demanded, he called the plaintiff’s attention to the certain matters or points, as he called them, of non-compliance with the contract, which he enumerated in detail. He does not say at what period, prior to that interview, he so informed the plaintiff; and the plaintiff denies this statement. He says, “ Morell did not so inform me on these points.” So we must assume, on the referee’s findings of fact, that, up to the time when the last certificate was demanded, the plaintiff’s attention had not been called by the architect to the deviations.and omissions enumerated in his testimony. He does say, however, that three months before the interview with Christian he called the plaintiff’s attention to a broken beam, which was mended by nailing a piece of board on one side of it; that he told him that it was not workmanlike to patch up the beam; that a new beam should have been put in. But the plaintiff’s witness, Hagen, testifies that the architect called his attention to this split or broken beam, and that he told him to put two planks on the side, which he did; so that this patching of the beam which he testified to as unworkmanlike, was done, according to this evidence, by his direction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lackland v. Edwin
165 S.W. 314 (Supreme Court of Missouri, 1914)
Duell v. McCraw
33 N.Y.S. 528 (New York Supreme Court, 1895)
Snaith v. Smith
27 N.Y.S. 379 (New York Court of Common Pleas, 1894)
Pucci v. Barney
21 N.Y.S. 1099 (New York Court of Common Pleas, 1893)
Jackson Architectural Iron-Works v. Rouss
15 N.Y.S. 137 (Superior Court of New York, 1891)
Jackson Architectural Iron Works v. Rouss
27 Jones & S. 512 (The Superior Court of New York City, 1891)
Laserowitsch v. Reiman
6 N.Y. St. Rep. 246 (New York Court of Common Pleas, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
12 Daly 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-v-meislahn-nyctcompl-1883.