Lackland v. Edwin

165 S.W. 314, 256 Mo. 133, 1914 Mo. LEXIS 401
CourtSupreme Court of Missouri
DecidedMarch 24, 1914
StatusPublished
Cited by19 cases

This text of 165 S.W. 314 (Lackland v. Edwin) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lackland v. Edwin, 165 S.W. 314, 256 Mo. 133, 1914 Mo. LEXIS 401 (Mo. 1914).

Opinion

BLAIR, C.

— This controversy arises upon a surety bond given to secure plaintiffs against loss by reason of any failure of the defendant contractors to perform their contract to erect a building in St. Louis. The trial court gave judgment for the defendant surety company. The questions presented relate solely to the efficacy of certain facts to release the surety from its obligation. Respondent company is in the business of acting as surety, charging a premium therefor. It had received compensation for becoming surety on the bond in suit.

The defenses and findings upon which the surety was released below will be examined in order. They must be vieAved in the light of some applicable general principles.

[140]*140By the general law of suretyship, evolved at a time when sureties were all of the class whose obligations were entered into from motives of friendship and without pecuniary considerations moving to them, any change in the contract releases the surety, unless made with his consent.

Sureties for Profit. “But the rule of strictissimi juris is a stringent one, and is liable at times to work a practical injustice. It is one which ought not to be extended to contracts not within the reason .of the rule, particularly when the bond is underwritten by a corporation which has undertaken for a profit to insure the obligee against a failure of performance on the part of the principal obligor.” [Hill v. American Surety Co., 200 U. S. l. c. 202.]

“The doctrine that a surety is a favorite of the law, and that a claim against bim is strictissimi juris, does not apply where the bond or undertaking is executed upon a consideration by a corporation organized to make such bonds or undertakings for profit. While such corporations may call themselves ‘surety companies,’ their business is in all essential particulars that of insurers. Their contracts are usually in the terms prescribed by themselves, and should be construed most strongly in favor of the obligee. ’ ’ [32 Cye. 306.]

contract-Alterations, So far the decisions are in practical accord though there is a wide divergence of opinion as to the effect and application of these principles. In this case one ground upon which the surety was held released was that changes had been made in the plans without the surety’s consent.

The contract provided: “Should any alteration be required in the work shown or described by the drawings or specifications, a fair and reasonable valuation of the work added or omitted shall be made by the architects, and the sum herein agreed to be paid [141]*141for the work according to the original specification shall be increased or diminished as the case may be. In case such valuation is not agreed to, the contractors shall proceed with the alteration upon the written order of the architects, and the valuation of the work added or omitted shall be referred to three arbitrators” selected in a prescribed manner.

The referee’s finding on this phase of the case is that alterations in the work were made from time to time but that the architects did not pass upon these changes and determine, before each was made, the sum to be added or deducted on account of it; that the changes were not made upon the written order of the architects, nor was arbitration asked by the contractors. He finds that in July, after the building was nearing completion, the contractors and the representative of plaintiffs and local superintendent for the architects, went over the building and made a list of changes; having made the list, the parties, agreed upon the sums to be added and subtracted. The list of changes and agreed allowances were put in writing and signed by the parties and approved and signed by the architects. The net result was the enhancement of the contract price by $391 and the payment of that additional sum to the contractors. The referee concludes his finding on this branch of the case thus: “So far as. the allowances made in this exhibit to the defendants Renshaw, for changes and alterations, are concerned, the referee believes and finds they were fair and reasonable and not in excess of their true value; but as already suggested, they were not agreed upon in the manner provided for in the contract. ’ ’

On his view, the departures from the contract made were (1) the failure of the architects to fix the increase or decrease of the contract price before the change was made; (2) that the changes were not made upon the written order of the architect; and (3) that arbitration was not requested by the contractors.

[142]*142By the quoted clause of the contract, the parties had the right to alter the plans, and á fair and reasonable increase or decrease in the contract price was to follow any such alteration. The architects were to determine what increase or decrease was fair and reasonable in each case. That was, the extent of the surety’s interest. That was, done in this case. The contract does not specifically provide that the architects shall make their estimate in advance of the doing of the work under the changed specifications. Such a construction of the first sentence of this paragraph of the contract is merely an inference from the following sentence, the real function of which., however, is to provide a method whereby the contractors can be compelled to proceed in case of a disagreement.

In view of the principles above announced, it appears the learned referee applied too strict a rule on this branch of the case. The surety lost nothing, its risk of loss was in no way increased and, in fact, in the end it received the exact protection to which the contract entitled it.

In Chapman v. Eneberg, 95 Mo. App. 127, there was an express provision in the contract to the effect that “no work of any description is to be considered as extra work unless the same shall have been understood and agreed upon in writing before such work is commenced.” That case is, therefore, unlike the one at bar. The contract provision and the facts in Furniture Co. v. Toll, 133 Mo. App. l. c. 407, resemble closely those in this case, and the decision therein is in full accord with the conclusions reached above.

Payment ¡n' Architects’18' orders. Another ground upon which the referee held the surety released was that plaintiffs had disregarded the contract provisions as to the payment of installments of the contract price.

The contract price was $26,838 and was to be paid in twelve installments, each falling due when the work [143]*143reached a designated stage, it being also provided, ‘ ‘ that the final payment shall be made within ten days after this contract is completely finished; provided, that in such of the said cases the architects shall certify in writing that all the work upon the performance of which the payment is to become, due has been done to their satisfaction.”

In this connection the referee finds that the certificates or orders given by the architects were in the following form:

“No. 1. Office of J. B. Legg, Architect.
St. Louis, December 29, 1902.
Missouri Botanical Garden:
Pay to the order of Renshaw & Son one thousand and five hundred ($1500) x-100 dollars, on account of their contract for building your Eddy factory building-, S. W. Corner Market and Main streets. $1500.00.
J. B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BAYER & MINGOLLA CONSTRUCTION CO. INC. v. Deschenes
205 N.E.2d 208 (Massachusetts Supreme Judicial Court, 1965)
County of Audrain Ex Rel. First National Bank of Mexico v. Walker
155 S.W.2d 251 (Missouri Court of Appeals, 1941)
State Ex Rel. Union Indemnity Co. v. Shain
66 S.W.2d 102 (Supreme Court of Missouri, 1933)
Shaw v. New Amsterdam Casualty Co.
164 A. 916 (Supreme Court of Pennsylvania, 1932)
Southern Surety Co. v. MacMillan Co.
58 F.2d 541 (Tenth Circuit, 1932)
Noonan v. Independence Indemnity Co.
41 S.W.2d 162 (Supreme Court of Missouri, 1931)
School Dist. Eddystone v. Lewis
101 Pa. Super. 583 (Superior Court of Pennsylvania, 1930)
Union State Bank v. American Surety Co.
23 S.W.2d 1038 (Supreme Court of Missouri, 1930)
North Texas Nat. Bank v. Thompson
23 S.W.2d 494 (Court of Appeals of Texas, 1929)
Fuqua v. Tulsa Masonic Bldg. Ass'n
1928 OK 71 (Supreme Court of Oklahoma, 1928)
Community Bldg. Co. v. Maryland Casualty Co.
8 F.2d 678 (Ninth Circuit, 1925)
Kansas City Ex Rel. Ingalls Stone Co. v. New Amsterdam Casualty Co.
269 S.W. 693 (Missouri Court of Appeals, 1925)
Johannes v. St. Regis Realty & Investment Co.
188 S.W. 1138 (Missouri Court of Appeals, 1916)
Commercial Bank v. American Bonding Co.
187 S.W. 99 (Missouri Court of Appeals, 1916)
Barton v. Title Guaranty & Surety Co.
183 S.W. 694 (Missouri Court of Appeals, 1916)
Joblin v. Illinois Surety Co.
182 S.W. 143 (Missouri Court of Appeals, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
165 S.W. 314, 256 Mo. 133, 1914 Mo. LEXIS 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lackland-v-edwin-mo-1914.