National Surety Co. v. Long

125 F. 887, 60 C.C.A. 623, 1903 U.S. App. LEXIS 4226
CourtCourt of Appeals for the Eighth Circuit
DecidedNovember 23, 1903
DocketNo. 1,883
StatusPublished
Cited by55 cases

This text of 125 F. 887 (National Surety Co. v. Long) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Long, 125 F. 887, 60 C.C.A. 623, 1903 U.S. App. LEXIS 4226 (8th Cir. 1903).

Opinion

SANBORN, Circuit Judge,

after stating the case as above, delivered the opinion of the court.

One of the defenses of the surety company, and the only one that it will be necessary to notice in this court, was that the plaintiff below failed to comply with the third and fourth paragraphs of the bond, which by its terms constituted conditions precedent to the liability of the defendant. In so far as these paragraphs are material in this case, they read in this way:

“If, at any time, the above-named principal shall, in any manner, fail, neglect or refuse to keep, do or perform, any matter or thing at the time and in the manner in said contract set forth and specified to be by said principal kept, done or performed, the obligee shall immediately so notify the company in writing, by registered letter, prepaid, addressed to the company, at its principal offices in the Oity of New York.”
“If, at any time, it appears that the above-named principal has abandoned the work, or will not be able, or does not intend, to carry out or perform the contract, the obligee shall immediately so notify the company in writing, by registered letter, prepaid, addressed to the Company, at its principal offices in the City of New York, and the company shall have the right at its option, to assume such contract and to sublet or complete the same, and, if it so elect, all moneys due, or to become due thereafter, under said contract, including percentages agreed to be withheld until completion, shall, as the same shall become due and payable under the terms of said contract, be paid to the company, regardless of any assignment or transfer thereof by the principal.”

The contract contained this stipulation:

“The said party of the second part agrees to complete said building by the first day of September, 1901, and the said party of the second part further agrees that in case he fails to complete said building by the fifteenth day of September, 1901, shall pay to the said party of the first part, as liquidated damages, the sum of five dollars for each and every day or part of a day that said building remains incompleted after the said time, that sum being the actual loss occurring to the said party of the first part by said delay.”

The uncontradicted evidence was that on September i, 1901, the plaintiff knew that the contractor, Humphreys, would not be able to, and that he had already failed to, perform his contract in the time and manner specified therein. He knew that the building then lacked roof, doors, windows, plastering, and floors. Nevertheless he never notified the surety company of any of these facts until September 12, 1901, three days after Humphreys had abandoned his contract and absconded.

In one of the paragraphs of the bond, which precedes the conditions that have been quoted, this stipulation is found:

“This bond is executed by tbe company as surety on condition that its liability shall be limited by, and subject to, the conditions and provisions here[889]*889inafter contained, which shall be conditions precedent to the right of the obligee to recover hereunder, anything in said contract to the contrary notwithstanding.”

Moreover, the eleventh paragraph of the bond reads:

“The failure, neglect or refusal of the obligee to keep, strictly observe, and fully perform, any matter or thing in this bond or in said contract stipulated and agreed to be done, kept or performed by the obligee, at the time and in the manner specified, shall relieve the company from all liability under this bond.”

In this state of the case, the circuit court refused to instruct the jury to return a verdict for the defendant, and charged them that the time fixed by the contract for the completion of the building was September 15, 1901; that, if the plaintiff gave the notice of the inability or failure of the contractor to perform his contract to the surety company in such time as a man of ordinary prudence would have given it under similar circumstances, they might return a verdict in his favor, but that, if he was guilty of negligence in this matter, their verdict should be for the defendant. The surety company ^excepted to these rulings, and it has assigned them as error.

The care or negligence with which an obligor, who fails, seeks to perform his contract, is no defense to an action for damages for his failure. The only test of the right to recover in such an action is the existence of the breach of the covenant. It is no answer to an action for a failure to pay a promissory note that the maker, although he paid no part of it, exercised all the care to pay it that a person of ordinary prudence in similar circumstances would have used. It is no defense to an action for the breach of a contract that, although the obligor failed to perform it, yet he exercised ordinary care to do so. The very purpose of a promise or of a covenant is to relieve the obligee of all inquiry relative to the care or negligence with which the obligor acts in its fulfillment, and to impose upon the latter the absolute obligation to perform it. Nothing less than full performance satisfies the undertaking. The obligation of a promise or of a covenant to pay a debt or to do an act is not to use ordinary care to comply with the terms of the agreement, but it is to perform it; and, in an action for its breach, it is not material what care the obligor used, or what negligence he was guilty of, in his endeavor to fulfill it. The only question is, did he perform his contract? Guarantee Co. v. Mechanics’, etc., Co., 183 U. S. 402, 421, 422, 22 Sup. Ct. 124, 46 L. Ed. 253. The covenant of the plaintiff in the case under consideration was to immediately notify the surety company of any failure or inability of the contractor to construct and complete the building at the time and in the manner specified in the contract, and the question was not whether or not, although he failed to give the notice, he had exercised ordinary care to do so, but whether or not he had actually given the notice immediately upon the appearance of the known inability and failure of the contractor to perform his agreement. The circuit court fell into an error when it instructed the jury that the care or negligence of the plaintiff conditioned his right to recover here.

[890]*890By the stipulation in the contract between Humphreys and the plaintiff which has been set forth above, the contractor agreed “to complete said building by the first day of September, 1901,” and that if he failed to complete it by September 15, 1901,'he would pay to the plaintiff damages to the amount of $5 for every day from that time until the building was finished. The former date was clearly the time fixed for the completion of the performance of the contract, while the latter was the stipulated day from' which the time that measured the liquidated damages which the contractor agreed to pay in case he failed to finish the building by September 15th should commence to run. The two subjects—the time for the completion of the building, and the day from which the time that measured the liquidated damages should be reckoned—were distinct and separate. There was no rule of right or of law that required these times to fall upon the same day. The parties had the undoubted right to agree upon what date each should fall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BAYER & MINGOLLA CONSTRUCTION CO. INC. v. Deschenes
205 N.E.2d 208 (Massachusetts Supreme Judicial Court, 1965)
T. W. Warner Co. v. Andrews
94 F.2d 13 (Second Circuit, 1938)
MacNear v. Malow
276 N.W. 433 (Michigan Supreme Court, 1937)
Shiya v. Erickson
156 Misc. 738 (City of New York Municipal Court, 1935)
Union Indemnity Co. v. Lang
71 F.2d 901 (Ninth Circuit, 1934)
W. K. Mitchell & Co. v. American Credit Indemnity Co.
11 F. Supp. 394 (E.D. Pennsylvania, 1934)
Goben v. Des Moines Asphalt Paving Co.
252 N.W. 262 (Supreme Court of Iowa, 1934)
National Surety Co. v. Mutual Veneer Co.
66 F.2d 88 (Sixth Circuit, 1933)
Prudence Co. v. Fidelity & Deposit Co.
2 F. Supp. 454 (S.D. New York, 1933)
Connecticut Fire Ins. v. Lake Transfer Corp.
60 F.2d 172 (E.D. New York, 1932)
Southern Surety Co. v. MacMillan Co.
58 F.2d 541 (Tenth Circuit, 1932)
Witherspoon v. Choctaw Culvert & Machinery Co.
56 F.2d 984 (Eighth Circuit, 1932)
Odegard v. General Casualty & Surety Co.
44 F.2d 31 (Eighth Circuit, 1930)
Southern Surety Co. v. Slayton
41 F.2d 693 (Sixth Circuit, 1930)
Clements v. Preferred Acc. Ins. Co.
41 F.2d 470 (Eighth Circuit, 1930)
Weicker v. Bromfield
34 F.2d 377 (Tenth Circuit, 1929)
Reynolds v. Detroit Fidelity & Surety Co.
19 F.2d 110 (Sixth Circuit, 1927)
Community Bldg. Co. v. Maryland Casualty Co.
8 F.2d 678 (Ninth Circuit, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
125 F. 887, 60 C.C.A. 623, 1903 U.S. App. LEXIS 4226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-co-v-long-ca8-1903.