BAYER & MINGOLLA CONSTRUCTION CO. INC. v. Deschenes

205 N.E.2d 208, 348 Mass. 594, 1965 Mass. LEXIS 855
CourtMassachusetts Supreme Judicial Court
DecidedMarch 2, 1965
StatusPublished
Cited by21 cases

This text of 205 N.E.2d 208 (BAYER & MINGOLLA CONSTRUCTION CO. INC. v. Deschenes) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BAYER & MINGOLLA CONSTRUCTION CO. INC. v. Deschenes, 205 N.E.2d 208, 348 Mass. 594, 1965 Mass. LEXIS 855 (Mass. 1965).

Opinion

Cutter, J.

The plaintiff (Bayer) was the general contractor on a State highway contract (the prime contract), awarded on a unit price basis. The defendant Desehenes made a subcontract with Bayer to do certain excavation work “in strict compliance with . . . the [pjrime [c]on-tract” which was incorporated by reference in the subcontract. The subcontract unit prices were lower than the prime contract unit prices. Under the subcontract all work was to start not later than November 24, 1958. Desehenes started work on December 1. The work was to be completed on or before March 1,1959, a period of three months plus one week. By June 22,1959, when he quit, Desehenes had completed only about half the work.

The subcontract required Desehenes to “furnish a bond with surety satisfactory to” Bayer in the sum of $91,000, “conditioned that . . . [Desehenes] shall faithfully perform this [sube] ontract and satisfy all claims and demands *596 in connection with the performance of same and shall pay all bills contracted for ... in connection with the work . . . and shall reimburse . . . [Bayer] for all . . . expense which . . . [Bayer] may incur in making good any default of” Deschenes. Deschenes furnished a bond of Aetna Insurance Company (Aetna) for $91,000, which incorporated the subcontract by reference, to indemnify Bayer ‘ ‘ against any loss or damage directly arising by reason of . . . [Deschenes’s] failure . . . faithfully [to] perform . . . [the sub]contract” and to pay claims for labor and materials, “subject ... to the following express conditions [among others] ... (2) That upon receipt of written notice from . . . [Bayer] of [Deschenes’s] default . . . [Aetna] shall have the right within thirty . . . days after the receipt of such notice to remedy the default or to proceed, or procure others to proceed, with the performance of such [subcontract.; that if . . . [Aetna] does proceed or procure others to proceed with the performance of such [sube] ontract . . . all money that may at the time of such default be due, or that thereafter [may] become due to . . . [Deschenes] under said [sube] ontract shall become due and payable to . . . [Aetna] and . . . [Aetna] shall be subrogated to all the rights of . . . [Deschenes].” 1

There were various disputes between Bayer and Des-chenes over quantities and billings. Certain portions of the work were done by Bayer prior to June 22, 1959, for Bayer’s “own convenience and to facilitate other work . . . and Deschenes was either impliedly or expressly relieved from doing this work.” 2 In June, 1959, representatives of Bayer talked with Deschenes, who “told them that he had an opportunity to do another job . . . and was going to *597 leave the Bayer . . . job.” Bayer’s chief engineer said that they were “far behind schedule” and that he “wanted him to stay on the job.” It may easily be inferred that Bayer at all times was interested in getting Deschenes to perform his subcontract, rather than treating him as in default. On June 22,1959, Deschenes removed his last equipment from the job.

Bayer sent to Aetna various progress reports (the first sent on February 2, 1959) showing in each instance a probable completion date later than that set out in the subcontract. The last report indicated a probable completion date of December 1, 1959. When Deschenes left the job site, Bayer proceeded itself to complete the subcontracted work and finished doing so by September 2, 1959. On August 18, 1959, Bayer notified Aetna of Deschenes’s default. Deschenes was adjudicated a bankrupt on November 3, 1960.

As a consequence of these events, Bayer brought this action at law against Deschenes and Aetna for breach of contract and to recover on Aetna’s bond. 3 The facts already stated are based upon the report of an auditor, whose findings were to be final. He found that Bayer is entitled to recover $15,134.95 from Deschenes and Aetna for work that Bayer was required to do because of Deschenes’s breach of the subcontract.

The auditor also found (a) that “any extensions of the completion date ... [of the subcontract were] by mutual *598 agreement of Bayer . . . and Desehenes”; (b) that Aetna “had knowledge that the completion date had been extended”; (c) that Aetna “was not [in] any way damaged by Bayer . . . performing the balance of the work required by the sub-contract” and that Bayer’s delay in giving Aetna notice of Desehenes’s default ‘ ‘ was not injurious to Aetna ’ ’; and (d) that on August 21, 1959, Aetna acknowledged Bayer’s notice to it of Desehenes’s default.

The judge ordered judgments on the auditor’s report for Bayer for $16,848.66 against both Aetna and Desehenes. From these orders Aetna and Desehenes appealed.

1. Aetna contends that it is discharged as surety by the extensions of time for performance given by Bayer to Desehenes, despite Aetna’s knowledge of these extensions, and the absence of any finding of injury to Aetna caused thereby. Aetna, however, “is a compensated surety and is not entitled to invoke the ancient doctrine of strictissimi juris.” Veneto v. McCloskey & Co. 333 Mass. 95,104. See Agoos Leather Cos. Inc. v. American & Foreign Ins. Co. 342 Mass. 603, 608; Maryland Cas. Co. v. Dunlap, 68 F. 2d 289, 291 (1st Cir.). 4

.In the case of an accommodation surety, “where the principal and creditor, without the surety’s consent, make a binding agreement to extend . . . time . . . the surety is discharged unless the creditor in the extension agreement reserves his rights against the surety. ’ ’ Restatement: Security, § 129 (1). See Brockton Sav. Bank v. Shapiro, 311 Mass. 695, 702-704. Cf. Northampton Inst, for Sav. v. Putnam, 313 Mass. 1, 5-6 (burden rests on surety of showing an extension and that it was discharged). The modern rule, however, with respect to a compensated surety, see *599 Restatement: Security, § 129 (2), is that such a surety “is discharged only to the extent that he is harmed by the extension.” See Guaranty Co. v. Pressed Brick Co. 191 U. S. 416, 423-426; American Auto Ins. Co. v. United States, 269 F. 2d 406, 408-409 (1st Cir.); United States v. Bruce Constr. Corp. 272 F. 2d 62, 66 (5th Cir.); Phoenix Assur. Co. v. Buckner, 305 F. 2d 54, 57-58 (8th Cir.). See also Appleman, Insurance Law and Practice, §§ 6796, 6848-6851; annotation, 12 A.L.R. 382. Cf. Stearns, Suretyship (5th ed.) §§ 6.8, 6.16-6.19. Present day authority thus generally rejects, with respect to compensated sureties, the contrary rule stated in Schwartz v. American Sur. Co. 231 Mass. 490, 493-494 (Avhere there was no apparent consideration of the circumstance that the case dealt Avith a compensated surety). Cf.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyle v. Zurich American Insurance Co.
36 N.E.3d 1229 (Massachusetts Supreme Judicial Court, 2015)
Financial Resources Network, Inc. v. Brown & Brown, Inc.
867 F. Supp. 2d 153 (D. Massachusetts, 2012)
Boffoli v. Premier Insurance
880 N.E.2d 826 (Massachusetts Appeals Court, 2008)
C&I Steel, LLC v. Peabody Construction Co.
22 Mass. L. Rptr. 402 (Massachusetts Superior Court, 2007)
Enterprise Capital, Inc. v. San-Gra Corp.
284 F. Supp. 2d 166 (D. Massachusetts, 2003)
John T. Callahan & Sons, Inc. v. Dykeman Electric Co.
266 F. Supp. 2d 208 (D. Massachusetts, 2003)
Cooperative Fire Insurance v. White Caps, Inc.
694 A.2d 34 (Supreme Court of Vermont, 1997)
Carlino v. Aetna Casualty & Surety Co.
1993 Mass. App. Div. 191 (Mass. Dist. Ct., App. Div., 1993)
Chas. T. Main, Inc. v. Fireman's Fund Insurance
551 N.E.2d 28 (Massachusetts Supreme Judicial Court, 1990)
Gebrueder Heidemann, KG v. AMR Corp.
746 P.2d 579 (Idaho Court of Appeals, 1987)
McClure Newspapers, Inc. v. Brown
499 A.2d 765 (Supreme Court of Vermont, 1985)
Net Realty Holding Trust v. Giannini
432 N.E.2d 120 (Massachusetts Appeals Court, 1982)
Blackhawk Heating & Plumbing Co. v. Seaboard Surety Co.
534 F. Supp. 309 (N.D. Illinois, 1982)
Johnson Controls, Inc. v. Bowes
409 N.E.2d 185 (Massachusetts Supreme Judicial Court, 1980)
Industrial Equipment Corp. v. Builders Insurance
108 P.R. Dec. 290 (Supreme Court of Puerto Rico, 1979)
State v. Safeco Insurance Companies
396 N.E.2d 794 (Ohio Court of Appeals, 1978)
City Bank & Trust Co. v. Cooley
56 Mass. App. Dec. 192 (Mass. Dist. Ct., App. Div., 1975)
Town of Hingham v. B. J. Pentabone, Inc.
238 N.E.2d 534 (Massachusetts Supreme Judicial Court, 1968)
Antonelli Construction Co. v. Aetna Casualty & Surety Co.
238 N.E.2d 39 (Massachusetts Supreme Judicial Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
205 N.E.2d 208, 348 Mass. 594, 1965 Mass. LEXIS 855, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bayer-mingolla-construction-co-inc-v-deschenes-mass-1965.