Town of Hingham v. B. J. Pentabone, Inc.

238 N.E.2d 534, 354 Mass. 537, 1968 Mass. LEXIS 852
CourtMassachusetts Supreme Judicial Court
DecidedJune 24, 1968
StatusPublished
Cited by4 cases

This text of 238 N.E.2d 534 (Town of Hingham v. B. J. Pentabone, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Hingham v. B. J. Pentabone, Inc., 238 N.E.2d 534, 354 Mass. 537, 1968 Mass. LEXIS 852 (Mass. 1968).

Opinion

Spalding, J.

This is an action of contract which was tried together with a bill in equity. The law case was referred to an auditor (findings not to be final) who also sat as master in the equity case.

The declaration in the law case contains two counts. Count 1 alleges that the defendant B. J. Pentabone, Inc. (contractor), as principal, and the defendant, New Amsterdam Casualty Company (surety), delivered a performance bond to the town of Hingham, as security for the performance by the contractor of the terms and conditions of a decision of the town board of appeals rendered on August 8, 1958, and amended on February 5, 1959, approving the application of the Toomeys (owners) for permission to remove fill from land owned by them in the town. The town alleges a breach of the bond by the contractor in that it failed to comply with the board’s decision and that it and the surety are liable on the bond.

Count 2 of the declaration alleges that the contractor "entered into a contract, express and implied” with the board on behalf of the town and is against the contractor for an alleged failure to comply with the terms of that contract.

The equity case is a proceeding against the owners and the contractor pursuant to G. L. c. 40A, § 22, inserted by St. 1954, c. 368, § 2, to enforce the zoning by-law of the town. 2 The master filed a report which is in substance identical with his report as auditor.

*539 We summarize the auditor’s findings as follows: In July, 1958, the owners applied to the board in accordance with §§ V and VI-A of the zoning by-law for a permit to remove soil from their property. The board approved the application by a decision dated August 8, 1958. The decision was subject to fourteen conditions, one of which provided for a performance bond to be furnished by the owners and the contractor payable to the town in the sum of ©10,000 “conditioned on the strict compliance by the contractor of all conditions set forth in . : . [the] decision.” Other conditions related to the manner of soil removal and provided for respreading the area with existing loam and topsoil, removal or burial of boulders, and regrading and planting of the area.

Because of errors in the contractor’s original computations, the decision was amended to allow for the removal of a greater amount of fill, and changes were made with respect to the grading of the property. These amendments are set forth in the board’s decision of February 5, 1959. The amended decision required that the condition of the original decision concerning the performance bond be met. The auditor found that “in all other material aspects” the decisions are the same and that “Dfcjhe amendments allowed by the latter decision of the [Tbjoard of [ajppeals were for the benefit of the defendant, B. J. Pentabone, Inc.” The contractor attended the board hearings and had knowledge of the conditions. The plaintiff had given notice that it expected compliance with the decision of the board. Pursuant to a contract between the contractor and the owners for the purchase of fill, some 200,000 yards of fill were removed by the contractor.

The contractor did not comply with several conditions of the amended decision. In particular, the auditor found (1) that engineering data satisfactory to the building commissioner that the conditions of the decision had been met were not furnished; (2) that 50% of the excavated area was improperly graded and required regrading; (3) that all boulders were not buried or removed; (4) that loam was *540 improperly spread on the property; (5) that the land was not left in a uniformly graded condition; (6) that because the area had been improperly covered with topsoil, reseeding was required; and (7) that the spreading of loam or topsoil that did in fact occur took place two to three years after the date set forth in the board’s decision.

The auditor found that the fair cost of complying with the conditions amounted to $26,975 and found for the plaintiff on both counts of the declaration. On count 1 there was a finding against each defendant in the amount of $10,000, to be limited to one recovery. On count 2, he found for the plaintiff in the amount of $26,975, this amount to be reduced by the sum recovered from either defendant on count 1.

The law case was heard by a judge solely on the auditor’s report. The plaintiff moved for judgment on the report and this motion was granted. The contractor presented a motion to strike from the auditor’s report the findings against it on counts 1 and 2, which was denied; it also requested certain rulings, all of which were denied. 3 ****8 The contractor took exception to the allowance of the plaintiffs’ motion for judgment, the denial of its motion to strike, and the denial of its requests.

In the equity case, in which the owners and the contractor were defendants, the master found for the plaintiff against all the defendants. He found specifically that the contractor agreed to comply with the terms of the original decision of the board and requested at a later time that the terms of this decision be amended for its benefit.

After confirmation of the master’s report a final decree was entered granting a mandatory injunction requiring the defendants to comply with the unfulfilled conditions of the *541 board’s decision within three months from the date of the decree. The decree further provided that to the extent the town received satisfaction on any execution issued in the law case, the obligations of the defendants under the decree were to be reduced pro tanto. From this decree the contractor and the owners appealed.

The Law Case.

1. There was no error in the order for judgment against both defendants for $10,000 on count 1 of the law action. The contractor appears to concede that to the extent of the obligation contained in the bond it had entered into a contract with the town and that the bond was security for its undertaking. At all events that is the effect of what was done, for the bond obligates both the contractor and the surety in the amount of $10,000 if the contractor did not comply with the conditions of the town’s permit.

The only challenge to the order for judgment on count 1 comes from the surety; it argues that because of the modification in the town’s permit, without its knowledge or consent, it is discharged. This contention cannot prevail.

The modern rule with respect to a compensated surety is that the surety is “(i) discharged if the modification materially increases his risk, and (ii) not discharged if the risk is not materially increased, but his obligation is reduced to the extent of loss due to the modification.” Restatement: Security, § 128 (b). See New Amsterdam Cas. Co. v. Taylor Constr. Co. 12 F. 2d 972, 975-976 (5th Cir.); Maryland Cas. Co. v. Moore, 82 F. 2d 189 (1st Cir.); Stearns, Suretyship (5th ed.) §§ 6.2, 6.3, 6.8; Simpson, Suretyship, § 29; Williston, Contracts (3d ed.) §§ 1239-1243. The case of Bayer & Mingolla Constr. Co. Inc. v. Deschenes, 348 Mass. 594, approves this approach in the somewhat analogous situation of an extension of time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
238 N.E.2d 534, 354 Mass. 537, 1968 Mass. LEXIS 852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-hingham-v-b-j-pentabone-inc-mass-1968.