Maryland Casualty Co. v. Moore

82 F.2d 189, 1936 U.S. App. LEXIS 2938
CourtCourt of Appeals for the First Circuit
DecidedMarch 6, 1936
DocketNo. 3092
StatusPublished
Cited by7 cases

This text of 82 F.2d 189 (Maryland Casualty Co. v. Moore) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. Moore, 82 F.2d 189, 1936 U.S. App. LEXIS 2938 (1st Cir. 1936).

Opinion

MORTON, Circuit Judge.

This is an appeal by the defendant below from a judgment against it in an action at law upon a bond. We shall refer to the parties, plaintiff and defendant, as they appeared in the trial court. The case was heard jury waived, the only evidence submitted being the report of an auditor to whom it had been referred. The essential facts are as follows:

Pelham Hall, Inc., a Massachusetts corporation, acquired land in Brookline, Mass., and proceeded to erect on it a large apartment house having shops and offices on the street floor. Part of the necessary capital was obtained by an issue of bonds secured by a first mortgage on the property. Arrangements for the issue were made between Pelham Hall, Inc., and the American Bond & Mortgage Company, and the bonds were marketed by the latter company. The agreement covering this phase of the matter is in writing and is referred to as the “brokerage agreement.” The mortgage securing the bonds was made by Pelham Hall, Inc., to the plaintiff, Moore, as trustee for the bondholders. It was an elaborate tri-partite instrument signed by Pelham Hall, by Moore, and by the American Company.

The brokerage agreement required Pelham Hall to give a bond with surety guaranteeing to the American Company, to Moore as trustee, and to the “legal holders” of the bonds the completion of the proposed building. This bond was duly given, the defendant signing it as surety. It is the bond in suit. No question is now made but what Moore as trustee is entitled to bring action upon it. The bond refers to, and incorporates by reference, both the brokerage agreement and the tri-partite mortgage. The condition of it is, basically, that if the principal (Pelham Hall, Inc.) “shall, well and truly erect or cause to be erected the said building,” according to the terms, conditions, and requirements of the agreements referred to, then the obligation shall be void. The bond also contains certain explicit agreements by the surety which will be referred to later.

When the building was approaching completion, the contractor failed and abandoned the work; Pelham Hall, Inc., was unable to take it up and complete it; the defendant was requested to do so and refused; and Moore as mortgagee took possession of the property (as the mortgage gave him an express right to do under such circumstances), and carried the building forward to completion. The cost of doing so was about $306,500. Of this sum, $125,000 came from the proceeds of bonds which had been sold; the remaining $181,-500 was loaned to Moore by the American Bond & Mortgage Company. It is this latter sum with interest which he seeks to recover in the present suit.

The defendant’s first contention, which in the court below was its principal [191]*191contention, is that the building which was bonded was not the building which was built; that after the bond was signed the plans of the building were so radically changed that the surety is released. There is no controversy as to the changes which were made. They consisted, essentially, in enlarging and extending the commercial parts of the building, with a corresponding decrease in the apartments and in the rooms devoted to apartment use. They were confined to the street floor and to the portions of the building adjacent to or used with the shops and offices. The rest of the building was not changed at all; and its size was not changed. The number of apartments was reduced about 5 per cent., and the number of rooms about 10 per cent., and the commercial space was increased accordingly. The auditor found that the changes did not increase the cost of construction. He also found that the changes were substantial, and that the building actually erected could not properly be said to be the same building as that described in the plans and specifications on which the bond was based.

The' District Judge said, “Since the changes did not increase the cost of construction, it is difficult to see how the surety has been in any way prejudiced by these modifications. While the modifications arc of a substantial nature, I regard them as within the scope of the undertaking which the defendant insured. They did not constitute a new contract, imposing additional burdens upon the surety.

“The defendant was a compensated surety, and as such cannot invoke the ancient doctrine of strictissimi juris. * * * The fnore modem rule which, according to the great weight of authority, has been applied in cases involving the legal obligations of a compensated surety, is that the departure from the guaranteed contract [in order to release the surety] must be not only material but prejudicial to the surety. * * * The case at bar does not present a departure which substantially affects the character of the risk assumed by the defendant, and for that reason it is my opinion that it cannot be regarded as a valid defense to the plaintiff’s action.

“I, therefore, find and rule that the plaintiff is entitled to recover judgment in this action in the sum of 500,000, the penal sum of the bond.”

The question presented has been fre■quently considered in judicial opinions; it is not necessary to repeat the discussions. As the District Judge said, the great weight of authority supports the view which he took. See Maryland Casualty Co. v. Dunlap, 68 F.(2d) 289 (C.C.A.1) ; New Amsterdam Casualty Co. v. United States, 67 F.(2d) 488 (C.C.A.3) ; National Surety Co. v. Lincoln County, 238 F. 705 (C.C.A.9); Atlantic T. & D. Co. v. Laurinburg, 163 F. 690 (C.C.A.4). There are many cases to the same effect in the stafS courts. In American Surety Co. v. Greek Catholic Union, 284 U.S. 563, 52 S.Ct. 235, 76 L.Ed. 490 (1932), the court assumed the law to be that a change in the obligation guaranteed must, in order to release a compensated surety, be substantial and also prejudicial to the surety; and this appears to have been so decided in Chapman v. Hoage, 56 S.Ct. 333, 80 L.Ed. -, January 6, 1936. A change so basic as to alter the general character of the undertaking would, of course, release the surety. The District Judge was well warranted in finding that no such changes had been made in this case.

Moreover, the contract, performance of which was guaranteed by the bond, expressly reserved the right to make changes in the building. The defendant contends that this provision did not permit any change in the number of apartments or of rooms. So construed, the provision practically freezes the building into the form shown on the plans at the time when the bond was made, which was clearly the very thing the parties were endeavoring to avoid. We think that the reference to the number of apartments and rooms in this clause of the contract is descriptive rather than limiting, and that the provision gives by contract a right of alteration not greatly different from that implied by law as above stated. It follows that the bond was a valid obligation attaching to the building actually erected.

Passing by certain defenses of purely technical character raising points of practice or of pleading which do not seem to us to be well founded nor to require discussion, the defendant’s next contention is that steps, taken by Moore and the American B. & M. Company with reference to the completion of the building after the default by the contractor and the owner, operated to relieve the surety from liability, or from paying anything more than nominal damages.

Moore, as trustee, went into possession and completed the building without foreclosing the mortgage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Bonding Insurance Co. v. WS Newell, Inc.
232 So. 2d 616 (Supreme Court of Alabama, 1969)
Town of Hingham v. B. J. Pentabone, Inc.
238 N.E.2d 534 (Massachusetts Supreme Judicial Court, 1968)
Maryland Casualty Co. v. First Nat. Bank of Eufaula
165 So. 2d 359 (Supreme Court of Alabama, 1964)
Future Fashions v. American Surety Co. of New York
58 F. Supp. 36 (S.D. New York, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
82 F.2d 189, 1936 U.S. App. LEXIS 2938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-moore-ca1-1936.