M. DeMatteo Construction Co. v. Board of Appeals

334 N.E.2d 51, 3 Mass. App. Ct. 446, 1975 Mass. App. LEXIS 663
CourtMassachusetts Appeals Court
DecidedSeptember 3, 1975
StatusPublished
Cited by33 cases

This text of 334 N.E.2d 51 (M. DeMatteo Construction Co. v. Board of Appeals) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. DeMatteo Construction Co. v. Board of Appeals, 334 N.E.2d 51, 3 Mass. App. Ct. 446, 1975 Mass. App. LEXIS 663 (Mass. Ct. App. 1975).

Opinion

Goodman, J.

These are three appeals; two are by the board of appeals of Hingham (zoning board) from final decrees entered in cases brought under G. L. c. 40A, § 21, in which the zoning board was the defendant, and one is by the building commissioner of Hingham (building commissioner) from a final decree entered on a bill for declaratory relief (G. L. c. 231A) in which he was the defendant. 1 The plaintiff in all three cases is the owner of a tract of land (the locus) of about 174.5 acres in Hingham subject to a subdivision plan approved by the town planning board under the Subdivision Control Law. G. L. c. 41, §§ 81K-81GG. The plaintiff is engaged in general construction and land development. The cases originate from the plaintiff’s attempt to excavate and remove earth material from the locus and particularly from parts of the locus designated as roadways on the subdivision plan.

The relevant history of these cases begins on January 20, 1964, when the plaintiff filed with the planning board a preliminary plan of a proposed subdivision for the locus. G. L. c. 41, § 81S. On August 20, 1964, the plaintiff filed a *448 definitive subdivision plan which was disapproved on October 5, 1964. The plaintiff thereupon revised its plan to conform with the recommendations of the planning board, and this revised version of the definitive plan was approved, and so endorsed, on April 5, 1965. G. L. c. 41, § 81U. The subdivision plan comprised some 270 lots and called for a number of roads totaling almost four miles; none of them had been laid out or excavated on this undeveloped tract.

Meanwhile the town was taking steps to amend its zoning by-laws governing earth removal (see Goodwin v. Board of Selectmen of Hopkinton, 358 Mass. 164, 170 [1970]). Theretofore § V-E of the by-law (hereinafter old V-E), entitled “Removal of Earth Products,” had prohibited “[t]he removal from any premises of more than three (3) cubic yards of soil, loam, sand, stone or gravel in any one year... except when required in connection with the construction of a building or street or other activity authorized by this By-Law____” 2 On March 22,1965, the town voted to replace this section of the zoning by-law with a new § V-E (hereinafter V-E [1965]) which was approved by the Attorney General on April 13, 1965. V-E (1965) required generally (with exceptions not considered pertinent by the parties) a permit from the zoning board for the removal of earth materials. More explicit standards for the grant of a permit were provided, and the conditions which the zoning board was empowered to impose were elaborated. V-E (1965) was expressly made applicable to the removal of earth materials in a proposed subdivision “even though in connection with the construction of streets shown on the plan.” See Glacier Sand & Stone Co. Inc. v. Board of Appeals of Westwood, 362 Mass. 239, 241 (1972) (a zoning by-law using the same language).

*449 Upon approval of the definitive plan by the planning board, the plaintiff removed the trees and topsoil from the areas laid out as ways on the subdivision plan, stockpiled the topsoil at several locations on the tract, and also piled up brush and tree stumps on the sides of the ways. The plaintiff had begun excavating to bring the roads to grade when the building commissioner, “several weeks” (possibly five to seven weeks) after the plaintiff had begun to work on the tract, ordered that it stop operations because it had not obtained a special permit from the board for the removal of earth materials in accordance with V-E (1965).

The plaintiff on November 16, 1965, made application to the building commissioner for a permit “for removal of [approximately 857,000 cubic yards of] earth materials from [the roads shown on the subdivision plan for the locus] ... as required to construct said roads with slopes to conform with the grades approved by the Hingham

Planning Board____” On that same date, the plaintiff’s

application was rejected by the building commissioner on the ground that approval of the zoning board was required, and the plaintiff filed an application with the zoning board. Both applications stated that the plaintiff was proceeding under V-E (1965) but “without waiving and expressly reserving all rights... with respect to the question of the validity” of V-E (1965).

On February 14, 1966, the zoning board, after hearing, filed its decision denying the application. The decision was based on a number of grounds. It found that “the proposed operation ... would be especially harmful and detrimental to the neighborhood” and that “the earth removal operation proposed here would constitute, in effect, a commercial gravel pit under the guise of a residential development.” Also the zoning board pointed out that the plaintiff had requested that the application be considered “as a whole in the form submitted” 3 and thus precluded a *450 “section-by-section development.” The zoning board found that this position, if sanctioned, would permit “the excavation of the ways and adjacent slopes without relation to the grading and development of the lots [which] would expose the neighborhood and the Town to serious detrimental consequences such as the Planning Board describes.”* ** 4

The plaintiff appealed to the Superior Court under G. L. c. 40A, § 21, attacking the zoning board’s decision as “usurp [ing] the authority of the Planning Board... in derogation of... the Subdivision Control Law” and generally as exceeding the zoning board’s authority. This case (E-1011) was heard on June 7 and 8, 1966; the Superior Court in its “Findings, Rulings and Order” referred to the limitation which the plaintiff had placed on the applications (see fn. 3) and found and ruled that the denial of a permit with respect to the proposal as presented by the plaintiff for the excavation of the ways was “not arbitrary, unreasonable or capricious in the circumstances, and [wa]s not beyond the power or authority of the Board.”

The court held, however, that “[i]t appears likely that with the imposition of reasonable conditions the proposed operation could be carried out without material adverse effect on the health or safety of persons living in the neighborhood, on the use or amenities of adjacent land, or the *451 best interests of the Town, and, by the same means, guard against the project becoming merely a commercial gravel removal operation from its inception or thereafter.” 5

Accordingly, it entered a “final decree” upholding the zoning board, but providing for recommittal of the application to the zoning board if the plaintiff should move “for further consideration without the limitation... that the application must [not] be considered...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Czyoski v. Planning Board
928 N.E.2d 987 (Massachusetts Appeals Court, 2010)
Sergi v. Planning Board
805 N.E.2d 1005 (Massachusetts Appeals Court, 2004)
Hadley v. Casper
15 Mass. L. Rptr. 107 (Massachusetts Superior Court, 2002)
Apache Building & Development, Inc. v. Town of Barre
14 Mass. L. Rptr. 160 (Massachusetts Superior Court, 2001)
Franks v. Dirico
7 Mass. L. Rptr. 377 (Massachusetts Superior Court, 1997)
Young v. Planning Board
402 Mass. 841 (Massachusetts Supreme Judicial Court, 1988)
Hahn v. Planning Board
24 Mass. App. Ct. 553 (Massachusetts Appeals Court, 1987)
Iodice v. City of Newton
491 N.E.2d 618 (Massachusetts Supreme Judicial Court, 1986)
Serody v. Serody
474 N.E.2d 1171 (Massachusetts Appeals Court, 1985)
Samson v. San-Land Development Corp.
17 Mass. App. Ct. 977 (Massachusetts Appeals Court, 1984)
Pasqualino v. Board of Appeals
440 N.E.2d 523 (Massachusetts Appeals Court, 1982)
Gamache v. Town of Acushnet
438 N.E.2d 82 (Massachusetts Appeals Court, 1982)
Arthur J. Roberts & Co. v. Delfour, Inc.
436 N.E.2d 1246 (Massachusetts Appeals Court, 1982)
Hunters Brook Realty Corp. v. Zoning Board of Appeals
436 N.E.2d 978 (Massachusetts Appeals Court, 1982)
Lynch v. Town of Groton
11 Mass. App. Ct. 1008 (Massachusetts Appeals Court, 1981)
Matteson's Case
418 N.E.2d 363 (Massachusetts Appeals Court, 1981)
Andre Hardy v. William Callahan
634 F.2d 646 (First Circuit, 1980)
Planning Board of Cambridge v. Board of Zoning Appeal of Cambridge
390 N.E.2d 1121 (Massachusetts Appeals Court, 1979)
Falcone v. ZONING BOARD OF APPEALS OF BROCKTON
389 N.E.2d 1032 (Massachusetts Appeals Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
334 N.E.2d 51, 3 Mass. App. Ct. 446, 1975 Mass. App. LEXIS 663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-dematteo-construction-co-v-board-of-appeals-massappct-1975.