Duteau v. Salvucci

115 N.E.2d 726, 330 Mass. 531, 1953 Mass. LEXIS 509
CourtMassachusetts Supreme Judicial Court
DecidedNovember 9, 1953
StatusPublished
Cited by6 cases

This text of 115 N.E.2d 726 (Duteau v. Salvucci) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duteau v. Salvucci, 115 N.E.2d 726, 330 Mass. 531, 1953 Mass. LEXIS 509 (Mass. 1953).

Opinion

Ronan, J.

This is a bill in equity brought by one Duteau under G. L. (Ter. Ed.) c. 30, § 39, as appearing in St. 1935, c. 472, § 1, to obtain payment for labor furnished and equipment supplied to the individual defendants in the performance of a contract made on July 26, 1949, by the Commonwealth with them for the construction of a section of the Mid-Cape Highway, so called, in which the officers contracting in behalf of the Commonwealth were given the fight (which they exercised) to retain a certain percentage of the amounts earned by those defendants. They also in accordance with § 39 took a bond issued by the defendant casualty company. The sum retained and the bond constitute security for the payment of those who furnished labor or supplied materials or who let for hire certain equipment in the performance of the work required to be done in the completion of the contract. Several corporations which furnished labor or supplied materials or such equipment were allowed to intervene, including Gallo Construction Co., Inc., hereinafter called Gallo. 1 The case was referred to a master whose report was confirmed, and a final decree was entered establishing the indebtedness of the individual defendants to Gallo in the amount of $19,129.26 and the right of Gallo to have recourse to the security in the amount of $6,236.02, and ordering the Commonwealth to pay this amount to *533 Gallo out of the funds the Commonwealth had amounting to $99,534.53 and to pay the balance of $93,298.51 to the casualty company. All valid claims payable out of the security have been paid except that of Gallo.

The master found that Gallo commencing on October 18, 1949, embarked upon a continuing arrangement with the individual defendants to rent to them whatever road building equipment they needed if it was not already in use by someone else. No express contract with reference thereto was made. The master states that such an agreement was implied from the uniform nature and course of their dealings which he sets forth in much detail in his report. The parties continued in accordance with this arrangement until it. terminated within sixty days before July 20, 1950, when Gallo filed a sworn statement of its claim. The allowance of this claim for $6,236.02 to be paid out of the security is not disputed by any of the parties.

In November, 1949, Gallo and the individual defendants made a contract for unloading crushed stone by Gallo at its railroad siding and transporting it to the site of the work at an agreed price. This unloading commenced on April 10, 1950, and ended on May 8, 1950. The master found that this work was performed under a separate express contract which was in no way connected with the implied continuing contractual arrangement which he found existed with reference to the rental of the Gallo equipment. He found that the individual defendants owed Gallo $10,726.55 for the unloading and transportation of the stone but that Gallo had no right to reach the security because its sworn statement filed on July 20, 1950, was more than sixty days after the contract had been performed.

The only ground of Gallo’s appeal is that it should have been allowed to share in the security also in the amount just mentioned. If we assume that the unloading and transportation of the stone which went into the construction of the public way were work of such a character that it came within the description of work for the payment of which recourse could be had to the statutory security (see *534 now G. L. [Ter. Ed.] c. 30, § 39A, inserted by St. 1951, c. 694), in order to reach the security for the satisfaction of its claim it was necessary to file a sworn statement of its claim “within sixty days after the claimant ceases to perform labor or furnish labor, materials, appliances and equipment.” G. L. (Ter. Ed.) c. 30, § 39. Mario Pandolf Co. Inc. v. Commonwealth, 303 Mass. 251. Massachusetts Gas & Electric Light Supply Co. v. Rugo Construction Co. Inc. 321 Mass. 20.

The second question arises out of an appeal by the Commonwealth from the final decree dismissing its petition to intervene.

In view of the conclusion we reach in this intervening petition, we need not decide whether the Commonwealth was a proper party intervener. See Old Colony Crushed Stone Co. v. Cronin, 276 Mass. 221, 227.

The Commonwealth contends that it is entitled to have set off or deducted from the retained cash percentage an outstanding execution amounting to $1,841.26 which the Commonwealth, through its division of employment security, obtained for “contributions” or taxes owed by the individual defendants under G. L. (Ter. Ed.) c. 151A (as revised by St. 1941, c. 685, § 1), §§ 15, 16, and 17, as amended. It makes no contention that its claim as a judgment creditor of these defendants has priority over the claim of Gallo as allowed by the final decree but it insists that its judgment for the employment security taxes has priority over the rights of the casualty company to participate in the distribution of the cash retained by the Commonwealth and therefore that the final decree was wrong in ordering the Commonwealth to pay to the casualty company all this retained fund remaining after the payment to Gallo.

The bond and the sum retained by the Commonwealth together constituted the statutory security taken by those who contracted in behalf of the Commonwealth in accordance with G. L. (Ter. Ed.) c. 30, § 39, as appearing in St. 1935, c. 472, § 1, “for payment by the contractor and subcontractors for labor performed or furnished and for mate *535 rials used or employed” in the construction or repair of public buildings or other public works. Laborers and materialmen can have no private lien upon public property, and the object of the statute is to furnish an equitable interest in the security taken by the public officers. The remedy created by this statute does not extend to the general contractor. He needs no such remedy as he deals directly with the Commonwealth to which he may look for payment. Compliance with the terms of the statute by filing seasonably sworn statements of their claims gives to laborers and materialmen an equitable interest in the security. Nash v. Commonwealth, 174 Mass. 335. Burr v. Massachusetts School for the Feeble-Minded, 197 Mass. 357. Cook Borden & Co. Inc. v. Commonwealth, 293 Mass. 174. Berkal v. M. De Matteo Construction Co. 327 Mass. 329, 332. The statutory beneficiaries for whom the security was created are laborers and materialmen, and although the assignees of their claims may have recourse to the security, Dolben v. Duncan Construction Co. 276 Mass. 242; Barry v. Duffin, 290 Mass. 398, the rights of general creditors of the principal contractor are subordinate to the rights of the statutory beneficiaries in the security until the indebtedness of the latter has been paid. Old Colony Crushed Stone Co. v. Cronin, 276 Mass. 221. Newbury v. Lincoln, 276 Mass. 445.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G.M. Builders, Inc. v. Town of Barnstable
469 N.E.2d 1281 (Massachusetts Appeals Court, 1984)
Canter v. Schlager
267 N.E.2d 492 (Massachusetts Supreme Judicial Court, 1971)
BAYER & MINGOLLA CONSTRUCTION CO. INC. v. Deschenes
205 N.E.2d 208 (Massachusetts Supreme Judicial Court, 1965)
Aetna Casualty & Surety Co. v. Harvard Trust Co.
181 N.E.2d 673 (Massachusetts Supreme Judicial Court, 1962)
JJ Struzziery Co. Inc. v. AV Taurasi Co. Inc.
165 N.E.2d 120 (Massachusetts Supreme Judicial Court, 1960)
Waite Hardware Co. v. Ardini & Pfau, Inc.
162 N.E.2d 13 (Massachusetts Supreme Judicial Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
115 N.E.2d 726, 330 Mass. 531, 1953 Mass. LEXIS 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duteau-v-salvucci-mass-1953.