Berkal v. M. De Matteo Construction Co.

98 N.E.2d 617, 327 Mass. 329
CourtMassachusetts Supreme Judicial Court
DecidedMay 4, 1951
StatusPublished
Cited by18 cases

This text of 98 N.E.2d 617 (Berkal v. M. De Matteo Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berkal v. M. De Matteo Construction Co., 98 N.E.2d 617, 327 Mass. 329 (Mass. 1951).

Opinion

Counihan, J.

This is an action of contract according to an account annexed. The defendant had a contract, hereinafter called the prime contract, with the Commonwealth acting through its department of public works, hereinafter called the department, for the construction of runways at the Logan International Airport in East Boston. With the approval of the department as required by this contract, the defendant entered into a subcontract dated October 29, 1947, with Nicholas Bianco and Francis Bianco, a partnership doing business as Bianco Brothers and hereinafter called Bianco, to furnish and haul gravel to this job. Bianco *330 did work under this subcontract. On March 19, 1948, Bianco was adjudicated a bankrupt and the plaintiff was appointed its trustee in bankruptcy. The action was tried to a judge without jury upon an “Agreed Statement of Facts,” which incorporated the prime contract, the subcontract, and two stipulations of the parties. The judge found for the plaintiff in a sum less than that which he claimed to be due, and denied certain requests for rulings of the plaintiff. The action comes here upon exceptions of the plaintiff to the finding of the judge and the denial of the requests.

It appears from the “Agreed Statement of Facts” that Bianco earned under its contract the sum of $129,835.16, and that the defendant paid or credited Bianco the sum of $120,320.66, leaving a balance of $9,514.50. Out of this balance the defendant claims a further credit of $7,946.88, leaving a balance of $1,567.62 which it agreed was due the plaintiff. The judge found for this amount with interest.

The- sum of $7,946.88 for which the defendant claims credit was paid by it on May 10, 1948, to twenty claimants who had filed claims with the department in this amount -for labor and materials furnished Bianco for this job. It is agreed by the parties to this action that all of these claims were properly filed within the sixty days required by G. L. (Ter. Ed.) c. 30, § 39, as appearing in St. 1935, c. 472, § 1, 1 and that Bianco, before bankruptcy, had verified the amount of these claims. No petitions to enforce these claims were filed in the Superior Court within the time provided by statute, c. 30, § 39. Because of this statute the defendant was required to file and did file a surety bond as security for *331 payment by it and by subcontractors for labor performed or furnished and materials used or employed in the performance of the prime contract. Article 82 of the prime contract provides that the department shall retain fifteen per cent of the estimated value of work done each month as additional security for the fulfilment of the prime contract.

All of the payments to the twenty claimants were made without the knowledge or consent of Bianco or of the plaintiff, who had previously made oral and written demand for the balance of $9,514.50 the recovery of which he now seeks in this action.

Article 57 1 of the prime contract provides that the defendant shall be required to pay all bills for labor and materials contracted by it. It further provides that the Commonwealth may retain from any moneys due the defendant at any time so much of such moneys as the Commonwealth shall be of opinion will be required to settle claims for labor performed or furnished and materials used or employed in *332 the work to be done under the contract, such claims having been filed with the department in accordance with c. SO, § 39, or the Commonwealth may make settlements of such claims and apply thereto any moneys retained under the contract. If the moneys retained are insufficient to pay the sums due under such claims, the Commonwealth may, at its discretion, pay the same and the defendant shall repay it.

In the subcontract with Bianco the prime contract was specifically referred to by name and number. Bianco expressly agreed to hold the defendant harmless from any and all claims arising out of operations under the subcontract. There was also provision that the defendant could retain a certain percentage of moneys due Bianco and pay the same to it “thirty days after the receipt of a sworn statement that all bills and other obligations have been paid in connection with this contract.” No such sworn statement was ever given the defendant, and it is evident from the filing of the twenty claims that all bills had not been paid. Bianco made no provision to hold the defendant harmless on account of these bills which the defendant was obligated to pay under the terms of the prime contract and the statute, c. 30, § 39.

The plaintiff contends that the defendant had no right to pay these claims and deduct such payment from the balance due Bianco for several reasons, but principally because no petition to enforce these claims was ever filed in the Superior Court under c. 30, § 39.

This contention of the plaintiff is without merit.

The claimants to whom the defendant made payment were undoubtedly holders of equitable liens not only on the bond furnished by the defendant under the statute but also on the moneys due the defendant but retained by the Commonwealth under the prime contract. Burr v. Commonwealth, 212 Mass. 534. The prime contract provides that, before requiring such claimants to have recourse to the bond, the Commonwealth can settle with such claimants and charge such settlements to moneys retained by it and, if this sum is not sufficient, it can demand that the de *333 fendant pay it any excess. In these circumstances it does not seem like common sense or good business practice to insist that the Commonwealth should first pay such claims and then deduct the amount of them from moneys due the defendant. These claims had been verified as to amounts by Bianco and they were undoubtedly due the claimants. To require that such claimants be forced to file petitions in the Superior Court to enforce their claims which were recognized as due by Bianco and by the defendant, seems to us to be entirely unnecessary. If the construction urged by the plaintiff be put upon the statute and the contracts, innocent parties who in good faith rendered service and furnished materials, relying upon the statute and the contracts that they would be secure in receiving payment, would unwarrantly be deprived of the use of moneys justly due them and be put to the expense of unnecessary litigation. The same is true of the defendant. Such a result would be to foster and promote unreasonable and undesirable litigation. Such litigation is not to be encouraged but is to be avoided by all reasonable means. Clark v. State Street Trust Co. 270 Mass. 140, 153. Markus v. Boston Edison Co. 317 Mass. 1, 6. It has been said of a contract, “So far as reasonably practicable it should be given a construction which will make it a rational business instrument and will effectuate what appears to have been the intention of the parties.” Bray v. Hickman, 263 Mass. 409, 412. Waldo Bros. Co. v. Platt Contracting Co. Inc. 305 Mass. 349, 355.

The purpose of the statute, c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDonald's Corp. v. Lebow Realty Trust
710 F. Supp. 385 (D. Massachusetts, 1989)
Fay, Spofford & Thorndike, Inc. v. Massachusetts Port Authority
387 N.E.2d 206 (Massachusetts Appeals Court, 1979)
FAY, SPOFFORD & THORNDIKE v. Mass. Port Auth.
387 N.E.2d 206 (Massachusetts Appeals Court, 1979)
Cataldo v. Restaurant Associates, Inc.
383 N.E.2d 518 (Massachusetts Appeals Court, 1978)
Warren Bros. Co. v. Travi
53 Mass. App. Dec. 141 (Mass. Dist. Ct., App. Div., 1974)
Canter v. Schlager
267 N.E.2d 492 (Massachusetts Supreme Judicial Court, 1971)
Blout v. Johnson
43 Mass. App. Dec. 127 (Mass. Dist. Ct., App. Div., 1969)
Thorner v. Stone
42 Mass. App. Dec. 170 (Mass. Dist. Ct., App. Div., 1969)
Ucello v. Cosentino
235 N.E.2d 44 (Massachusetts Supreme Judicial Court, 1968)
New York Central Railroad v. New England Merchants National Bank
183 N.E.2d 852 (Massachusetts Supreme Judicial Court, 1962)
JJ Struzziery Co. Inc. v. AV Taurasi Co. Inc.
165 N.E.2d 120 (Massachusetts Supreme Judicial Court, 1960)
Finn v. Massachusetts Land Corp.
17 Mass. App. Dec. 91 (Mass. Dist. Ct., App. Div., 1959)
McDermott v. Jamula
154 N.E.2d 595 (Massachusetts Supreme Judicial Court, 1958)
Botaish v. Romanos
153 N.E.2d 753 (Massachusetts Supreme Judicial Court, 1958)
Duteau v. Salvucci
115 N.E.2d 726 (Massachusetts Supreme Judicial Court, 1953)
Peña v. Eastern Sugar Associates
75 P.R. Dec. 304 (Supreme Court of Puerto Rico, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
98 N.E.2d 617, 327 Mass. 329, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berkal-v-m-de-matteo-construction-co-mass-1951.