Waldo Bros. v. Platt Contracting Co.

25 N.E.2d 770, 305 Mass. 349, 1940 Mass. LEXIS 816
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 28, 1940
StatusPublished
Cited by28 cases

This text of 25 N.E.2d 770 (Waldo Bros. v. Platt Contracting Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waldo Bros. v. Platt Contracting Co., 25 N.E.2d 770, 305 Mass. 349, 1940 Mass. LEXIS 816 (Mass. 1940).

Opinion

Cox, J.

The plaintiff brought this action of contract upon a declaration which alleges, in substance, that the parties entered into a contract whereby thé defendant agreed to pay to the plaintiff a sum equal to eighty-five per cent of all materials and labor furnished by one of the defendant’s subcontractors, one Wilgoren, “up to and including the tenth day of July, 1937, less certain payments previously made by the defendant to the plaintiff; that said payment was to be made on the eighteenth day of July, 1937,” but that the defendant had failed to pay as agreed. The answer contains a general denial, plea of payment, and, further, an allegation that if there was a contract between the parties, it was “predicated” upon the performance of “the contract of . . . Wilgoren by” him, and that he “breached his contract with the defendant and did not perform the same.” The case was referred to an auditor and thereafter was tried by a judge of the Superior Court upon the report of the auditor and other evidence. The judge found the facts as found by the auditor to be true, except as stated in his findings, denied certain requests for rulings of the plaintiff, made certain rulings, and found for the defendant. The plaintiff seasonably excepted to his refusals to rule, to two of his rulings, “and to the court’s finding for the defendant.”

On February 12, 1937, the defendant had a written contract for the erection of a theatre and stores in West [352]*352Newton. On March 5,1937, Nathan Wilgoren (hereinafter referred to as Wilgoren) entered into a contract with the defendant, as a subcontractor to furnish certain labor and materials called for by the plans and specifications for the structure that the defendant was to build, for a price of $15,750. Payments were to be made by the defendant to Wilgoren on the third and eighteenth days of each month for eighty-five per cent of the value of the labor and materials furnished up to and including the last day of the previous month and the fourteenth day of the current month, said value to be determined by the defendant; and forty-three days after the completion of all of Wilgoren’s work, he was to receive the balance “of 15 per cent of the value of labor and materials.” This contract provided that “the word ' completion ’, wherever used in this agreement shall mean completion in every form and detail of the work called for under this agreement and shall not mean substantial performance,” and that Wilgoren’s right to compensation should be based upon completion of his contract within this meaning. There was a further provision that if Wilgoren at any time neglected or failed to begin and prosecute his work with promptness and diligence, the defendant might, after twenty-four hours’ notice to him, be at liberty to “repudiate” the agreement and proceed to complete the work; and might charge any proper loss to the account of the payments therein stipulated, and charge Wilgoren with damages for nonperformance of said work. The plaintiff was not a party to either of these contracts and did not know of their provisions. On June 23, 1937, Wilgoren’s work had progressed satisfactorily and on time, but he owed the plaintiff $4,589 for materials purchased, “for the most part brick used in the work on the theatre.” On that date a conference was held, which Wilgoren and representatives of the plaintiff and defendant attended, and Wilgoren’s indebtedness to the plaintiff was discussed. In response to an inquiry, he stated that it would cost “about $2,000 for labor and about $2,000 for materials to finish the work.” After considerable discussion, the plaintiff, the defendant and Wilgoren entered into a written agreement which was exe[353]*353outed on June 24, 1937. Strange as it may seem in view of this litigation, there is a specific finding by the auditor that all the parties had discussed all matters in the contract fully on the afternoon of June 23, 1937, “and that all parties fully understood the terms thereof.”

The agreement, executed in triplicate, recites the existence of the contract between Wilgoren and the defendant, its partial performance, and that “certain material and labor still remains to be furnished and performed in order to complete” the subcontract. There are further recitals of the amount due the plaintiff from Wilgoren; that the plaintiff “has agreed and hereby does agree to furnish under the terms and conditions hereinafter set forth” additional material required by Wilgoren to complete his contract “up to but not exceeding $2,000”; that the defendant desires “said additional material be furnished by” the plaintiff and that the contract between it and Wilgoren “be performed and completed in accordance with its provisions and without unnecessary delay”; that Wilgoren assigns and transfers to the plaintiff “all sums now due and hereafter to become due from the . . . [defendant], whether for material and labor heretofore furnished and hereafter to be furnished by . . . [Wilgoren] in the performance of the . . . [subcontract] or otherwise due or to become due under said . . . [subcontract]”; that it “is hereby agreed by all parties hereto that the balance which will be due . . . [Wilgoren] upon completion of said . . . [subcontract] will be not less than $7,503”; and that Wilgoren “further agrees to complete said . . . [subcontract] forthwith, in accordance with its terms and provisions,” and to prepare and submit to the defendant forthwith a requisition for material and labor furnished by him “up to the 25th day of June, 1937 and similar requisitions for material and labor furnished up to the 10th and 25th day of each month hereafter.” Following this, the clauses appear in the contract that seem to have caused the trouble: “3. The General Contractor [defendant] agrees to pay to the Assignee [plaintiff] on the 3rd day of July a sum equal to 85% of all material and labor furnished [354]*354by the Subcontractor [Wilgoren] up to and including the 25th day of June 1937 less whatever amounts may hereafter be advanced by the . . . [defendant] to the . . . [plaintiff] for payroll payments as hereinafter provided for, and to make similar payments to the . . . [plaintiff] on the 18th day of July and on the 3rd and 18th day of each month thereafter. The . . . [defendant] further agrees to pay to the . . . [plaintiff] on the 44th day following the completion of the . . . [defendant’s] contract with . . . [the owner], or forthwith upon receipt from said . . . [owner] of the final payment due to the . . . [defendant], whichever shall first occur, the total amount due to . . . [Wilgoren] for material and labor furnished and performed by . . . [Wilgoren] on said job, which amount shall be at least $7,503 less whatever amounts may hereafter be paid by the . . . [defendant] to the . . . [plaintiff] under the terms of this agreement. 4. The . . . [defendant] further agrees to pay to the . . . [plaintiff] before ten o’clock on Friday, June 25, 1937 an amount equal to the payroll due to . . . [Wilgoren’s] employees on that date and to pay to the . .■ . [plaintiff] on or before ten o’clock a.m. of each Friday thereafter an amount equal to the payroll due on each of said dates to . . . [Wilgoren’s] employees. 5. The . . . [plaintiff] hereby agrees to furnish to . . . [Wilgoren] material (of the kind regularly carried in stock and sold by the . . . [plaintiff]) required to finish said job, up to but not exceeding a total of $2,000. 6. The . . . [plaintiff] further agrees to apply all payments received from . . . [Wilgoren] as follows: (a) Sums received from the . . . [defendant] under the provisions of Paragraph 4 supra, up to but not exceeding a total of $2,000, shall be paid forthwith by the . . . [plaintiff] to . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winchester Gables, Inc. v. Host Marriott Corp.
875 N.E.2d 527 (Massachusetts Appeals Court, 2007)
Quaboag Transfer, Inc. v. Halpin
19 Mass. L. Rptr. 257 (Massachusetts Superior Court, 2005)
Ticknor v. Micro Ink Systems Corp.
2 Mass. L. Rptr. 550 (Massachusetts Superior Court, 1994)
Bruns v. Rennebohm Drug Stores, Inc.
442 N.W.2d 591 (Court of Appeals of Wisconsin, 1989)
Tremouliaris v. Pina
505 N.E.2d 225 (Massachusetts Appeals Court, 1987)
Katz v. Cowles
3 Mass. Supp. 843 (Massachusetts District Court, 1982)
Katz v. Cowles
1982 Mass. App. Div. 213 (Mass. Dist. Ct., App. Div., 1982)
Dube v. O'Connor
3 Mass. Supp. 91 (Massachusetts District Court, 1981)
Dube v. O'Connor
1981 Mass. App. Div. 253 (Mass. Dist. Ct., App. Div., 1981)
Priestley v. Sharaf's, Inc.
344 N.E.2d 905 (Massachusetts Appeals Court, 1976)
Louis Stoico, Inc. v. Colonial Development Corp.
343 N.E.2d 872 (Massachusetts Supreme Judicial Court, 1976)
Church of God in Christ, Inc. v. Congregation Kehillath Jacob
332 N.E.2d 918 (Massachusetts Appeals Court, 1975)
P. J. Riley & Co. v. Aberthaw Construction Co.
327 N.E.2d 909 (Massachusetts Appeals Court, 1975)
Lembo v. Waters
294 N.E.2d 566 (Massachusetts Appeals Court, 1973)
Malden Door & Window Co. v. Goss
38 Mass. App. Dec. 53 (Mass. Dist. Ct., App. Div., 1967)
Deschenes v. Vidunas
29 Mass. App. Dec. 186 (Mass. Dist. Ct., App. Div., 1964)
Finn v. Massachusetts Land Corp.
17 Mass. App. Dec. 91 (Mass. Dist. Ct., App. Div., 1959)
Bitker & Gerner Co. v. Green Investment Co.
76 N.W.2d 549 (Wisconsin Supreme Court, 1956)
George v. Goldman
131 N.E.2d 772 (Massachusetts Supreme Judicial Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
25 N.E.2d 770, 305 Mass. 349, 1940 Mass. LEXIS 816, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waldo-bros-v-platt-contracting-co-mass-1940.