Vanderhoof v. Shell

72 P. 166, 72 P. 126, 42 Or. 578, 1903 Ore. LEXIS 135
CourtOregon Supreme Court
DecidedApril 20, 1903
StatusPublished
Cited by9 cases

This text of 72 P. 166 (Vanderhoof v. Shell) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vanderhoof v. Shell, 72 P. 166, 72 P. 126, 42 Or. 578, 1903 Ore. LEXIS 135 (Or. 1903).

Opinion

Mr. Justice Wolverton,

after stating the facts, delivered the opinion of the court.

The principal questions involved by this controversy are with regard to the maintenance of the suit by plaintiff without having first obtained a certificate from the architect showing the completion of the work in accordance with the contract, and whether plaintiff was entitled to additional time for the completion of the work unless the same was claimed by him and allowed by the architect, and, if so, what amount.

1. Under the testimony adduced, it clearly appears, by a decided preponderance, that the defendant accepted the work as having been performed in due compliance with the undertaking of the plaintiff. On the 14th of October, plaintiff and defendant, accompanied by the architect and Cline, went through the building, inspecting it carefully for the purpose of ascertaining wherein, if in any respect, the requirements of the specifications had not been observed. A list of the defects was prepared and assented to by all the parties, showing what was yet necessary to be done to render the work acceptable. At the time certain parties wishing to rent portions of the building were ready to move in, and a controversy arose relative to the surrender of the keys by plaintiff, so as to admit *583 of its occupancy by them; he refusing to yield up the keys unless a settlement could be had. This was adjusted, however, by defendant accepting the work, or, as it was then denominated, the building, in all respects, except as to such defects as were noted in the list, whereupon the keys were surrendered and the tenants allowed to move in. There is some dispute among the witnesses in regard to the understanding reached by the parties at the time. The principal inharmony, however, arises from the testimony of defendant, who states that he agreed, “when those things were all remedied —defects in the building” — that he would accept. His architect, however, corroborates the plaintiff and Cline, who testify that defendant then agreed that he would ‘ ‘ accept the building up to this list, ’ ’ in consideration of the keys being surrendered. So that we are clear that there was an understanding concluded at the time that defendant accepted the work so far as completed, or the building, with the exception of the minor details mentioned in the list.

Subsequently, on October 22d, there was a meeting of the parties at the office of Mr. Martin, the architect, for the express purpose of settling all difficulties between them; Martin, Cline, Finnegan, and Kavanaugh being present. All these persons testify to what was done there, and are practically of one accord — that the list of defects prepared on the 14th was gone over, item by item, to determine whether the contractor had done the work as it was therein specified that he should. As to'many of the items, defendant frankly assented that there had been a compliance. As to some he was in doubt, but, being-advised by the architect that they had also been conformed to, he assented; and as to none did he insist that there had not been a performance. It seems, therefore, that it was finally concurred in by the defendant that everything had been done in this regard that he required, and plaintiff had agreed to do, on the 14th, as specified in the list. All the persons present, except the defendant and Kavanaugh, virtually agree in their testimony that defendant then finally accepted the building as having been constructed in full accord with plaintiff’s under *584 taking, but that a dispute arose as to who was responsible for the delay in completing the work, and when it was suggested by the plaintiff that each party had contributed about equally thereto, and that he was willing to call it even, the defendant replied that he would go home and sleep over it, and would notify the architect, who could tell the plaintiff what he would do, and thus the conference ended. Defendant testifies that he never accepted the building at that time, and Kavanaugh, who was his attorney and looked after his interests, says “that that was just what he intended not to do, ’ ’ and it may be possible that such was his purpose at the conference. It must be conceded, however, that these two witnesses are at cross-purposes with the other three, who had equal opportunities for knowing just what took place at the meeting. But, however we may look upon the disagreement of the witnesses as to this particular contention of the defendant, it must follow as a logical deduction, too plain for dispute, that, when it was agreed that the work specified in the list of odds and ends had been completed, an acceptance resulted from the understanding had on the 14th of the month, so that the acceptance of the work or building by defendant was a matter concluded, in any event, on the latter date. In this connection, it should be said of Martin’s testimony that he did not entirely concede that plaintiff had attended to all items as specified in the list, but noted some few minor repairs and changes that remained to be made, and signified their willingness to trust the plaintiff to attend to them, and that the acceptance of the building was agreed to by defendant notwithstanding. At this meeting the architect made out a statement of the account as it then stood beween the parties. It was written in pencil, and inspected and considered by. them without objection, except as it would be affected by the dispute as to the delay in completing the work. A copy in ink was given to each party the next day. This statement exhibited the contract price, with additions and deductions allowed for extra work and work of which the contractor was relieved, and payments made, showing a balance due the contractor of $2,489.38. On October 25th an *585 additional $2,000 was paid, leaving due a balance of $489.38, which is the amount sued for, plus $25, which plaintiff claims for extra work subsequently peifformed in putting in a couple of columns. Martin testifies that he made this out as a final statement, and so characterized it. It is also shown, and there is practically no dispute in regard thereto, that the plaintiff at that meeting requested Martin to give him his final certificate, so that the matter might be then fully adjusted, but that it was withheld by reason of the. defendant’s claim of damages for delay in completing the work as per the contract. Such a certificate has never been delivered, although written demand was made on Martin for it on December 4th following.

It is competent for parties to stipulate in a contract of the nature of the one here in controversy that the contractor shall procure the certificate of an architect that the work has been performed or the building completed in accordance with his undertaking, as a condition precedent to the payment of any installment or the amount finally to become due. Generally speaking, no action or suit can be maintained therefor against the owner until the condition is performed or its requirements waived. The contract becomes a law between the parties in this respect, as they expressly agree that the amount due for the service shall be established by the certificate of the architect ; and it throws upon the contractor the burden of producing the particular kind of evidence required by the mutual stipulations of the parties concerning it, unless the circumstances are such that the certificate has been waived, or that the contractor is unable to produce it through no fault of his.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shepherd v. Gass
488 P.2d 1180 (Oregon Supreme Court, 1971)
Waldo Bros. v. Platt Contracting Co.
25 N.E.2d 770 (Massachusetts Supreme Judicial Court, 1940)
Rutherford v. Kahler
298 S.W. 9 (Supreme Court of Arkansas, 1927)
Hoskins v. Powder Land & Irr. Co.
176 P. 124 (Oregon Supreme Court, 1918)
Leiter v. Dwyer Plumbing Co.
133 P. 1180 (Oregon Supreme Court, 1913)
Pippy v. Winslow
125 P. 298 (Oregon Supreme Court, 1912)
Wallis v. Inhabitants of Wenham
90 N.E. 396 (Massachusetts Supreme Judicial Court, 1910)
Huber v. St. Joseph's Hospital
83 P. 768 (Idaho Supreme Court, 1905)
Livesley v. Johnston
76 P. 13 (Oregon Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
72 P. 166, 72 P. 126, 42 Or. 578, 1903 Ore. LEXIS 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vanderhoof-v-shell-or-1903.