Hoskins v. Powder Land & Irr. Co.

176 P. 124, 90 Or. 217, 1918 Ore. LEXIS 198
CourtOregon Supreme Court
DecidedNovember 26, 1918
StatusPublished
Cited by18 cases

This text of 176 P. 124 (Hoskins v. Powder Land & Irr. Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoskins v. Powder Land & Irr. Co., 176 P. 124, 90 Or. 217, 1918 Ore. LEXIS 198 (Or. 1918).

Opinion

BURNETT, J.

At the hearing before the Circuit Court it was agreed that the following items of the plaintiff’s claim were the only ones disputed:

[221]*221Concrete piers, 4.86 cubic yards, at $15.60 per yard ................................. $75.25

Excavation and placing earth in the embankment for reservoir dam, 32,691 cubic yards, at 35^ per yard................11,441.85

"Work and labor for August, 1916, in addition to above .................... 123.44

The defendants admit $121.95 of this last item, challenging thereof only $1.49, but dispute the following:

For work, labor and material furnished for

September, 1916, in addition to the above. $899.81 Work and labor for October, 1916, in addition to the above ......................... 460.32

Work and labor and material furnished for November, 1916, in addition to the above 416.75

1, 2. We note that the complaint attempts to plead tiiodification of the contract in three respects: 1. The waiver of the time in which the work should be completed. 2. That on or about September 5, 1916, the agent of the defendants in whose name the contract was made was to furnish powder, caps and fuse and pay for clearing' and grubbing the borrow-pits, plus 10 per cent of the cost. 3. That during the progress of the undertaking at the special instance and request of W. A. Steward, the agent of the defendants, the plaintiff performed extra work and furnished extra material in the construction of the dam and reservoir not included in the terms of the written contract, for which the defendants agreed to pay the plaintiff. Taking these in inverse order, we discern from the contract, which was admitted in evidence without objection, that:

“No extra work shall be done without written orders from W. A. Steward or his engineer. Extra work or material of a character not provided for in the specifications if ordered in writing by the engineer, [222]*222will be paid for at actual necessary cost, as determined by the engineer, plus 10 per cent for profit, superintendence, and general expenses. The cost of extra work shall include all materials, labor and fuel furnished by the contractor; but shall not include use ' of tools or machinery, office expenses, general superintendence, or other general expenses. Demand for payment must be made in writing by the contractor promptly upon the completion of the extra work or furnishing of the extra material. The account including the same must be accompanied by the certificate of the engineer stating that such work has been satisfactorily performed or such material furnished, and stating the amount to be allowed therefor. The contractor shall, when requested by the engineer, furnish itemized statements of the cost of the work ordered, and give the engineer access to accounts, bills, and vouchers relating thereto.”

If ,the work mentioned in the third modification, as pleaded, related to the erection of the dam in any way, it was already provided for in the excerpt just quoted from the written contract, so that the allegation does not amount to a modification. As to the expense for powder, caps and the clearing and grubbing of the borrow-pits, the consideration for the alleged agreement of Steward to pay for the same as averred in the complaint is that:

“The plaintiff thereupon agreed to and with said Steward, agent for defendant * * to proceed with the construction of the said reservoir and dam and to finish and complete the same as soon as possible, and without unnecessary delay. ’J

Recalling that at that very time the plaintiff was under contract to finish the identical dam, we read from 13 C. J. 351:

“A promise to do what the promisor is already bound to do cannot be a consideration, for if a person gets nothing in return for his promise but that to [223]*223which he is already legally entitled, the consideration • is unreal. Therefore, as a general rule, the performance of, or promise to perform, an existing legal obligation is not a valid consideration. This legal obligation may arise from the law independent of contract, or it may arise from a subsisting contract»1’

After discussion of the obligation at law, the author, speaking of subsisting contractual obligations, continues on page 353:

“The promise of a person to carry out a subsisting contract with the promisee or the performance of such contractual duty is clearly no consideration, as he is doing no more than he was already obliged to do, and hence has sustained no detriment, nor has the other party to the contract obtained any benefit. Thus a promise to pay additional compensation for the performance by the -promisee of a contract which the promisee is already under obligation to the promisor to perform is without consideration.”

See, also, Nine v. Starr, 8 Or. 49; Myers v. Livesley, 56 Or. 383, 389 (107 Pac. 476, 108 Pac. 121); Hillman v. Young, 64 Or. 73 (127 Pac. 793, 129 Pac. 124); Muir v. Morris, 80 Or. 378 (154 Pac. 117, 157 Pac. 785).

The testimony of the plaintiff in this connection is in substance that after he had entered upon the performance of the undertaking he saw that he would be unible to complete the contract except at a loss, and therefore went to Steward and offered him $1,000 if the latter would release the plaintiff from the work, but that Steward declined the offer, whereupon it was agreed that Steward should pay the plaintiff for clearing the borrow-pits and the like, as stated, in consideration of which the plaintiff agreed to complete the dam. The reason he avowed for thus approaching Steward was that he was compelled to haul earth to make the fill of the dam farther than he had [224]*224originally supposed. In that respect the admitted con tract contains this provision:

“The party of the first part hereby agrees that he has, in person, or by his agent, examined the premises and line'of dam on which the work is to be performed, and his knowledge of the conditions surrounding the same is gained firmn such observations and not from representations of the engineer or - the party of the second part.”

In the specifications attached to and made a part of the contract and introduee'd into evidence by the plaintiff appears the following:

“Borrow-pits and classification of material: — The engineer will designate the borrow-pits from which all materials for the fills shall be obtained. The contractor shall strip the borrow-pits to the satisfaction of the engineer and the cost of such stripping shall be included in the price bid for the fill. , The classification of the materials from the borrow-pits shall be under the supervision of the engineer who will, at all times, direct at what points it shall be placed on the dam. The price per cubic yard, bid by the 'Contractor, for fill shall include all plowing or loosening in the borrow-pits, loading, hauling, unloading, spreading, wetting and rolling, and no allowance whatever will be made for overhaul. The average length of haul will be approximately one thousand (1,000) feet from the borrow-pits to the dam. All payments for materials placed in the fill shall be on the basis of actual volume measured in the dam after settlement of the fill has ceased.” • \

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barinaga v. JP Morgan Chase & Co.
749 F. Supp. 2d 1164 (D. Oregon, 2010)
King v. Suniga
634 P.2d 812 (Court of Appeals of Oregon, 1981)
B & D Investment Corp. v. Petticord
617 P.2d 276 (Court of Appeals of Oregon, 1980)
Krieg v. UNION PACIFIC LAND RESOURCES CORPORATION
525 P.2d 48 (Oregon Supreme Court, 1974)
McGrath v. Electrical Construction Co.
370 P.2d 231 (Oregon Supreme Court, 1961)
Collins v. POST
362 P.2d 325 (Oregon Supreme Court, 1961)
Enco, Inc. v. F. C. Russell Co.
311 P.2d 737 (Oregon Supreme Court, 1957)
State Highway Commission v. Green-Boots Const. Co.
1947 OK 221 (Supreme Court of Oklahoma, 1947)
Portland Mortgage Co. v. Horenstein
91 P.2d 533 (Oregon Supreme Court, 1939)
Ollman v. Huddleston
64 P.2d 97 (New Mexico Supreme Court, 1937)
Kansas City Bridge Co. v. State
250 N.W. 343 (South Dakota Supreme Court, 1933)
Stoop v. United States National Bank
250 P. 760 (Oregon Supreme Court, 1926)
Lovell v. Potts
207 P. 1006 (Oregon Supreme Court, 1924)
Jeffries v. Pankow
223 P. 745 (Oregon Supreme Court, 1924)
Bagley v. Bagley
222 P. 722 (Oregon Supreme Court, 1924)
Conroy Bros. v. J. J. Duggan & Brother
17 Ohio App. 429 (Ohio Court of Appeals, 1923)
Feenaughty v. Beall
178 P. 600 (Oregon Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
176 P. 124, 90 Or. 217, 1918 Ore. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoskins-v-powder-land-irr-co-or-1918.