B & D Investment Corp. v. Petticord

617 P.2d 276, 48 Or. App. 345, 1980 Ore. App. LEXIS 3495
CourtCourt of Appeals of Oregon
DecidedSeptember 22, 1980
Docket77-6-414, CA 14774
StatusPublished
Cited by10 cases

This text of 617 P.2d 276 (B & D Investment Corp. v. Petticord) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B & D Investment Corp. v. Petticord, 617 P.2d 276, 48 Or. App. 345, 1980 Ore. App. LEXIS 3495 (Or. Ct. App. 1980).

Opinion

*347 CAMPBELL, J.

Plaintiff B & D Investment Corporation (B & D) contracted in December 1976 with defendants James and Doris Petticord, husband and wife, to build a residence according to plans and specifications supplied by the Petticords and prepared by their architect, Donald Cloyd. Soon after B & D began construction, serious disagreements between the parties arose, and in April 1977, when the house was approximately 25 percent complete, the Petticords terminated B & D’s right to continue work and took exclusive possession of the premises. B & D filed suit to recover the reasonable value of work performed prior to the alleged wrongful termination, and to foreclose a construction lien in that amount. Defendants 1 appeal from a trial court order entering judgment against the Petticords for $42,114.10 plus interest, costs, and a $15,000 attorney’s fee, impressing the house with a construction lien, and ordering the lien foreclosed. We review de novo. Ralph Allen, Inc. v. Lumpkin, 279 Or 71, 566 P2d 872 (1977).

Defendants first argue that the trial court erred in denying their demurrer to plaintiff’s complaint on the grounds that it failed to state facts sufficient to constitute a cause of suit. The pertinent portions of the complaint state:

"On or about December 27, 1976, defendants Petticord entered into a contract with claimant directing plaintiff to perform certain labor and furnish certain materials for the construction of a dwelling on said lot in accordance with certain plans and specifications represented by defendants Petticord to be sufficient and adequate for building.
"Thereafter, plaintiff furnished materials and labor from December 27,1976, until on or about April 25, 1977, when defendants Petticord wrongfully terminated the contract, resulting in a rescission thereof on or about April 25, 1977. The reasonable value of claimant’s labor, materials and equipment was and is the sum of $67,146.93.
*348 "Plaintiff has demanded payment of the aforesaid sum of $67,146.93, but defendants Petticord have failed and refused to pay said sum except for the sum of $19,936.96. Defendants Petticord now owe plaintiff the sum of $47,209.97, together with interest thereon at 6 percent per annum from April 25,1977.”

Defendants did not demur to the complaint until the close of the evidence. Therefore, the complaint is construed liberally in favor of the pleader. Sinclair v. Barker, 236 Or 599, 390 P2d 321 (1964).

Due to our resolution of this case, it is sufficient that we now conclude that the complaint alleged facts sufficient to state a cause of action in quantum meruit. See Bastian v. Henderson, 277 Or 539, 561 P2d 595 (1977). Cf. Ward v. Town Tavern et al, 191 Or 1, 35, 228 P2d 216 (1951).

We turn next to defendants’ contention that the trial court erred in finding that B & D did not breach or anticipatorily repudiate the contract. Defendants first argue that B & D is not entitled to enforce a lien because it had not substantially performed its contractual duties as of April 25, 1977, the date of termination. Among the failures by B & D pointed to by the Petticords is that the construction was contrary in material respects to the plans and specifications.

When a contractor makes intentional and substantial deviations from the contract plans and specifications without the owner’s consent, he is not entitled to foreclose a construction lien. Walker the Weeper v. Commercial Eng. Corp., 283 Or 407, 584 P2d 268 (1978); Shepherd v. Gass, 260 Or 84, 488 P2d 1180 (1971); Culver v. Rendahl et ux, 211 Or 682, 318 P2d 275 (1957); Birkemeier v. Knobel, 149 Or 292, 40 P2d 694 (1935); Pippy v. Winslow, 62 Or 219, 125 P 298 (1912). B & D does not disagree that in building the house it deviated substantially from the plans and specifications. Plaintiff contends, however, that the changes were necessitated by defects in the plans and specifications, and were authorized by Cloyd, who acted as the Petticords’ agent. In its memorandum opinion, the trial court stated:

*349 "The plans, specifications and cost estimate material submitted by Mr. Cloyd to the plaintiff were inaccurate and erroneous to the extent that major modifications of the location of the home on the lot was necessary, resulting in a major change in the foundation and cement work with a major increase in costs. Mr. Cloyd, together with plaintiff, examined this problem and orally agreed upon going ahead with construction with alterations of the specifications and plot plan to correct the errors in design. Written change order signed by the Pettycords [sic] was not required since Mr. Cloyd was acting as supervisor and agent for them, and the changes were of such magnitude that Cloyd’s action constituted a waiver of such written change order.”

After reviewing the 1200-page transcript and approximately 100 exhibits, we agree that the plans and specifications were inaccurate in major respects, including (1) incorrect depiction of the location of a tree which was one of the crucial reference points in determining the placement of the house, and (2) an inaccurate topographical map, showing the land less steep in the planned location of the house than it actually is, and showing the contour lines of the land running roughly parallel to the long axis of the house at its proposed location rather than at a significant angle. We also find that as a result of these defects in the plans and specifications it was necessary to alter the placement of the house on the lot and to make major changes in the design of the foundation and retaining wall, all of which caused a substantial increase in the cost of the construction over that originally contemplated.

The contract, which was a standard form building contract prepared by defendants’ attorney, provided that "All of said work is to be done under the supervision of owner who, for brevity hereinafter is designated as 'supervisor.’ ” (In a previous proposed contract on an identical form, prepared by Donald Giddings, president of B & D, Giddings had designated himself as "supervisor.”) Article V of the contract provided:

*350 "No eliminations or alterations shall be made in the work except upon written order of the supervisor. Should any such eliminations or alterations require new plans or specifications, the owner shall supply the same at his expense. Should any of said eliminations or alterations require an adjustment of the agreed price (upward or downward) such adjustment shall be evidenced by the written agreement of the parties. Should they not be able so to agree, the work shall go on nevertheless under the order mentioned above and the determination of the proper adjustment shall be referred to arbitration as hereinafter provided.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emmert Industrial Corp. v. Sanders
883 P.2d 1304 (Court of Appeals of Oregon, 1994)
Bowers v. Winitzki
730 P.2d 1253 (Court of Appeals of Oregon, 1986)
Western Engineers, Inc. v. Bullier & Bullier, Inc.
717 P.2d 644 (Court of Appeals of Oregon, 1986)
B & D Investment Corp. v. Petticord
689 P.2d 1052 (Court of Appeals of Oregon, 1984)
Myers v. Oregon Shores Associates, Ltd.
687 P.2d 159 (Court of Appeals of Oregon, 1984)
Barker v. Parker
662 P.2d 779 (Court of Appeals of Oregon, 1983)
Dale's Sand & Gravel Co. v. Westwood Construction Co.
661 P.2d 1378 (Court of Appeals of Oregon, 1983)
Oshatz v. Goltz
637 P.2d 628 (Court of Appeals of Oregon, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
617 P.2d 276, 48 Or. App. 345, 1980 Ore. App. LEXIS 3495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-d-investment-corp-v-petticord-orctapp-1980.