Bastian v. Henderson

561 P.2d 595, 277 Or. 539, 1977 Ore. LEXIS 1169
CourtOregon Supreme Court
DecidedMarch 17, 1977
DocketTC 74-789-L, SC 24382
StatusPublished
Cited by3 cases

This text of 561 P.2d 595 (Bastian v. Henderson) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bastian v. Henderson, 561 P.2d 595, 277 Or. 539, 1977 Ore. LEXIS 1169 (Or. 1977).

Opinion

TONGUE, J.

This is an action by a building contractor against the owner and tenant of a building in Grants Pass for the reasonable value of work, labor and materials furnished by plaintiff at the request of the defendants in the construction of an addition to the building and in remodeling work on the building. The case was tried before the court, without a jury. Judgment was entered against both defendants in the sum of $6,497.44. It was ordered, however, that plaintiff be estopped from enforcing the judgment against the owner, defendant Henderson. The tenant, Ruemar, Inc., appeals. We affirm.1

Plaintiff contends that defendant Ruemar’s five assignments of error fail to comply with the requirements of Rule 6.18 of the Rules of Procedure of this court.2 We hold, however, that the first four of the assignments of error are sufficient to raise the follow[542]*542ing questions, which we believe to be decisive in this case:3

(1) Did the complaint allege sufficient facts to support a cause of action in quantum meruit by plaintiff (as a building contractor), against defendant Ruemar (as a tenant)?
(2) Was there sufficient evidence to support the judgment? More specifically:
(a) Was there substantial evidence to support the findings by the court "[t]hat there was no express or written contract between Plaintiff and Defendants for such work, labor and materials”?
(b) Was there substantial evidence to support the finding by the court that such "work, labor and materials were furnished” at the instance and request of Defendants (including defendant Ruemar)?
(c) Was there substantial evidence to support the finding by the court that the reasonable value of such work, labor and materials was the sum of $13,829.82, of which $6,497.44 remained due, owing and unpaid?
(3) Did the court err in failing to sustain defendant Ruemar’s equitable defense of estoppel?

Summary of the facts.

After reviewing the testimony and exhibits we find that the facts which we believe to be material to these issues are accurately stated in the following excerpts from the written opinion by the trial court: [543]*543Plaintiff Bastian advice from time to time on a method of charging for his services.

[542]*542"* * * plaintiff is a general contractor who performed work on the building in question. The Defendant Thomas W. Henderson is the owner of the building and the lessor of the property to the Defendant Ruemar, Inc. For all practical purposes the Defendant Ruemar, Inc. is George Thompson. Mr. Thompson is a certified public accountant and a member of an accounting firm in Grants Pass. As such accountant, he performed accounting services for the Plaintiff Bastian and gave the

[543]*543"Apparently the Defendant Thompson also kept books for the former operation of the property involved known as Taco Tree. For some reason Mr. Thompson became interested in the operation of the restaurant and concluded that certain changes would have to be made in order to make the operation profitable. He desired to build onto the building by adding a family dining room and discussed the matter with the Plaintiff Bastian.

"Thompson apparently was interested in a building known as the A and W Root Beer for architectural design and construction. He approached Mr. Henderson to see if Mr. Henderson would finance the remodeling of the building and take the cost of construction out in additional rent. Mr. Henderson agreed to finance the improvement to the extent of $8,000, although there was discussion of expending the sum of $8,500.

"The figure of $8,000 or $8,500 was apparently derived from a sheet of paper which Mr. Bastian furnished to Mr. Thompson and which was admitted in evidence as Plaintiffs Exhibit 56. This was an estimate sheet in which the figure of $7,955 was totaled.

"It is the contention of Thompson that there was a contract entered into between him and the Plaintiff Bastian to do the contemplated work for the sum of $8,000 based on this estimate sheet, and Mr. Henderson agreed to the figure of $8,000. No plans or specifications of any kind were prepared except for a sketch drawn for Bastian which, according to Plaintiff, was to indicate the contour of the roof line. * * * Thompson assumed that he had a firm contract with Bastian for not more than $8,000 based upon the rough estimate which the Plaintiff Bastian furnished him. Bastian’s position is that the estimate sheet was only an estimate, and since there were no details the contract was one for the reasonable value of the work actually performed.

******

"As it turned out, the total amount of the services performed by the Plaintiff was the sum of $13,829.82, of which he has received the sum of $7,332.38, leaving a balance due of $6,497.44 for which he seeks recovery.

"* * * From the very first it was found that things [544]*544would be different than planned as it was necessary to pour an entirely new slab of concrete. From time to time various additions were made to the plans, such as block planters, screens for sheltering the garbage area, divider walls, paneling of blocks, light fixtures which were selected by Mrs. Thompson and approved by Mr. Thompson. Also it is apparent to the Court that a considerable amount of work in the kitchen not contemplated by any phase of the contract or estimates was performed on the orders of Mrs. Thompson, and it appears that Mr. Thompson gave Mrs. Thompson carte blanche for whatever she felt it was necessary to do. In addition, air conditioning and heat were installed and many changes and additions were made which could not possibly have been contemplated.
* * * *
"The Defendant Henderson did not enter into any of the negotiations for the construction of the building. He simply approved the plans submitted by Thompson and the price given to him by Thompson and agreed to pay a certain portion thereof. * * *”

1. The sufficiency of the complaint.

Defendant Ruemar contends, by its second assignment of error, that as a tenant, rather than as an owner, it cannot be liable in an action of quantum meruit "concerning the reasonable value of improvements to real property”; that Ruemar only "requested plaintiff to submit a bid for the work”; and that plaintiff knew that Henderson was owner of the property, citing Porter Const. Co. v. Berry et al, 136 Or 80, 298 P 179 (1931).

The complaint in this case alleges that

"* * * Plaintiff, at the special instance and request of the Defendant, THOMAS W. HENDERSON and RUEMAR, INC., furnished work, labor and materials to be used, and which were used, in the repair and remodeling of, and the addition to, the improvement located at 201 S.E. Park Street, Grants Pass, Oregon.” (Emphasis added)

There was no demurrer to this complaint.

[545]*545 The contention by defendant Ruemar that it was a tenant, rather than owner, of the building, raises a question of fact, and one that goes outside the allegations of the complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kizer Excavating v. Stout Building Contractors
525 P.3d 883 (Court of Appeals of Oregon, 2023)
In re Klemp
418 P.3d 733 (Oregon Supreme Court, 2018)
B & D Investment Corp. v. Petticord
617 P.2d 276 (Court of Appeals of Oregon, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
561 P.2d 595, 277 Or. 539, 1977 Ore. LEXIS 1169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bastian-v-henderson-or-1977.