Kizer Excavating v. Stout Building Contractors

525 P.3d 883, 324 Or. App. 211
CourtCourt of Appeals of Oregon
DecidedFebruary 15, 2023
DocketA177168
StatusPublished
Cited by10 cases

This text of 525 P.3d 883 (Kizer Excavating v. Stout Building Contractors) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kizer Excavating v. Stout Building Contractors, 525 P.3d 883, 324 Or. App. 211 (Or. Ct. App. 2023).

Opinion

Argued and submitted December 23, 2022; affirmed on appeal, reversed and remanded on cross-appeal February 15; on appellant’s petition for reconsideration filed February 28, and respondent’s response filed March 8, reconsideration allowed by opinion May 3, 2023 See 325 Or App 642, 529 P3d 1024 (2023)

KIZER EXCAVATING CO., an Oregon corporation, Plaintiff-Appellant Cross-Respondent, v. STOUT BUILDING CONTRACTORS, LLC, a Utah limited liability company, Defendant-Respondent Cross-Appellant. Clackamas County Circuit Court 20CV17226; A177168 525 P3d 883

Plaintiff Kizer Excavating Co., an excavation subcontractor, brought claims for breach of a subcontract and quantum meruit against the general contractor, defendant Stout Building Contractors, LLC, seeking payment for excavation work for which plaintiff sought to be compensated through a change order request that defendant had rejected. Plaintiff appeals from a judgment in its favor on its quan- tum meruit claim, assigning error to the trial court’s rejection of its request for attorney fees. Defendant cross-appeals, assigning error to the trial court’s legal determination that plaintiff could recover on its quantum meruit claim in view of the existence of the express subcontract governing the parties’ agreement, as well as to the court’s denial of its own request for attorney fees on plaintiff’s claim for breach of the subcontract, on which defendant prevailed. Held: The parties had an express contract that governed the work to be performed, and the trial court therefore erred in determining that plaintiff could recover on its quantum meruit claim. Because defendant prevailed on plaintiff’s breach of contract claim as well as on the quantum meruit claim, defendant was the prevailing party. And because the parties had an agreement that provided for attorney fees to the prevailing party in a claim based on their subcontract, the court erred rejecting defendant’s request for attorney fees. Affirmed on appeal; reversed and remanded on cross-appeal.

Susie L. Norby, Judge. Paul B. Barton argued the cause for appellant-cross- respondent. Also on the briefs were Alexander Graven and Olsen Barton LLC. 212 Kizer Excavating v. Stout Building Contractors

Holly E. Pettit argued the cause for respondent-cross- appellant. Also on the briefs were Peter J. Viteznik and Kilmer Voorhees & Laurick, P.C. Before Egan, Presiding Judge, and Kamins, Judge, and Hadlock, Judge pro tempore. EGAN, P. J. Affirmed on appeal; reversed and remanded on cross- appeal. Cite as 324 Or App 211 (2023) 213

EGAN, P. J.

This appeal concerns an action arising out the excavation of a commercial construction project in Dallas, Oregon. Plaintiff Kizer Excavating Co., the excavation sub- contractor, appeals from a judgment in its favor on its quantum meruit claim, assigning error to the trial court’s rejection of its request for attorney fees. Defendant Stout Building Contractors, LLC, the general contractor, cross- appeals, assigning error to the trial court’s legal determina- tion that plaintiff could recover on its quantum meruit claim as well as to the court’s denial of its own request for attorney fees on plaintiff’s claim of breach of an express subcontract, on which it prevailed. We conclude that the trial court erred in entering judgment for plaintiff on its quantum meruit claim, and therefore erred in determining that plaintiff was the prevailing party and in rejecting defendant’s request for attorney fees on plaintiff’s claim of breach of the par- ties’ subcontract. Accordingly, we reverse and remand the judgment.

The relevant facts for purposes of the issues raised on appeal and cross-appeal are largely undisputed: The parties executed a subcontract for plaintiff to provide labor and materials for, among other services, the excavation nec- essary for the construction of a Jiffy Lube service station in Dallas, Oregon. The subcontract incorporated plaintiff’s “Proposal and Breakdown Sheet,” which estimated that plaintiff would excavate 500 cubic yards of fill from the prop- erty. The subcontract provided that plaintiff would complete the work for $139,077.

In completing the work, plaintiff excavated 3,290 cubic yards of fill, a significant increase over plaintiff’s estimate. The parties agree that the discrepancy was due in part to a clerical error by plaintiff: the Proposal and Breakdown Sheet should have stated that plaintiff would excavate 1,500 cubic yards of dirt, rather than 500 cubic yards. The parties disagreed as to the cause of the remaining disparity. The trial court found that the disparity was due in part to an erroneous survey and in part to unanticipated water. 214 Kizer Excavating v. Stout Building Contractors

Plaintiff sought to be compensated for the additional work through an untimely change order. After defendant rejected the change order, plaintiff initiated this litigation, seeking damages for, among other claims, breach of con- tract and quantum meruit. For its breach of contract claim, plaintiff’s complaint alleged that, pursuant to the parties’ valid and enforceable subcontract, plaintiff performed labor for and provided materials to defendant, and that defen- dant breached the subcontract by failing to pay plaintiff the amount of $36,602.72 for work performed under the sub- contract. For its separate quantum meruit claim, plaintiff alleged that it had provided the additional excavation ser- vices for defendant’s benefit and at defendant’s request, that it would be unjust to allow defendant to retain the benefit of those services without paying plaintiff, and that plaintiff was entitled to be compensated in the amount of $36,602.72 for labor and materials. Defendant admitted that the parties had a valid and enforceable subcontract but denied that it owed plaintiff the additional amount either under the subcontract or on a quantum meruit theory. Defendant alleged as an affirma- tive defense that “[p]laintiff’s damages, if any, are the result of Plaintiff’s failure to perform in accordance with contract documents.” Plaintiff’s theory at trial was that it was entitled to be compensated for the additional excavation work under the terms of the subcontract, but that, if the subcontract was deemed to be unenforceable, it was entitled to be com- pensated on a theory of quantum meruit. The subcontract did not include an attorney fee pro- vision. During the litigation but before trial, the parties exe- cuted an “Agreement Regarding Attorney Fees,” in which they agreed to amend the subcontract “to address the sole issue of the recovery of attorney fees and costs by the pre- vailing party in disputes arising under the Subcontract.” The parties agreed: “The prevailing party in any litigation, or other mutu- ally agreed upon dispute resolution proceeding, between Contractor and Subcontractor shall be entitled to the recov- ery of its reasonable attorney fees and costs.” Cite as 324 Or App 211 (2023) 215

The attorney fee agreement was retroactive to the date of the execution of the subcontract. After a lengthy trial, the trial court issued a letter opinion with detailed findings. The trial court determined that both parties had fulfilled their obligations under the terms of the subcontract, and it therefore rejected plaintiff’s claim that defendant had breached the subcontract. As for plaintiff’s quantum meruit claim, the trial court concluded that, when defendant rejected the change order relating to the additional excavation, that work became “extracon- tractual,” outside the consensual agreement of the parties, but that plaintiff had a reasonable expectation that defen- dant would pay for the work. Thus, the court concluded, on a quantum meruit theory, plaintiff was entitled to be com- pensated for that work, under an “implied-in-fact” contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seabold Construction v. Koz 2211 SW 4th Avenue
344 Or. App. 688 (Court of Appeals of Oregon, 2025)
Employer Solutions Staffing Group v. SAIF
343 Or. App. 206 (Court of Appeals of Oregon, 2025)
McAllister Construction Co. v. Liu
343 Or. App. 53 (Court of Appeals of Oregon, 2025)
Wecker v. Salem Clinic, P.C.
529 P.3d 991 (Court of Appeals of Oregon, 2023)
Kizer Excavating v. Stout Building Contractors
529 P.3d 1024 (Court of Appeals of Oregon, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
525 P.3d 883, 324 Or. App. 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kizer-excavating-v-stout-building-contractors-orctapp-2023.